Jobs Delayed From The March 2019 Letting

 
 
Last Update: Monday, February 11, 2019

Jan |Feb |Mar |Apr |May |Jun |Jul |Aug |Sep |Oct |Nov |Dec

Seq No County Project ID CCSJ Highway Reason for change
3026 Denton STP 2019(798)HES 2250-02-017 SL 88 Late PS.&E
3034 Webb STP 2019(607)HES 0018-03-058 IH 35 District Funds Consideration
3216 Chamber STP 1802(599)HES 1024-01-072 FM 565 Late PS.&E
3236 Webb STP 2019(608)HES 0086-14-073 US 59 District Funds Consideration
3038 Scurry STP 2019(642) 1529-02-010 FM 1607 Pending AFA
3010 Upshur C 520-5-50 0520-05-050 SH 155 Project Acceleration
3036 Karnes NH 2019(669) 0100-05-001 US 181 Late PS.&E
3027 Calhoun STP 2019(637) 0515-03-051 FM 1090 Unclear Utilities
3010 Concho STP 2000(292)TE 0070-03-049 US 87 Environmental Clearance (dist)
3042 Knox STP 2019(772) 0133-03-047 US 82 Environmental Clearance (dist)
3018 Chamber STP 2018(850) 1024-01-042 FM 565 Environmental Clearance (dist)
3209 Gaines NH 2019(612) 0228-02-048 US 62 Statewide Fund. Considerations

 