1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4114030 MGR.NO. 770 PAGE 001 CONT 6222 SEC 66 JOB 001 RES ENGR CHOATE, LOWELL PROJ RMC - 622266001 HWY IH0035 7901 N IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 2,420,000.00 REPORT DATE 07/18/2012 15.35.38 CONTRACTOR D. I. J. CONSTRUCTION, INC. 440 EST PERIOD JUN 01,2011 TO JUN 01,2012 EST NO 013 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 01, 2011 TIME COMPUTED FROM JUN 01, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 240 366 212 154 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUN 12 1 1 WORK COMPLETED AND ACCEPTED TOTAL DAYS ALLOWED = 240 DATE WORK COMPLETED 06/01/12 DAYS CHARGED TO DATE = 212 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 800 0 LIQUIDATED DAMAGES 0 DAYS AT $ 800 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 367 212 155 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4114030 MGR.NO. 770 PAGE 001 CONT 6222 SEC 66 JOB 001 RES ENGR CHOATE, LOWELL PROJ RMC - 622266001 HWY IH0035 7901 N IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 2,420,000.00 REPORT DATE 07/18/2012 15.35.39 CONTRACTOR D. I. J. CONSTRUCTION, INC. 440 EST PERIOD JUN 01,2011 TO JUN 01,2012 EST NO 013 & FINAL DIST. 14 COUNTY TRAVIS CONTROL 6222-66-001 PROJECT RMC - 622266001 HIGHWAY IH0035 0LIMITS- VAROUS LOCATIONS IN THE AUSTIN DISTRICT . 0TYPE OF WORK- PAVEMENT MARKINGS AND MARKERS 0 0005 PREPARED BY LESLIE MILLER 1-20-2011 0 0055 ROUTINE MAINTENANCE NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0666 REFL PAV MRK TY I (W) 4" (BRK)(060MIL) LF 250,000.000 275,369.000 .200 55,073.80 0060 0666 ADJ EST QUANTITY TO DATE 295,000.000 0065 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 75,000.000 129,909.000 .320 41,570.88 0065 0666 ADJ EST QUANTITY TO DATE 125,000.000 0070 0666 REFL PAV MRK TY I (W) 4" (SLD)(060MIL) LF 2,000,000.000 2,435,854.000 .180 438,453.72 0070 0666 ADJ EST QUANTITY TO DATE 2,075,000.000 0075 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 800,000.000 1,857,614.000 .320 594,436.48 0075 0666 ADJ EST QUANTITY TO DATE 845,000.000 0080 0666 REFL PAV MRK TY I (W) 8" (SLD)(060MIL) LF 70,000.000 257,837.000 .380 97,978.06 0080 0666 ADJ EST QUANTITY TO DATE 110,000.000 0085 0666 REFL PAV MRK TY I (W) 12"(SLD)(100MIL) LF 15,000.000 10,658.000 2.350 25,046.30 0090 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 10,000.000 9,696.000 5.000 48,480.00 0090 0666 ADJ EST QUANTITY TO DATE 10,500.000 0095 0666 REFL PAV MRK TY I (W) (ARROW) (100MIL) EA 120.000 240.000 105.000 25,200.00 0095 0666 ADJ EST QUANTITY TO DATE 140.000 0100 0666 REFL PAV MRK TY I(W)(DBL ARROW)(100MIL) EA 50.000 61.000 130.000 7,930.00 0105 0666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 50.000 19.000 380.000 7,220.00 0110 0666 REFL PAV MRK TY I(W) (SYMBOL) (100MIL) EA 50.000 0.000 115.000 .00 1 0115 0666 REFL PAV MRK TY I (W) (WORD) (100MIL) EA 100.000 215.000 135.000 29,025.00 0115 0666 ADJ EST QUANTITY TO DATE 120.000 0120 0666 REF PAV MRK TY I(W)18"(YLD TRI)(100MIL) EA 300.000 78.000 17.000 1,326.00 0125 0666 REF PAV MRK TY I(W)36"(YLD TRI)(100MIL) EA 300.000 83.000 38.000 3,154.00 0130 0666 REFL PAV MRK TY I (Y) 4" (BRK)(060MIL) LF 500,000.000 180,170.000 .190 34,232.30 0130 0666 ADJ EST QUANTITY TO DATE 575,000.000 0135 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 250,000.000 128,676.000 .335 43,106.46 0135 0666 ADJ EST QUANTITY TO DATE 325,000.000 0140 0666 REFL PAV MRK TY I (Y) 4" (SLD)(060MIL) LF 3,000,000.000 2,649,599.000 .190 503,423.81 0140 0666 ADJ EST QUANTITY TO DATE 3,700,000.000 0145 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 1,000,000.000 2,032,436.000 .330 670,703.88 0145 0666 ADJ EST QUANTITY TO DATE 1,150,000.000 0150 0666 REFL PAV MRK TY I (Y) 12"(SLD)(100MIL) LF 3,000.000 428.000 2.350 1,005.80 0155 0666 REFL PAV MRK TY I(W)(LEGENDS)(100MIL) SF 2,000.000 0.000 1.600 .00 0160 0668 PREFAB PAV MRK (TY C)(MULTI)(SHIELD) EA 4.000 0.000 1,500.000 .00 0165 0672 REFL PAV MRKR TY I-C (HV) EA 36,000.000 4,085.000 2.500 10,212.50 0165 0672 ADJ EST QUANTITY TO DATE 43,500.000 0170 0672 REFL PAV MRKR TY II-A-A (HV) EA 85,000.000 32,896.000 2.580 84,871.68 0170 0672 ADJ EST QUANTITY TO DATE 95,000.000 0175 0672 REFL PAV MRKR TY II-C-R (HV) EA 4,000.000 5,406.000 5.000 27,030.00 0180 0677 ELIM EXT PAV MRK & MRKS (12") LF 5,000.000 790.000 1.500 1,185.00 0185 0677 ELIM EXT PAV MRK & MRKS (24") LF 5,000.000 100.000 3.000 300.00 0190 8020 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 50,000.000 12,546.000 .870 10,915.02 0195 8020 REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) LF 50,000.000 500.000 .880 440.00 0200 0666 REF PAV MRK TY I (BLACK)6"(BRK)(100MIL) LF 10,000.000 0.000 1.000 .00 0 SUBTOTAL BID ITEMS $ 2,762,320.69 0 MATERIAL ON HAND 0 LINE MATRL. NO MATERIAL DESCRIPTION UNIT QUANTITY % INV UNIT PRICE AMOUNT NO. PRICE ALLOWED($) ($) 0 0205 775 ENNIS WHITE THERMO TON 0.000 100 1,225.000 .00 0210 776 SHERMAN WIILIAMS WHITE TON 0.000 100 1,435.000 .00 0215 777 ENNIS YELLOW THERMO TON 0.000 100 1,225.000 .00 1 0220 778 SHERWIN WILLIAMS YELLOW TON 0.000 100 1,435.000 .00 0 TOTAL AMOUNT WORK DONE ROUTINE MAINTENANCE $ 2,762,320.69 0 TOTAL AMOUNT WORK DONE CONTROL 6222-66-001 $ 2,762,320.69 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4114030 MGR.NO. 770 PAGE 001 CONT 6222 SEC 66 JOB 001 RES ENGR CHOATE, LOWELL PROJ RMC - 622266001 HWY IH0035 7901 N IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 2,420,000.00 REPORT DATE 07/18/2012 15.35.39 CONTRACTOR D. I. J. CONSTRUCTION, INC. 440 EST PERIOD JUN 01,2011 TO JUN 01,2012 EST NO 013 & FINAL 0*********************************************************************************************************************************** -LIMITS - VAROUS LOCATIONS IN THE AUSTIN DISTRICT 0 . DATE WORK BEGAN JUN 1 , 2011 WORKING DAYS USED 212 PERCENT COMPLETE 100.00 PERCENT TIME USED 88.30 DATE COMPLETED JUN 1 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6222-66-001 RMC - 622266001 14 IH0035 TRAVIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0666 REFL PAV MRK TY I (W) 4" (BRK)(060MIL) LF 250,000.000 275,369.000 .200 55,073.80 0666 ADJ EST QUANTITY TO DATE 295,000.000 0666 REFL PAV MRK TY I (W) 4" (BRK)(100MIL) LF 75,000.000 129,909.000 .320 41,570.88 0666 ADJ EST QUANTITY TO DATE 125,000.000 0666 REFL PAV MRK TY I (W) 4" (SLD)(060MIL) LF 2,000,000.000 2,435,854.000 .180 438,453.72 0666 ADJ EST QUANTITY TO DATE 2,075,000.000 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 800,000.000 1,857,614.000 .320 594,436.48 0666 ADJ EST QUANTITY TO DATE 845,000.000 0666 REFL PAV MRK TY I (W) 8" (SLD)(060MIL) LF 70,000.000 257,837.000 .380 97,978.06 0666 ADJ EST QUANTITY TO DATE 110,000.000 0666 REFL PAV MRK TY I (W) 12"(SLD)(100MIL) LF 15,000.000 10,658.000 2.350 25,046.30 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 10,000.000 9,696.000 5.000 48,480.00 0666 ADJ EST QUANTITY TO DATE 10,500.000 0666 REFL PAV MRK TY I (W) (ARROW) (100MIL) EA 120.000 240.000 105.000 25,200.00 0666 ADJ EST QUANTITY TO DATE 140.000 0666 REFL PAV MRK TY I(W)(DBL ARROW)(100MIL) EA 50.000 61.000 130.000 7,930.00 10666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 50.000 19.000 380.000 7,220.00 0666 REFL PAV MRK TY I (W) (WORD) (100MIL) EA 100.000 215.000 135.000 29,025.00 0666 ADJ EST QUANTITY TO DATE 120.000 0666 REF PAV MRK TY I(W)18"(YLD TRI)(100MIL) EA 300.000 78.000 17.000 1,326.00 0666 REF PAV MRK TY I(W)36"(YLD TRI)(100MIL) EA 300.000 83.000 38.000 3,154.00 0666 REFL PAV MRK TY I (Y) 4" (BRK)(060MIL) LF 500,000.000 180,170.000 .190 34,232.30 0666 ADJ EST QUANTITY TO DATE 575,000.000 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 250,000.000 128,676.000 .335 43,106.46 0666 ADJ EST QUANTITY TO DATE 325,000.000 0666 REFL PAV MRK TY I (Y) 4" (SLD)(060MIL) LF 3,000,000.000 2,649,599.000 .190 503,423.81 0666 ADJ EST QUANTITY TO DATE 3,700,000.000 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 1,000,000.000 2,032,436.000 .330 670,703.88 0666 ADJ EST QUANTITY TO DATE 1,150,000.000 0666 REFL PAV MRK TY I (Y) 12"(SLD)(100MIL) LF 3,000.000 428.000 2.350 1,005.80 0672 REFL PAV MRKR TY I-C (HV) EA 36,000.000 4,085.000 2.500 10,212.50 0672 ADJ EST QUANTITY TO DATE 43,500.000 0672 REFL PAV MRKR TY II-A-A (HV) EA 85,000.000 32,896.000 2.580 84,871.68 0672 ADJ EST QUANTITY TO DATE 95,000.000 0672 REFL PAV MRKR TY II-C-R (HV) EA 4,000.000 5,406.000 5.000 27,030.00 0677 ELIM EXT PAV MRK & MRKS (12") LF 5,000.000 790.000 1.500 1,185.00 0677 ELIM EXT PAV MRK & MRKS (24") LF 5,000.000 100.000 3.000 300.00 8020 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 50,000.000 12,546.000 .870 10,915.02 8020 REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) LF 50,000.000 500.000 .880 440.00 0 SUBTOTAL BID ITEMS $ 2,762,320.69 0 CONTRACT TOTAL ALL ITEMS $ 2,762,320.69 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4114030 MGR.NO. 770 PAGE 001 CONT 6222 SEC 66 JOB 001 RES ENGR CHOATE, LOWELL PROJ RMC - 622266001 HWY IH0035 7901 N IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 2,420,000.00 REPORT DATE 07/18/2012 15.35.39 CONTRACTOR D. I. J. CONSTRUCTION, INC. 440 EST PERIOD JUN 01,2011 TO JUN 01,2012 EST NO 013 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 227 RMC - 622266001 6222-66-001 2,762,320.69 .00 2,762,320.69 .00 .00 2,762,320.69 2,762,320.69 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 2,762,320.69 .00 2,762,320.69 .00 .00 2,762,320.69 2,762,320.69 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4114030 MGR.NO. 770 PAGE 001 CONT 6222 SEC 66 JOB 001 RES ENGR CHOATE, LOWELL PROJ RMC - 622266001 HWY IH0035 7901 N IH 35 AUSTIN CNTY TRAVIS DIST 14 CONTRACT PRICE $ 2,420,000.00 REPORT DATE 07/18/2012 15.35.40 CONTRACTOR D. I. J. CONSTRUCTION, INC. 440 EST PERIOD JUN 01,2011 TO JUN 01,2012 EST NO 013 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6222-66-001 RMC - 622266001 14 IH0035 TRAVIS -LIMITS - VAROUS LOCATIONS IN THE AUSTIN DISTRICT . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 2,762,320.69