1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3101932 MGR.NO. 054 PAGE 001 CONT 6208 SEC 64 JOB 001 RES ENGR PETERS, CARL PROJ SUP - 620864001 HWY US0259 552 US 259 NORTH DAINGERF CNTY MORRIS DIST 19 CONTRACT PRICE $ 7,440.00 REPORT DATE 04/14/2011 08.16.46 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2010 TO MAR 31,2011 EST NO 013 & FINAL CAMP COUNTY SERVICE INDUSTRIES 10865 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 01, 2010 TIME COMPUTED FROM APR 01, 2010 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 334 334 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 11 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 03/31/11 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3101932 MGR.NO. 054 PAGE 001 CONT 6208 SEC 64 JOB 001 RES ENGR PETERS, CARL PROJ SUP - 620864001 HWY US0259 552 US 259 NORTH DAINGERF CNTY MORRIS DIST 19 CONTRACT PRICE $ 7,440.00 REPORT DATE 04/14/2011 08.16.47 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2010 TO MAR 31,2011 EST NO 013 & FINAL CAMP COUNTY SERVICE INDUSTRIES 10865 DIST. 19 COUNTY MORRIS CONTROL 6208-64-001 PROJECT SUP - 620864001 HIGHWAY US0259 0LIMITS- VARIOUS . 0TYPE OF WORK- GROUNDS MIANTENANCE 0 0005 PREPARED BY ROBERT H. RATCLIFF, P.E. 0 0055 GROUNDS MAINTENANCE - DAINGERFIELD NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7013 GROUNDS MAINTENANCE CYC 24.000 19.000 310.000 5,890.00 0 SUBTOTAL BID ITEMS $ 5,890.00 0 TOTAL AMOUNT WORK DONE GROUNDS MAINTENANCE - DAINGERFIELD $ 5,890.00 0 TOTAL AMOUNT WORK DONE CONTROL 6208-64-001 $ 5,890.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3101932 MGR.NO. 054 PAGE 001 CONT 6208 SEC 64 JOB 001 RES ENGR PETERS, CARL PROJ SUP - 620864001 HWY US0259 552 US 259 NORTH DAINGERF CNTY MORRIS DIST 19 CONTRACT PRICE $ 7,440.00 REPORT DATE 04/14/2011 08.16.47 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2010 TO MAR 31,2011 EST NO 013 & FINAL CAMP COUNTY SERVICE INDUSTRIES 10865 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN APR 1 , 2010 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED MAR 31 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6208-64-001 SUP - 620864001 19 US0259 MORRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7013 GROUNDS MAINTENANCE CYC 24.000 19.000 310.000 5,890.00 0 SUBTOTAL BID ITEMS $ 5,890.00 0 CONTRACT TOTAL ALL ITEMS $ 5,890.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3101932 MGR.NO. 054 PAGE 001 CONT 6208 SEC 64 JOB 001 RES ENGR PETERS, CARL PROJ SUP - 620864001 HWY US0259 552 US 259 NORTH DAINGERF CNTY MORRIS DIST 19 CONTRACT PRICE $ 7,440.00 REPORT DATE 04/14/2011 08.16.47 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2010 TO MAR 31,2011 EST NO 013 & FINAL CAMP COUNTY SERVICE INDUSTRIES 10865 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 172 SUP - 620864001 6208-64-001 5,890.00 .00 5,890.00 .00 .00 5,890.00 5,890.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 5,890.00 .00 5,890.00 .00 .00 5,890.00 5,890.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3101932 MGR.NO. 054 PAGE 001 CONT 6208 SEC 64 JOB 001 RES ENGR PETERS, CARL PROJ SUP - 620864001 HWY US0259 552 US 259 NORTH DAINGERF CNTY MORRIS DIST 19 CONTRACT PRICE $ 7,440.00 REPORT DATE 04/14/2011 08.16.47 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2010 TO MAR 31,2011 EST NO 013 & FINAL CAMP COUNTY SERVICE INDUSTRIES 10865 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6208-64-001 SUP - 620864001 19 US0259 MORRIS -LIMITS - VARIOUS . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 5,890.00