1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9112003 MGR.NO. 051 PAGE 001 CONT 6233 SEC 61 JOB 001 RES ENGR CARON, CHRIS PROJ EMC - 623361001 HWY IH0010 8450 US 69N BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 68,200.00 REPORT DATE 09/27/2011 10.28.13 CONTRACTOR APAC-TEXAS, INC. 154 EST PERIOD SEP 03,2011 TO SEP 04,2011 EST NO 002 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 03, 2011 TIME COMPUTED FROM SEP 03, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 3 0 0 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 11 TOTAL DAYS ALLOWED = 3 DATE WORK COMPLETED 09/04/11 3 1 DAYS CHARGED TO DATE = 1 4 1 WORK COMPLETED AND ACCEPTED ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 0 0 LIQUIDATED DAMAGES 0 DAYS AT $ 0 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 2 1 1 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9112003 MGR.NO. 051 PAGE 001 CONT 6233 SEC 61 JOB 001 RES ENGR CARON, CHRIS PROJ EMC - 623361001 HWY IH0010 8450 US 69N BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 68,200.00 REPORT DATE 09/27/2011 10.28.14 CONTRACTOR APAC-TEXAS, INC. 154 EST PERIOD SEP 03,2011 TO SEP 04,2011 EST NO 002 & FINAL DIST. 20 COUNTY JEFFERSON CONTROL 6233-61-001 PROJECT EMC - 623361001 HIGHWAY IH0010 0LIMITS- NORTH STREET HARRISON STREET 0TYPE OF WORK- STABILIZATION OF IH 10 MSE WALL 0 0050 RETAINING WALLS NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 EMER STABILIZATION RETAINING WALL IH10 0 0075 0500 MOBILIZATION (EMERGENCY) EA 88.000 0.000 775.000 .00 0075 0500 ADJ EST QUANTITY TO DATE 0.000 0080 9001*MOVE & INSTALL CTB TO STABILZE RET WALL EA 88.000 88.000 775.000 68,200.00 0 SUBTOTAL BID ITEMS $ 68,200.00 0 TOTAL AMOUNT WORK DONE RETAINING WALLS $ 68,200.00 0 TOTAL AMOUNT WORK DONE CONTROL 6233-61-001 $ 68,200.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9112003 MGR.NO. 051 PAGE 001 CONT 6233 SEC 61 JOB 001 RES ENGR CARON, CHRIS PROJ EMC - 623361001 HWY IH0010 8450 US 69N BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 68,200.00 REPORT DATE 09/27/2011 10.28.14 CONTRACTOR APAC-TEXAS, INC. 154 EST PERIOD SEP 03,2011 TO SEP 04,2011 EST NO 002 & FINAL 0*********************************************************************************************************************************** -LIMITS - NORTH STREET 0 HARRISON STREET DATE WORK BEGAN SEP 3 , 2011 WORKING DAYS USED 1 PERCENT COMPLETE 100.00 PERCENT TIME USED 33.30 DATE COMPLETED SEP 4 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6233-61-001 EMC - 623361001 20 IH0010 JEFFERSON 0000 88.000 88.000 68,200.00 0 SUBTOTAL BID ITEMS $ 68,200.00 0 CONTRACT TOTAL ALL ITEMS $ 68,200.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9112003 MGR.NO. 051 PAGE 001 CONT 6233 SEC 61 JOB 001 RES ENGR CARON, CHRIS PROJ EMC - 623361001 HWY IH0010 8450 US 69N BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 68,200.00 REPORT DATE 09/27/2011 10.28.14 CONTRACTOR APAC-TEXAS, INC. 154 EST PERIOD SEP 03,2011 TO SEP 04,2011 EST NO 002 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 124 EMC - 623361001 6233-61-001 68,200.00 .00 68,200.00 .00 .00 68,200.00 68,200.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 68,200.00 .00 68,200.00 .00 .00 68,200.00 68,200.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9112003 MGR.NO. 051 PAGE 001 CONT 6233 SEC 61 JOB 001 RES ENGR CARON, CHRIS PROJ EMC - 623361001 HWY IH0010 8450 US 69N BEAUMONT CNTY JEFFERSON DIST 20 CONTRACT PRICE $ 68,200.00 REPORT DATE 09/27/2011 10.28.14 CONTRACTOR APAC-TEXAS, INC. 154 EST PERIOD SEP 03,2011 TO SEP 04,2011 EST NO 002 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6233-61-001 EMC - 623361001 20 IH0010 JEFFERSON -LIMITS - NORTH STREET HARRISON STREET - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 68,200.00