Jobs Delayed From The October 2018 Letting

 
 
Last Update: Tuesday, September 25, 2018

Jan |Feb |Mar |Apr |May |Jun |Jul |Aug |Sep |Oct |Nov |Dec

Seq No County Project ID CCSJ Highway Reason for change
002 BASTROP NH 2019(106) 0114-05-037 US 290 due to unclear utilities
009 HIDALGO STP 2019(086)TP 0921-02-409 CS Project switched to Local Let
012 HENDERSON NH 2019(089) 0164-01-072 SH 31 due to late PS&E
204 HIDALGO STP 2019(085) 0342-01-074 SH 107 STIP revision required
213 COLORADO BR 2019(096) 0446-03-047 US 90A Moved to 03/2019
221 NUECES STP 2019(082) 0916-00-087 VA add to the new 2019 District wide Seal Coat program projects
227 TRAVIS STP 2019(337)HES 2210-01-007 RM 2322 due to project acceleration

 