1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9121793 MGR.NO. 054 PAGE 001 CONT 6250 SEC 69 JOB 001 RES ENGR JEFFREY, MARK PROJ SUP - 625069001 HWY US0084 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 96,580.12 REPORT DATE 12/10/2013 08.59.23 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2012 TO NOV 30,2013 EST NO 014 & FINAL CEN-TEX ASSOCIATION FOR RETARDED CHILDREN 09519 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 01, 2012 TIME COMPUTED FROM OCT 01, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 396 396 0 BROUGHT FORWARD ADDL DAYS GRANTED = 61 NOV 13 1 1 TOTAL DAYS ALLOWED = 426 2 1 DATE WORK COMPLETED 11/30/13 3 1 DAYS CHARGED TO DATE = 426 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 426 426 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9121793 MGR.NO. 054 PAGE 001 CONT 6250 SEC 69 JOB 001 RES ENGR JEFFREY, MARK PROJ SUP - 625069001 HWY US0084 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 96,580.12 REPORT DATE 12/10/2013 08.59.25 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2012 TO NOV 30,2013 EST NO 014 & FINAL CEN-TEX ASSOCIATION FOR RETARDED CHILDREN 09519 DIST. 17 COUNTY FREESTONE CONTROL 6250-69-001 PROJECT SUP - 625069001 HIGHWAY US0084 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- LITTER PICKUP AND DISPOSAL 0 0005 LIDS CONTRACT PREPARED BY DISTRICT MAINTENANCE 0 0055 LITTER PICKUP & DISPOSAL FREESTONE NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL - TRACT (1) CYC 2.000 2.000 1,510.030 3,020.06 0065 0734 LITTER REMOVAL - TRACT (2) CYC 2.000 2.000 1,712.160 3,424.32 0070 0734 LITTER REMOVAL - TRACT (3) CYC 2.000 2.000 448.540 897.08 0075 0734 LITTER REMOVAL - TRACT (4) CYC 2.000 2.000 69.960 139.92 0080 0734 LITTER REMOVAL - TRACT (5) CYC 2.000 3.000 366.450 1,099.35 0085 0734 LITTER REMOVAL - TRACT (6) CYC 2.000 3.000 952.320 2,856.96 0090 0734 LITTER REMOVAL - TRACT (7) CYC 2.000 3.000 121.200 363.60 0095 0734 LITTER REMOVAL - TRACT (8) CYC 2.000 3.000 870.400 2,611.20 0100 0734 LITTER REMOVAL - TRACT (9) CYC 2.000 2.000 468.630 937.26 0105 0734 LITTER REMOVAL - TRACT (10) CYC 2.000 2.000 407.740 815.48 0110 0734 LITTER REMOVAL - TRACT (11) CYC 2.000 2.000 1,337.310 2,674.62 0115 0734 LITTER REMOVAL - TRACT (12) CYC 2.000 3.000 628.200 1,884.60 0120 0734 LITTER REMOVAL - TRACT (13) CYC 2.000 2.000 9,578.200 19,156.40 0125 0734 LITTER REMOVAL - TRACT (14) CYC 2.000 2.000 1,223.240 2,446.48 0130 0734 LITTER REMOVAL - TRACT (15) CYC 2.000 2.000 7,777.960 15,555.92 0135 0734 LITTER REMOVAL - TRACT (16) CYC 2.000 3.000 1,983.600 5,950.80 0140 0734 LITTER REMOVAL - TRACT (17) CYC 2.000 2.000 2,739.200 5,478.40 0145 0734 LITTER REMOVAL - TRACT (18) CYC 2.000 3.000 604.800 1,814.40 0150 0734 LITTER REMOVAL - TRACT (19) CYC 2.000 2.000 22.400 44.80 0155 0734 LITTER REMOVAL - TRACT (20) CYC 2.000 2.000 495.900 991.80 0160 0734 LITTER REMOVAL - TRACT (21) CYC 2.000 2.000 2,091.690 4,183.38 0165 0734 LITTER REMOVAL - TRACT (22) CYC 2.000 2.000 1,153.600 2,307.20 0170 0734 LITTER REMOVAL - TRACT (23) CYC 2.000 2.000 2,011.680 4,023.36 0175 0734 LITTER REMOVAL - TRACT (24) CYC 2.000 2.000 86.450 172.90 0180 0734 LITTER REMOVAL - TRACT (25) CYC 2.000 2.000 1,586.880 3,173.76 0185 0734 LITTER REMOVAL - TRACT (26) CYC 2.000 2.000 130.130 260.26 0190 0734 LITTER REMOVAL - TRACT (27) CYC 2.000 2.000 170.170 340.34 0195 0734 LITTER REMOVAL - TRACT (28) CYC 2.000 2.000 70.070 140.14 1 0200 0734 LITTER REMOVAL - TRACT (29) CYC 2.000 2.000 437.600 875.20 0205 0734 LITTER REMOVAL - TRACT (30) CYC 2.000 2.000 678.280 1,356.56 0210 0734 LITTER REMOVAL - TRACT (31) CYC 2.000 2.000 160.160 320.32 0215 0734 LITTER REMOVAL - TRACT (32) CYC 2.000 2.000 10.010 20.02 0220 0734 LITTER REMOVAL - TRACT (33) CYC 2.000 2.000 100.100 200.20 0225 0734 LITTER REMOVAL - TRACT (34) CYC 2.000 2.000 470.400 940.80 0230 0734 LITTER REMOVAL - TRACT (35) CYC 2.000 2.000 313.600 627.20 0235 0734 LITTER REMOVAL - TRACT (36) CYC 2.000 2.000 834.390 1,668.78 0240 0734 LITTER REMOVAL - TRACT (37) CYC 2.000 2.000 361.460 722.92 0245 0734 LITTER REMOVAL - TRACT (38) CYC 2.000 2.000 740.740 1,481.48 0250 0734 LITTER REMOVAL - TRACT (39) CYC 2.000 2.000 273.500 547.00 0255 0734 LITTER REMOVAL - TRACT (40) CYC 2.000 2.000 460.460 920.92 0260 0734 LITTER REMOVAL - TRACT (41) CYC 2.000 2.000 370.500 741.00 0265 0734 LITTER REMOVAL - TRACT (42) CYC 2.000 2.000 49.400 98.80 0270 0734 LITTER REMOVAL - TRACT (43) CYC 2.000 2.000 37.050 74.10 0275 0734 LITTER REMOVAL - TRACT (44) CYC 2.000 2.000 61.750 123.50 0280 0734 LITTER REMOVAL - TRACT (45) CYC 2.000 2.000 61.750 123.50 0285 0734 LITTER REMOVAL CYC 300.000 0.000 15.000 .00 0 SUBTOTAL BID ITEMS $ 97,607.09 0 TOTAL AMOUNT WORK DONE LITTER PICKUP & DISPOSAL FREESTONE $ 97,607.09 0 TOTAL AMOUNT WORK DONE CONTROL 6250-69-001 $ 97,607.09 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9121793 MGR.NO. 054 PAGE 001 CONT 6250 SEC 69 JOB 001 RES ENGR JEFFREY, MARK PROJ SUP - 625069001 HWY US0084 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 96,580.12 REPORT DATE 12/10/2013 08.59.26 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2012 TO NOV 30,2013 EST NO 014 & FINAL CEN-TEX ASSOCIATION FOR RETARDED CHILDREN 09519 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN OCT 1 , 2012 WORKING DAYS USED 426 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED NOV 30 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6250-69-001 SUP - 625069001 17 US0084 FREESTONE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL - TRACT (1) CYC 2.000 2.000 1,510.030 3,020.06 0734 LITTER REMOVAL - TRACT (2) CYC 2.000 2.000 1,712.160 3,424.32 0734 LITTER REMOVAL - TRACT (3) CYC 2.000 2.000 448.540 897.08 0734 LITTER REMOVAL - TRACT (4) CYC 2.000 2.000 69.960 139.92 0734 LITTER REMOVAL - TRACT (5) CYC 2.000 3.000 366.450 1,099.35 0734 LITTER REMOVAL - TRACT (6) CYC 2.000 3.000 952.320 2,856.96 0734 LITTER REMOVAL - TRACT (7) CYC 2.000 3.000 121.200 363.60 0734 LITTER REMOVAL - TRACT (8) CYC 2.000 3.000 870.400 2,611.20 0734 LITTER REMOVAL - TRACT (9) CYC 2.000 2.000 468.630 937.26 0734 LITTER REMOVAL - TRACT (10) CYC 2.000 2.000 407.740 815.48 0734 LITTER REMOVAL - TRACT (11) CYC 2.000 2.000 1,337.310 2,674.62 0734 LITTER REMOVAL - TRACT (12) CYC 2.000 3.000 628.200 1,884.60 0734 LITTER REMOVAL - TRACT (13) CYC 2.000 2.000 9,578.200 19,156.40 0734 LITTER REMOVAL - TRACT (14) CYC 2.000 2.000 1,223.240 2,446.48 0734 LITTER REMOVAL - TRACT (15) CYC 2.000 2.000 7,777.960 15,555.92 0734 LITTER REMOVAL - TRACT (16) CYC 2.000 3.000 1,983.600 5,950.80 0734 LITTER REMOVAL - TRACT (17) CYC 2.000 2.000 2,739.200 5,478.40 0734 LITTER REMOVAL - TRACT (18) CYC 2.000 3.000 604.800 1,814.40 0734 LITTER REMOVAL - TRACT (19) CYC 2.000 2.000 22.400 44.80 0734 LITTER REMOVAL - TRACT (20) CYC 2.000 2.000 495.900 991.80 0734 LITTER REMOVAL - TRACT (21) CYC 2.000 2.000 2,091.690 4,183.38 0734 LITTER REMOVAL - TRACT (22) CYC 2.000 2.000 1,153.600 2,307.20 0734 LITTER REMOVAL - TRACT (23) CYC 2.000 2.000 2,011.680 4,023.36 0734 LITTER REMOVAL - TRACT (24) CYC 2.000 2.000 86.450 172.90 10734 LITTER REMOVAL - TRACT (25) CYC 2.000 2.000 1,586.880 3,173.76 0734 LITTER REMOVAL - TRACT (26) CYC 2.000 2.000 130.130 260.26 0734 LITTER REMOVAL - TRACT (27) CYC 2.000 2.000 170.170 340.34 0734 LITTER REMOVAL - TRACT (28) CYC 2.000 2.000 70.070 140.14 0734 LITTER REMOVAL - TRACT (29) CYC 2.000 2.000 437.600 875.20 0734 LITTER REMOVAL - TRACT (30) CYC 2.000 2.000 678.280 1,356.56 0734 LITTER REMOVAL - TRACT (31) CYC 2.000 2.000 160.160 320.32 0734 LITTER REMOVAL - TRACT (32) CYC 2.000 2.000 10.010 20.02 0734 LITTER REMOVAL - TRACT (33) CYC 2.000 2.000 100.100 200.20 0734 LITTER REMOVAL - TRACT (34) CYC 2.000 2.000 470.400 940.80 0734 LITTER REMOVAL - TRACT (35) CYC 2.000 2.000 313.600 627.20 0734 LITTER REMOVAL - TRACT (36) CYC 2.000 2.000 834.390 1,668.78 0734 LITTER REMOVAL - TRACT (37) CYC 2.000 2.000 361.460 722.92 0734 LITTER REMOVAL - TRACT (38) CYC 2.000 2.000 740.740 1,481.48 0734 LITTER REMOVAL - TRACT (39) CYC 2.000 2.000 273.500 547.00 0734 LITTER REMOVAL - TRACT (40) CYC 2.000 2.000 460.460 920.92 0734 LITTER REMOVAL - TRACT (41) CYC 2.000 2.000 370.500 741.00 0734 LITTER REMOVAL - TRACT (42) CYC 2.000 2.000 49.400 98.80 0734 LITTER REMOVAL - TRACT (43) CYC 2.000 2.000 37.050 74.10 0734 LITTER REMOVAL - TRACT (44) CYC 2.000 2.000 61.750 123.50 0734 LITTER REMOVAL - TRACT (45) CYC 2.000 2.000 61.750 123.50 0 SUBTOTAL BID ITEMS $ 97,607.09 0 CONTRACT TOTAL ALL ITEMS $ 97,607.09 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9121793 MGR.NO. 054 PAGE 001 CONT 6250 SEC 69 JOB 001 RES ENGR JEFFREY, MARK PROJ SUP - 625069001 HWY US0084 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 96,580.12 REPORT DATE 12/10/2013 08.59.26 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2012 TO NOV 30,2013 EST NO 014 & FINAL CEN-TEX ASSOCIATION FOR RETARDED CHILDREN 09519 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 82 SUP - 625069001 6250-69-001 97,607.09 .00 97,607.09 .00 .00 97,607.09 93,520.09 4,087.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 97,607.09 .00 97,607.09 .00 .00 97,607.09 93,520.09 4,087.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9121793 MGR.NO. 054 PAGE 001 CONT 6250 SEC 69 JOB 001 RES ENGR JEFFREY, MARK PROJ SUP - 625069001 HWY US0084 340 WEST US 84 FAIRFIELD CNTY FREESTONE DIST 17 CONTRACT PRICE $ 96,580.12 REPORT DATE 12/10/2013 08.59.26 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2012 TO NOV 30,2013 EST NO 014 & FINAL CEN-TEX ASSOCIATION FOR RETARDED CHILDREN 09519 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6250-69-001 SUP - 625069001 17 US0084 FREESTONE -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 95 0734 LITTER REMOVAL - TRACT (8) CYC 2.000 1.000 870.400 870.40 115 0734 LITTER REMOVAL - TRACT (12) CYC 2.000 1.000 628.200 628.20 135 0734 LITTER REMOVAL - TRACT (16) CYC 2.000 1.000 1,983.600 1,983.60 145 0734 LITTER REMOVAL - TRACT (18) CYC 2.000 1.000 604.800 604.80 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 4,087.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 97,607.09