1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3131932 MGR.NO. 053 PAGE 001 CONT 6255 SEC 05 JOB 001 RES ENGR SHARP, MICHAEL PROJ SUP - 625505001 HWY SH0049 24522 SH 49 JEFFERSON CNTY MARION DIST 19 CONTRACT PRICE $ 15,582.00 REPORT DATE 05/13/2014 16.48.09 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO MAR 31,2014 EST NO 013 & FINAL SDR & ASSOC. INC. 15541 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 01, 2013 TIME COMPUTED FROM APR 01, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 334 334 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 14 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 03/31/14 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3131932 MGR.NO. 053 PAGE 001 CONT 6255 SEC 05 JOB 001 RES ENGR SHARP, MICHAEL PROJ SUP - 625505001 HWY SH0049 24522 SH 49 JEFFERSON CNTY MARION DIST 19 CONTRACT PRICE $ 15,582.00 REPORT DATE 05/13/2014 16.48.10 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO MAR 31,2014 EST NO 013 & FINAL SDR & ASSOC. INC. 15541 DIST. 19 COUNTY MARION CONTROL 6255-05-001 PROJECT SUP - 625505001 HIGHWAY SH0049 0LIMITS- VARIOUS . 0TYPE OF WORK- GROUNDS MAINTENANCE 0 0005 PREPARED BY ROBERT H. RATCLIFF, P.E. 0 0055 GOUNDS MAINTENANCE - JEFFERSON MAIN NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7013 GROUNDS MAINTENANCE CYC 24.000 10.000 649.250 6,492.50 0 SUBTOTAL BID ITEMS $ 6,492.50 0 TOTAL AMOUNT WORK DONE GOUNDS MAINTENANCE - JEFFERSON MAIN $ 6,492.50 0 TOTAL AMOUNT WORK DONE CONTROL 6255-05-001 $ 6,492.50 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3131932 MGR.NO. 053 PAGE 001 CONT 6255 SEC 05 JOB 001 RES ENGR SHARP, MICHAEL PROJ SUP - 625505001 HWY SH0049 24522 SH 49 JEFFERSON CNTY MARION DIST 19 CONTRACT PRICE $ 15,582.00 REPORT DATE 05/13/2014 16.48.10 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO MAR 31,2014 EST NO 013 & FINAL SDR & ASSOC. INC. 15541 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN APR 1 , 2013 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED MAR 31 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6255-05-001 SUP - 625505001 19 SH0049 MARION - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7013 GROUNDS MAINTENANCE CYC 24.000 10.000 649.250 6,492.50 0 SUBTOTAL BID ITEMS $ 6,492.50 0 CONTRACT TOTAL ALL ITEMS $ 6,492.50 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3131932 MGR.NO. 053 PAGE 001 CONT 6255 SEC 05 JOB 001 RES ENGR SHARP, MICHAEL PROJ SUP - 625505001 HWY SH0049 24522 SH 49 JEFFERSON CNTY MARION DIST 19 CONTRACT PRICE $ 15,582.00 REPORT DATE 05/13/2014 16.48.10 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO MAR 31,2014 EST NO 013 & FINAL SDR & ASSOC. INC. 15541 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 155 SUP - 625505001 6255-05-001 6,492.50 .00 6,492.50 .00 .00 6,492.50 6,492.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 6,492.50 .00 6,492.50 .00 .00 6,492.50 6,492.50 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3131932 MGR.NO. 053 PAGE 001 CONT 6255 SEC 05 JOB 001 RES ENGR SHARP, MICHAEL PROJ SUP - 625505001 HWY SH0049 24522 SH 49 JEFFERSON CNTY MARION DIST 19 CONTRACT PRICE $ 15,582.00 REPORT DATE 05/13/2014 16.48.10 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO MAR 31,2014 EST NO 013 & FINAL SDR & ASSOC. INC. 15541 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6255-05-001 SUP - 625505001 19 SH0049 MARION -LIMITS - VARIOUS . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 6,492.50