Jobs Delayed From The November 2018 Letting

 
 
Last Update: Monday, October 15, 2018

Jan |Feb |Mar |Apr |May |Jun |Jul |Aug |Sep |Oct |Nov |Dec

Seq No County Project ID CCSJ Highway Reason for change
033 El Paso NH 2019(063) 0374-02-097 US 62 rescheduled back Oct. 2018
201 CHAMBERS NH 2018(953) 0508-02-120 IH 10 late P.S.&E
202 EL PASO NH 2019(168) 2552-02-028 SL 375 unclear utilities
212 CHAMBERS STP 2019(187)MM 2242-02-022 FM 2354 STIP
217 SOMERVELL STP 2019(208)HES 0259-02-051 US 67 environment clearance (Dist)
002 PECOS NH 1802(325) 0076-01-029 US 67 late P.S.&E (outside source)
201 CHAMBERS STP 2018(953)MM 0508-02-120 IH 10 late P.S.&E
223 HARRIS NH 1802(596) 0177-07-114 IH 69 PS&E revision being required

 
Off Site Icon Electronic State Business Daily