1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5112003 MGR.NO. 007 PAGE 001 CONT 6209 SEC 57 JOB 001 RES ENGR COX, MARK PROJ RMC - 620957001 HWY IH0010 3128 SH 62N ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 254,993.50 REPORT DATE 04/12/2013 07.35.58 CONTRACTOR P-VILLE, INCORPORATED 6856 EST PERIOD JUN 08,2011 TO APR 30,2013 EST NO 019 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 08, 2011 TIME COMPUTED FROM JUN 08, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 114 542 39 503 BROUGHT FORWARD ADDL DAYS GRANTED = 0 APR 13 1 1 WORK SUSPENDED TOTAL DAYS ALLOWED = 114 2 1 WORK SUSPENDED DATE WORK COMPLETED 04/04/13 3 1 WORK SUSPENDED DAYS CHARGED TO DATE = 29 4 1 WORK COMPLETED AND ACCEPTED ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 546 39 507 0 SATURDAY 0 SUNDAY 0 HOLIDAY 3 WORK SUSPENDED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5112003 MGR.NO. 007 PAGE 001 CONT 6209 SEC 57 JOB 001 RES ENGR COX, MARK PROJ RMC - 620957001 HWY IH0010 3128 SH 62N ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 254,993.50 REPORT DATE 04/12/2013 07.35.58 CONTRACTOR P-VILLE, INCORPORATED 6856 EST PERIOD JUN 08,2011 TO APR 30,2013 EST NO 019 & FINAL DIST. 20 COUNTY ORANGE CONTROL 6209-57-001 PROJECT RMC - 620957001 HIGHWAY IH0010 0LIMITS- JEFFERSON COUNTY LINE LOUISIANA STATE LINE 0TYPE OF WORK- MOWING OF RIGHT OF WAY- ORANGE SECTION 0 0005 THIS IS A MOWING CONTRACT FOR ORANGE MAINT SECTION 0 0055 MOWING SEGMENT NET LENGTH611.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 19.000 19.000 1.000 19.00 0065 0730 STRIP MOWING AC 342.000 342.000 27.270 9,326.34 0070 0730 FULL-WIDTH MOWING AC 8,908.000 8,908.000 27.270 242,921.16 0075 0730 SPOT MOWING AC 100.000 0.000 27.270 .00 0 SUBTOTAL BID ITEMS $ 252,266.50 0 TOTAL AMOUNT WORK DONE MOWING SEGMENT $ 252,266.50 0 TOTAL AMOUNT WORK DONE CONTROL 6209-57-001 $ 252,266.50 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5112003 MGR.NO. 007 PAGE 001 CONT 6209 SEC 57 JOB 001 RES ENGR COX, MARK PROJ RMC - 620957001 HWY IH0010 3128 SH 62N ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 254,993.50 REPORT DATE 04/12/2013 07.35.58 CONTRACTOR P-VILLE, INCORPORATED 6856 EST PERIOD JUN 08,2011 TO APR 30,2013 EST NO 019 & FINAL 0*********************************************************************************************************************************** -LIMITS - JEFFERSON COUNTY LINE 0 LOUISIANA STATE LINE DATE WORK BEGAN JUN 8 , 2011 WORKING DAYS USED 29 PERCENT COMPLETE 100.00 PERCENT TIME USED 25.40 DATE COMPLETED APR 4 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6209-57-001 RMC - 620957001 20 IH0010 ORANGE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 19.000 19.000 1.000 19.00 0730 STRIP MOWING AC 342.000 342.000 27.270 9,326.34 0730 FULL-WIDTH MOWING AC 8,908.000 8,908.000 27.270 242,921.16 0 SUBTOTAL BID ITEMS $ 252,266.50 0 CONTRACT TOTAL ALL ITEMS $ 252,266.50 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5112003 MGR.NO. 007 PAGE 001 CONT 6209 SEC 57 JOB 001 RES ENGR COX, MARK PROJ RMC - 620957001 HWY IH0010 3128 SH 62N ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 254,993.50 REPORT DATE 04/12/2013 07.35.58 CONTRACTOR P-VILLE, INCORPORATED 6856 EST PERIOD JUN 08,2011 TO APR 30,2013 EST NO 019 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 181 RMC - 620957001 6209-57-001 252,266.50 .00 252,266.50 .00 .00 252,266.50 252,262.50 4.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 252,266.50 .00 252,266.50 .00 .00 252,266.50 252,262.50 4.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5112003 MGR.NO. 007 PAGE 001 CONT 6209 SEC 57 JOB 001 RES ENGR COX, MARK PROJ RMC - 620957001 HWY IH0010 3128 SH 62N ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 254,993.50 REPORT DATE 04/12/2013 07.35.58 CONTRACTOR P-VILLE, INCORPORATED 6856 EST PERIOD JUN 08,2011 TO APR 30,2013 EST NO 019 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6209-57-001 RMC - 620957001 20 IH0010 ORANGE -LIMITS - JEFFERSON COUNTY LINE LOUISIANA STATE LINE LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0502 BARRICADES, SIGNS AND MO 19.000 4.000 1.000 4.00 TRAFFIC HANDLING --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 4.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 252,266.50