1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10122008 MGR.NO. 051 PAGE 001 CONT 6246 SEC 51 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624651001 HWY SH0062 3128 SH 62 ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 56,783.66 REPORT DATE 09/24/2013 15.33.14 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 01,2012 TO SEP 09,2013 EST NO 011 & FINAL WOODCREEK OUTREACH REHABILITATION DEVELOPMENT 14415 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 01, 2012 TIME COMPUTED FROM NOV 01, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 304 260 44 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 13 1 1 SUNDAY TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 3 1 WORK COMPLETED AND ACCEPTED DAYS CHARGED TO DATE = 288 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 334 288 46 0 SATURDAY 1 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10122008 MGR.NO. 051 PAGE 001 CONT 6246 SEC 51 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624651001 HWY SH0062 3128 SH 62 ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 56,783.66 REPORT DATE 09/24/2013 15.33.15 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 01,2012 TO SEP 09,2013 EST NO 011 & FINAL WOODCREEK OUTREACH REHABILITATION DEVELOPMENT 14415 DIST. 20 COUNTY ORANGE CONTROL 6246-51-001 PROJECT SUP - 624651001 HIGHWAY SH0062 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- ORANGE ~ LITTER 0 0005 ANAHUAC MAINTENANCE 0 0055 LITTER PICK UP NET LENGTH 1.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL(SPOT) AC 100.000 66.000 12.000 792.00 0065 0734 LITTER REMOVAL - TRACT (1) CYC 3.000 0.000 7,086.560 .00 0065 0734 ADJ EST QUANTITY TO DATE 0.000 0070 0734 LITTER REMOVAL - TRACT (2) CYC 2.000 2.000 1,872.140 3,744.28 0075 0734 LITTER REMOVAL - TRACT (3) CYC 6.000 4.000 836.830 3,347.32 0080 0734 LITTER REMOVAL - TRACT (4) CYC 3.000 3.000 1,595.760 4,787.28 0085 0734 LITTER REMOVAL - TRACT (5) CYC 2.000 2.000 2,474.020 4,948.04 0090 0734 LITTER REMOVAL - TRACT (6) CYC 2.000 2.000 173.560 347.12 0095 0734 LITTER REMOVAL - TRACT (7) CYC 1.000 0.000 471.740 .00 0100 0734 LITTER REMOVAL - TRACT (8) CYC 1.000 1.000 1,059.010 1,059.01 0105 0734 LITTER REMOVAL - TRACT (9) CYC 2.000 2.000 1,460.140 2,920.28 0110 0734 LITTER REMOVAL - TRACT (10) CYC 2.000 2.000 345.970 691.94 0115 0734 LITTER REMOVAL - TRACT (11) CYC 3.000 3.000 325.260 975.78 0120 0734 LITTER REMOVAL - TRACT (12) CYC 1.000 1.000 1,965.480 1,965.48 0125 0734 LITTER REMOVAL - TRACT (13) CYC 2.000 2.000 358.680 717.36 0130 0734 LITTER REMOVAL - TRACT (14) CYC 2.000 2.000 991.110 1,982.22 0135 0734 LITTER REMOVAL - TRACT (15) CYC 1.000 1.000 398.700 398.70 0140 0734 LITTER REMOVAL - TRACT (16) CYC 2.000 2.000 1,061.870 2,123.74 0145 0734 LITTER REMOVAL - TRACT (17) CYC 3.000 3.000 394.720 1,184.16 0150 0734 LITTER REMOVAL - TRACT (18) CYC 2.000 3.000 414.090 1,242.27 0155 0734 LITTER REMOVAL - TRACT (19) CYC 1.000 1.000 157.690 157.69 0300 0734*LITTER REMOVAL - TRACT (20) CYC 4.000 4.000 5,562.930 22,251.72 0 SUBTOTAL BID ITEMS $ 55,636.39 0 TOTAL AMOUNT WORK DONE LITTER PICK UP $ 55,636.39 0 TOTAL AMOUNT WORK DONE CONTROL 6246-51-001 $ 55,636.39 1 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10122008 MGR.NO. 051 PAGE 001 CONT 6246 SEC 51 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624651001 HWY SH0062 3128 SH 62 ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 56,783.66 REPORT DATE 09/24/2013 15.33.16 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 01,2012 TO SEP 09,2013 EST NO 011 & FINAL WOODCREEK OUTREACH REHABILITATION DEVELOPMENT 14415 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN NOV 1 , 2012 WORKING DAYS USED 288 PERCENT COMPLETE 97.97 PERCENT TIME USED 78.90 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6246-51-001 SUP - 624651001 20 SH0062 ORANGE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL(SPOT) AC 100.000 66.000 12.000 792.00 0734 LITTER REMOVAL - TRACT (2) CYC 2.000 2.000 1,872.140 3,744.28 0734 LITTER REMOVAL - TRACT (3) CYC 6.000 4.000 836.830 3,347.32 0734 LITTER REMOVAL - TRACT (4) CYC 3.000 3.000 1,595.760 4,787.28 0734 LITTER REMOVAL - TRACT (5) CYC 2.000 2.000 2,474.020 4,948.04 0734 LITTER REMOVAL - TRACT (6) CYC 2.000 2.000 173.560 347.12 0734 LITTER REMOVAL - TRACT (8) CYC 1.000 1.000 1,059.010 1,059.01 0734 LITTER REMOVAL - TRACT (9) CYC 2.000 2.000 1,460.140 2,920.28 0734 LITTER REMOVAL - TRACT (10) CYC 2.000 2.000 345.970 691.94 0734 LITTER REMOVAL - TRACT (11) CYC 3.000 3.000 325.260 975.78 0734 LITTER REMOVAL - TRACT (12) CYC 1.000 1.000 1,965.480 1,965.48 0734 LITTER REMOVAL - TRACT (13) CYC 2.000 2.000 358.680 717.36 0734 LITTER REMOVAL - TRACT (14) CYC 2.000 2.000 991.110 1,982.22 0734 LITTER REMOVAL - TRACT (15) CYC 1.000 1.000 398.700 398.70 0734 LITTER REMOVAL - TRACT (16) CYC 2.000 2.000 1,061.870 2,123.74 0734 LITTER REMOVAL - TRACT (17) CYC 3.000 3.000 394.720 1,184.16 0734 LITTER REMOVAL - TRACT (18) CYC 2.000 3.000 414.090 1,242.27 0734 LITTER REMOVAL - TRACT (19) CYC 1.000 1.000 157.690 157.69 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 00734* LITTER REMOVAL - TRACT (20) CYC 4.000 4.000 5,562.930 22,251.72 0 SUBTOTAL BID ITEMS $ 55,636.39 1 CONTRACT TOTAL ALL ITEMS $ 55,636.39 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10122008 MGR.NO. 051 PAGE 001 CONT 6246 SEC 51 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624651001 HWY SH0062 3128 SH 62 ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 56,783.66 REPORT DATE 09/24/2013 15.33.16 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 01,2012 TO SEP 09,2013 EST NO 011 & FINAL WOODCREEK OUTREACH REHABILITATION DEVELOPMENT 14415 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 181 SUP - 624651001 6246-51-001 55,636.39 .00 55,636.39 .00 .00 55,636.39 55,636.39 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 55,636.39 .00 55,636.39 .00 .00 55,636.39 55,636.39 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10122008 MGR.NO. 051 PAGE 001 CONT 6246 SEC 51 JOB 001 RES ENGR RYAN, PATRICK PROJ SUP - 624651001 HWY SH0062 3128 SH 62 ORANGE CNTY ORANGE DIST 20 CONTRACT PRICE $ 56,783.66 REPORT DATE 09/24/2013 15.33.16 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD NOV 01,2012 TO SEP 09,2013 EST NO 011 & FINAL WOODCREEK OUTREACH REHABILITATION DEVELOPMENT 14415 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6246-51-001 SUP - 624651001 20 SH0062 ORANGE -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 55,636.39