1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12122002 MGR.NO. 051 PAGE 001 CONT 6242 SEC 90 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624290001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 7,867.30 REPORT DATE 01/13/2014 15.27.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2013 TO DEC 31,2013 EST NO 012 & FINAL SPINDLETOP MHMR SERVICES 09725 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JAN 01, 2013 TIME COMPUTED FROM JAN 01, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 247 334 328 6 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 13 1 1 TOTAL DAYS ALLOWED = 247 2 1 DATE WORK COMPLETED 12/31/13 3 1 DAYS CHARGED TO DATE = 357 4 1 ASSESSED LIQ DAMAGES = 110 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 110 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 HOLIDAY 25 1 HOLIDAY 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 365 357 8 0 SATURDAY 0 SUNDAY 2 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12122002 MGR.NO. 051 PAGE 001 CONT 6242 SEC 90 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624290001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 7,867.30 REPORT DATE 01/13/2014 15.27.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2013 TO DEC 31,2013 EST NO 012 & FINAL SPINDLETOP MHMR SERVICES 09725 DIST. 20 COUNTY HARDIN CONTROL 6242-90-001 PROJECT SUP - 624290001 HIGHWAY US0069 0LIMITS- US 69 US 69 0TYPE OF WORK- KOUNTZE ~ GROUNDS 0 0005 KOUNTZE ~ GROUNDS 0 0055 CREATED BY SUSAN WILL NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7013 GROUNDS MAINTENANCE CYC 16.000 16.000 415.620 6,649.92 0065 7205 GROUNDS MAINTENANCE CYC 1.000 0.000 415.620 .00 0070 7205 LEAF RAKING & REMOVAL CYC 4.000 3.000 200.440 601.32 0 SUBTOTAL BID ITEMS $ 7,251.24 0 TOTAL AMOUNT WORK DONE CREATED BY SUSAN WILL $ 7,251.24 0 TOTAL AMOUNT WORK DONE CONTROL 6242-90-001 $ 7,251.24 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12122002 MGR.NO. 051 PAGE 001 CONT 6242 SEC 90 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624290001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 7,867.30 REPORT DATE 01/13/2014 15.27.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2013 TO DEC 31,2013 EST NO 012 & FINAL SPINDLETOP MHMR SERVICES 09725 0*********************************************************************************************************************************** -LIMITS - US 69 0 US 69 DATE WORK BEGAN JAN 1 , 2013 WORKING DAYS USED 357 PERCENT COMPLETE 100.00 PERCENT TIME USED 144.50 DATE COMPLETED DEC 31 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6242-90-001 SUP - 624290001 20 US0069 HARDIN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7013 GROUNDS MAINTENANCE CYC 16.000 16.000 415.620 6,649.92 7205 LEAF RAKING & REMOVAL CYC 4.000 3.000 200.440 601.32 0 SUBTOTAL BID ITEMS $ 7,251.24 0 CONTRACT TOTAL ALL ITEMS $ 7,251.24 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12122002 MGR.NO. 051 PAGE 001 CONT 6242 SEC 90 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624290001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 7,867.30 REPORT DATE 01/13/2014 15.27.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2013 TO DEC 31,2013 EST NO 012 & FINAL SPINDLETOP MHMR SERVICES 09725 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 101 SUP - 624290001 6242-90-001 7,251.24 .00 7,251.24 .00 .00 7,251.24 6,635.18 616.06 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 7,251.24 .00 7,251.24 .00 .00 7,251.24 6,635.18 616.06 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12122002 MGR.NO. 051 PAGE 001 CONT 6242 SEC 90 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624290001 HWY US0069 8450 EASTEX FRWY BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 7,867.30 REPORT DATE 01/13/2014 15.27.13 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2013 TO DEC 31,2013 EST NO 012 & FINAL SPINDLETOP MHMR SERVICES 09725 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6242-90-001 SUP - 624290001 20 US0069 HARDIN -LIMITS - US 69 US 69 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 7013 GROUNDS MAINTENANCE CYC 16.000 1.000 415.620 415.62 70 7205 LEAF RAKING & REMOVAL CYC 4.000 1.000 200.440 200.44 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 616.06 0 TOTAL AMOUNT WORK DONE TO DATE - $ 7,251.24