1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5134006 MGR.NO. 050 PAGE 001 CONT 6247 SEC 63 JOB 001 RES ENGR DILL, ROY PROJ RMC - 624763001 HWY FM1984 174 SH 21 EAST BASTROP CNTY CALDWELL DIST 14 CONTRACT PRICE $ 448,144.43 REPORT DATE 12/04/2013 15.38.16 CONTRACTOR HUNTER INDUSTRIES, LTD. 9560 EST PERIOD SEP 25,2013 TO NOV 30,2013 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 25, 2013 TIME COMPUTED FROM OCT 02, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 17 37 10 27 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 13 1 1 30 DAY PERFORMANCE PERIOD ON BUTTONS TOTAL DAYS ALLOWED = 17 2 1 30 DAY PERFORMANCE PERIOD ON BUTTONS DATE WORK COMPLETED 3 1 30 DAY PERFORMANCE PERIOD ON BUTTONS DAYS CHARGED TO DATE = 10 4 1 30 DAY PERFORMANCE PERIOD ON BUTTONS ASSESSED LIQ DAMAGES = 0 5 1 30 DAY PERFORMANCE PERIOD ON BUTTONS LIQ DAMAGE RATE $ 590 6 1 30 DAY PERFORMANCE PERIOD ON BUTTONS 7 1 30 DAY PERFORMANCE PERIOD ON BUTTONS LIQUIDATED DAMAGES 8 1 30 DAY PERFORMANCE PERIOD ON BUTTONS 0 DAYS AT $ 590 PER DAY 9 1 30 DAY PERFORMANCE PERIOD ON BUTTONS TOTAL = $ .00 10 1 30 DAY PERFORMANCE PERIOD ON BUTTONS 11 1 30 DAY PERFORMANCE PERIOD ON BUTTONS CERTIFIED AS CORRECT AND 12 1 30 DAY PERFORMANCE PERIOD ON BUTTONS ONE COPY HAS BEEN GIVEN 13 1 30 DAY PERFORMANCE PERIOD ON BUTTONS TO THE CONTRACTOR 14 1 30 DAY PERFORMANCE PERIOD ON BUTTONS 15 1 WORK COMPLETED AND ACCEPTED 16 1 WORK COMPLETED AND ACCEPTED ---------------------------- 17 1 WORK COMPLETED AND ACCEPTED AREA/PROJECT ENGINEER 18 1 WORK COMPLETED AND ACCEPTED 19 1 WORK COMPLETED AND ACCEPTED 20 1 WORK COMPLETED AND ACCEPTED 21 1 WORK COMPLETED AND ACCEPTED 22 1 WORK COMPLETED AND ACCEPTED 23 1 WORK COMPLETED AND ACCEPTED 24 1 WORK COMPLETED AND ACCEPTED 25 1 WORK COMPLETED AND ACCEPTED 26 1 WORK COMPLETED AND ACCEPTED 27 1 WORK COMPLETED AND ACCEPTED 28 1 WORK COMPLETED AND ACCEPTED 29 1 WORK COMPLETED AND ACCEPTED 30 1 WORK COMPLETED AND ACCEPTED 0 ----- ----- ----- 67 10 57 0 SATURDAY 0 SUNDAY 0 HOLIDAY 14 30 DAY PERFORMANCE PERIOD ON BUTTONS 16 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5134006 MGR.NO. 050 PAGE 001 CONT 6247 SEC 63 JOB 001 RES ENGR DILL, ROY PROJ RMC - 624763001 HWY FM1984 174 SH 21 EAST BASTROP CNTY CALDWELL DIST 14 CONTRACT PRICE $ 448,144.43 REPORT DATE 12/04/2013 15.38.17 CONTRACTOR HUNTER INDUSTRIES, LTD. 9560 EST PERIOD SEP 25,2013 TO NOV 30,2013 EST NO 003 & FINAL DIST. 14 COUNTY CALDWELL CONTROL 6247-63-001 PROJECT RMC - 624763001 HIGHWAY FM1984 0LIMITS- VARIOUS LOCATIONS IN CALDWELL COUNTY 0TYPE OF WORK- SEAL COAT 0 0050 ROADWAY NET LENGTH 7.129 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0055 0316 ASPH (TIER II) GAL 44,026.000 41,040.000 3.730 153,079.20 0060 0316 AGGR (TIER II) CY 958.000 962.750 61.950 59,642.36 0065 3267 D-GR HMA(SQ) TY-D PG64-22 TON 1,948.000 1,973.060 68.640 135,430.84 0070 0500 MOBILIZATION LS 1.000 1.000 42,856.500 42,856.50 0075 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 1,986.200 1,986.20 0080 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 1,695.000 1,559.000 1.510 2,354.09 0085 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 75,282.000 72,548.000 .280 20,313.44 0090 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 84.000 65.000 11.000 715.00 0095 0666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 2.000 2.000 165.000 330.00 0100 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 4,706.000 4,790.000 .280 1,341.20 0105 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 47,052.000 41,871.000 .280 11,723.88 0110 0666 REF PAV MRK TY II (W) 4" (SLD) LF 15,056.000 0.000 .160 .00 0115 0666 REF PAV MRK TY II (Y) 4" (BRK) LF 942.000 0.000 .160 .00 0120 0666 REF PAV MRK TY II (Y) 4" (SLD) LF 9,410.000 0.000 .160 .00 0125 0672 REFL PAV MRKR TY II-A-A EA 825.000 747.000 2.880 2,151.36 0130 1122 TEMPORARY SEDIMENT CONTROL FENCE INSTLL LF 10.000 0.000 10.000 .00 0135 1122 TEMPORARY SEDIMENT CONTROL FENCE REMOVE LF 10.000 0.000 10.000 .00 0 SUBTOTAL BID ITEMS $ 431,924.07 1 TOTAL AMOUNT WORK DONE ROADWAY $ 431,924.07 0 TOTAL AMOUNT WORK DONE CONTROL 6247-63-001 $ 431,924.07 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5134006 MGR.NO. 050 PAGE 001 CONT 6247 SEC 63 JOB 001 RES ENGR DILL, ROY PROJ RMC - 624763001 HWY FM1984 174 SH 21 EAST BASTROP CNTY CALDWELL DIST 14 CONTRACT PRICE $ 448,144.43 REPORT DATE 12/04/2013 15.38.17 CONTRACTOR HUNTER INDUSTRIES, LTD. 9560 EST PERIOD SEP 25,2013 TO NOV 30,2013 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN 0 CALDWELL COUNTY DATE WORK BEGAN SEP 25, 2013 WORKING DAYS USED 10 PERCENT COMPLETE 96.38 PERCENT TIME USED 58.80 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6247-63-001 RMC - 624763001 14 FM1984 CALDWELL - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0316 ASPH (TIER II) GAL 44,026.000 41,040.000 3.730 153,079.20 0316 AGGR (TIER II) CY 958.000 962.750 61.950 59,642.36 0500 MOBILIZATION LS 1.000 1.000 42,856.500 42,856.50 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 1,986.200 1,986.20 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 1,695.000 1,559.000 1.510 2,354.09 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 75,282.000 72,548.000 .280 20,313.44 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 84.000 65.000 11.000 715.00 0666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 2.000 2.000 165.000 330.00 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 4,706.000 4,790.000 .280 1,341.20 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 47,052.000 41,871.000 .280 11,723.88 0672 REFL PAV MRKR TY II-A-A EA 825.000 747.000 2.880 2,151.36 3267 D-GR HMA(SQ) TY-D PG64-22 TON 1,948.000 1,973.060 68.640 135,430.84 0 SUBTOTAL BID ITEMS $ 431,924.07 0 CONTRACT TOTAL ALL ITEMS $ 431,924.07 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5134006 MGR.NO. 050 PAGE 001 CONT 6247 SEC 63 JOB 001 RES ENGR DILL, ROY PROJ RMC - 624763001 HWY FM1984 174 SH 21 EAST BASTROP CNTY CALDWELL DIST 14 CONTRACT PRICE $ 448,144.43 REPORT DATE 12/04/2013 15.38.17 CONTRACTOR HUNTER INDUSTRIES, LTD. 9560 EST PERIOD SEP 25,2013 TO NOV 30,2013 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 28 RMC - 624763001 6247-63-001 431,924.07 .00 431,924.07 .00 .00 431,924.07 427,638.42 4,285.65 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 431,924.07 .00 431,924.07 .00 .00 431,924.07 427,638.42 4,285.65 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5134006 MGR.NO. 050 PAGE 001 CONT 6247 SEC 63 JOB 001 RES ENGR DILL, ROY PROJ RMC - 624763001 HWY FM1984 174 SH 21 EAST BASTROP CNTY CALDWELL DIST 14 CONTRACT PRICE $ 448,144.43 REPORT DATE 12/04/2013 15.38.17 CONTRACTOR HUNTER INDUSTRIES, LTD. 9560 EST PERIOD SEP 25,2013 TO NOV 30,2013 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6247-63-001 RMC - 624763001 14 FM1984 CALDWELL -LIMITS - VARIOUS LOCATIONS IN CALDWELL COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 70 0500 MOBILIZATION LS 1.000 0.100 42,856.500 4,285.65 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 4,285.65 0 TOTAL AMOUNT WORK DONE TO DATE - $ 431,924.07