1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10122001 MGR.NO. 051 PAGE 001 CONT 6243 SEC 91 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 624391001 HWY SH0326 8450 US 69N BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 108,561.10 REPORT DATE 04/15/2013 09.09.08 CONTRACTOR WIDGEON CONSTRUCTION, INC. 2043 EST PERIOD NOV 06,2012 TO JAN 16,2013 EST NO 004 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 07, 2012 TIME COMPUTED FROM NOV 06, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 39 56 18 38 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 13 1 1 HOLIDAY TOTAL DAYS ALLOWED = 39 2 1 TIME SUSPENDED DATE WORK COMPLETED 01/16/13 3 1 TIME SUSPENDED DAYS CHARGED TO DATE = 18 4 1 TIME SUSPENDED ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 590 6 1 SUNDAY 7 1 TIME SUSPENDED LIQUIDATED DAMAGES 8 1 TIME SUSPENDED 0 DAYS AT $ 590 PER DAY 9 1 TIME SUSPENDED TOTAL = $ .00 10 1 WORK COMPLETED 11 1 AWAITING ACCEPTANCE CERTIFIED AS CORRECT AND 12 1 TOO WINDY AND DUSTY ONE COPY HAS BEEN GIVEN 13 1 WORK ACCEPTED TO THE CONTRACTOR 14 1 AWAITING ACCEPTANCE 15 1 AWAITING ACCEPTANCE 16 1 WORK ACCEPTED ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 72 18 54 1 SATURDAY 1 SUNDAY 1 HOLIDAY 6 TIME SUSPENDED 1 WORK COMPLETED 3 AWAITING ACCEPTANCE 1 TOO WINDY AND DUSTY 2 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10122001 MGR.NO. 051 PAGE 001 CONT 6243 SEC 91 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 624391001 HWY SH0326 8450 US 69N BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 108,561.10 REPORT DATE 04/15/2013 09.09.09 CONTRACTOR WIDGEON CONSTRUCTION, INC. 2043 EST PERIOD NOV 06,2012 TO JAN 16,2013 EST NO 004 & FINAL DIST. 20 COUNTY HARDIN CONTROL 6243-91-001 PROJECT RMC - 624391001 HIGHWAY SH0326 0LIMITS- VARIOUS LOCATIONS VARIOUS LOCATIONS 0TYPE OF WORK- INLET AND CULVERT REPAIRS 0 0005 PREPARED 6-21-12 0 0055 ROADWAY NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0104 REMOVING CONC (RIPRAP) SY 60.000 60.000 14.700 882.00 0065 0110 EXCAVATION (CHANNEL) CY 110.000 110.000 48.650 5,351.50 0067 0110*EXCAVATION (SPECIAL) CY 27.000 27.000 87.000 2,349.00 0070 0132 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 150.000 150.000 23.000 3,450.00 0072 0162*BLOCK SODDING SY 320.000 311.110 8.750 2,722.21 0075 0247 FL BS (CMP IN PLC)(TY A GR 1) TON 3.000 3.000 163.000 489.00 0080 0400 CEM STABIL BKFL CY 60.000 60.000 110.000 6,600.00 0085 0402 TRENCH EXCAVATION PROTECTION LF 21.000 21.000 62.000 1,302.00 0090 0432 RIPRAP (CONC)(5 IN) CY 121.000 125.480 209.000 26,225.32 0095 0432 RIPRAP (STONE PROTECTION)(12 IN) CY 48.000 69.530 285.000 19,816.05 0100 0462 CONC BOX CULV (7 FT X 7 FT) LF 21.000 21.000 530.000 11,130.00 0105 0464 RC PIPE (CL III)(18 IN) LF 10.000 8.000 41.450 331.60 0110 0464 RC PIPE (CL III)(24 IN) LF 8.000 8.000 54.700 437.60 0115 0465 INLET (COMP)(GRATE) EA 1.000 1.000 5,698.000 5,698.00 0120 0466 WINGWALL (PW)(HW=8 FT) EA 1.000 1.000 21,415.000 21,415.00 0125 0467 SET (TY II)(24 IN)(RCP)(6:1)(P) EA 2.000 2.000 1,215.000 2,430.00 0130 0496 REMOV STR (INLET) EA 1.000 1.000 2,875.000 2,875.00 0135 0496 REMOV STR (SET) EA 2.000 2.000 350.000 700.00 0140 0500 MOBILIZATION LS 1.000 1.000 5,200.000 5,200.00 0145 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 220.000 660.00 0147 0529*CONC CURB & GUTTER (TY II) LF 150.000 150.000 51.000 7,650.00 0150 0550 CHAIN LINK FENCE (REMOVE) LF 50.000 50.000 3.500 175.00 0155 0550 CHAIN LINK FENCE (INSTALL)(6')BARB TOP LF 50.000 50.000 7.650 382.50 1 0160 9001*CO#1-REPAIR CPJR(US69 NBFR@SH105EXIT)FA DOL 35,952.100 35,952.100 1.000 35,952.10 0165 9002*CO#3-FINGER JOINT REPAIR(TEMPORARY) LS 1.000 1.000 1,325.810 1,325.81 0 SUBTOTAL BID ITEMS $ 165,549.69 0 TOTAL AMOUNT WORK DONE ROADWAY $ 165,549.69 0 TOTAL AMOUNT WORK DONE CONTROL 6243-91-001 $ 165,549.69 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10122001 MGR.NO. 051 PAGE 001 CONT 6243 SEC 91 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 624391001 HWY SH0326 8450 US 69N BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 108,561.10 REPORT DATE 04/15/2013 09.09.10 CONTRACTOR WIDGEON CONSTRUCTION, INC. 2043 EST PERIOD NOV 06,2012 TO JAN 16,2013 EST NO 004 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS 0 VARIOUS LOCATIONS DATE WORK BEGAN NOV 7 , 2012 WORKING DAYS USED 18 PERCENT COMPLETE 100.00 PERCENT TIME USED 46.10 DATE COMPLETED JAN 16 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6243-91-001 RMC - 624391001 20 SH0326 HARDIN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0104 REMOVING CONC (RIPRAP) SY 60.000 60.000 14.700 882.00 0110 EXCAVATION (CHANNEL) CY 110.000 110.000 48.650 5,351.50 0132 EMBANKMENT (FINAL)(ORD COMP)(TY B) CY 150.000 150.000 23.000 3,450.00 0247 FL BS (CMP IN PLC)(TY A GR 1) TON 3.000 3.000 163.000 489.00 0400 CEM STABIL BKFL CY 60.000 60.000 110.000 6,600.00 0402 TRENCH EXCAVATION PROTECTION LF 21.000 21.000 62.000 1,302.00 0432 RIPRAP (CONC)(5 IN) CY 121.000 125.480 209.000 26,225.32 0432 RIPRAP (STONE PROTECTION)(12 IN) CY 48.000 69.530 285.000 19,816.05 0462 CONC BOX CULV (7 FT X 7 FT) LF 21.000 21.000 530.000 11,130.00 0464 RC PIPE (CL III)(18 IN) LF 10.000 8.000 41.450 331.60 0464 RC PIPE (CL III)(24 IN) LF 8.000 8.000 54.700 437.60 0465 INLET (COMP)(GRATE) EA 1.000 1.000 5,698.000 5,698.00 0466 WINGWALL (PW)(HW=8 FT) EA 1.000 1.000 21,415.000 21,415.00 0467 SET (TY II)(24 IN)(RCP)(6:1)(P) EA 2.000 2.000 1,215.000 2,430.00 0496 REMOV STR (INLET) EA 1.000 1.000 2,875.000 2,875.00 0496 REMOV STR (SET) EA 2.000 2.000 350.000 700.00 0500 MOBILIZATION LS 1.000 1.000 5,200.000 5,200.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 220.000 660.00 0550 CHAIN LINK FENCE (REMOVE) LF 50.000 50.000 3.500 175.00 0550 CHAIN LINK FENCE 1 (INSTALL)(6')BARB TOP LF 50.000 50.000 7.650 382.50 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00110* EXCAVATION (SPECIAL) CY 27.000 27.000 87.000 2,349.00 0162* BLOCK SODDING SY 320.000 311.110 8.750 2,722.21 0529* CONC CURB & GUTTER (TY II) LF 150.000 150.000 51.000 7,650.00 9001* CO#1-REPAIR CPJR(US69 NBFR@SH105EXIT)FA DOL 35,952.100 35,952.100 1.000 35,952.10 9002* CO#3-FINGER JOINT REPAIR(TEMPORARY) LS 1.000 1.000 1,325.810 1,325.81 0 SUBTOTAL BID ITEMS $ 165,549.69 0 CONTRACT TOTAL ALL ITEMS $ 165,549.69 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10122001 MGR.NO. 051 PAGE 001 CONT 6243 SEC 91 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 624391001 HWY SH0326 8450 US 69N BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 108,561.10 REPORT DATE 04/15/2013 09.09.10 CONTRACTOR WIDGEON CONSTRUCTION, INC. 2043 EST PERIOD NOV 06,2012 TO JAN 16,2013 EST NO 004 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 101 RMC - 624391001 6243-91-001 165,549.69 .00 165,549.69 .00 .00 165,549.69 165,471.48 78.21 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 165,549.69 .00 165,549.69 .00 .00 165,549.69 165,471.48 78.21 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10122001 MGR.NO. 051 PAGE 001 CONT 6243 SEC 91 JOB 001 RES ENGR CARON, CHRIS PROJ RMC - 624391001 HWY SH0326 8450 US 69N BEAUMONT CNTY HARDIN DIST 20 CONTRACT PRICE $ 108,561.10 REPORT DATE 04/15/2013 09.09.10 CONTRACTOR WIDGEON CONSTRUCTION, INC. 2043 EST PERIOD NOV 06,2012 TO JAN 16,2013 EST NO 004 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6243-91-001 RMC - 624391001 20 SH0326 HARDIN -LIMITS - VARIOUS LOCATIONS VARIOUS LOCATIONS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 140 0500 MOBILIZATION LS 1.000 0.030 5,200.000 156.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 72 0162* BLOCK SODDING SY 0.000 -8.890 8.750 -77.79 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 78.21 0 TOTAL AMOUNT WORK DONE TO DATE - $ 165,549.69