1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3124018 MGR.NO. PAGE 001 CONT 6231 SEC 69 JOB 001 RES ENGR SMITH, LARRY PROJ RMC - 623169001 HWY US0183 906 EAST MAIN EASTLAND CNTY STEPHENS DIST 23 CONTRACT PRICE $ 592,587.82 REPORT DATE 06/10/2013 14.32.41 CONTRACTOR ZACK BURKETT CO. 236 EST PERIOD JUL 30,2012 TO SEP 01,2012 EST NO 004 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 30, 2012 TIME COMPUTED FROM AUG 02, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 15 33 14 19 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 12 1 1 WORK ACCEPTED TOTAL DAYS ALLOWED = 15 DATE WORK COMPLETED 09/01/12 DAYS CHARGED TO DATE = 14 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 610 0 LIQUIDATED DAMAGES 0 DAYS AT $ 610 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 34 14 20 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3124018 MGR.NO. PAGE 001 CONT 6231 SEC 69 JOB 001 RES ENGR SMITH, LARRY PROJ RMC - 623169001 HWY US0183 906 EAST MAIN EASTLAND CNTY STEPHENS DIST 23 CONTRACT PRICE $ 592,587.82 REPORT DATE 06/10/2013 14.32.41 CONTRACTOR ZACK BURKETT CO. 236 EST PERIOD JUL 30,2012 TO SEP 01,2012 EST NO 004 & FINAL DIST. 23 COUNTY STEPHENS CONTROL 6231-69-001 PROJECT RMC - 623169001 HIGHWAY US0183 0LIMITS- JCT FM 2231, SOUTH JCT FM 1032 0TYPE OF WORK- HOT MIX OVERLAY 0 0050 HOT MIX OVERLAY NET LENGTH 8.753 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0055 0500 MOBILIZATION LS 1.000 1.000 40,000.000 40,000.00 0060 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 4,484.000 4,484.00 0065 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 3,470.000 3,470.000 1.000 3,470.00 0070 0672 REFL PAV MRKR TY I-C EA 10.000 36.000 3.810 137.16 0075 0672 REFL PAV MRKR TY II-A-A EA 850.000 764.000 3.810 2,910.84 0080 3243 FGSM (ASPHALT) PG 76-22 TON 283.000 346.460 926.000 320,821.96 0085 3243 FGSM (AGGREGATE) (TY I FGPFC) SAC-B TON 4,711.000 4,983.750 47.500 236,728.13 0090 8251 RE PM W/RET REQ TY I(W)4"(BRK)(090MIL) LF 790.000 710.000 .460 326.60 0095 8251 RE PM W/RET REQ TY I(W)4"(SLD)(090MIL) LF 94,076.000 94,076.000 .390 36,689.64 0100 8251 RE PM W/RET REQ TY I(Y)4"(BRK)(090MIL) LF 8,950.000 10,940.000 .460 5,032.40 0105 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(090MIL) LF 36,812.000 17,844.000 .390 6,959.16 0 SUBTOTAL BID ITEMS $ 657,559.89 0 TOTAL AMOUNT WORK DONE HOT MIX OVERLAY $ 657,559.89 0 TOTAL AMOUNT WORK DONE CONTROL 6231-69-001 $ 657,559.89 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3124018 MGR.NO. PAGE 001 CONT 6231 SEC 69 JOB 001 RES ENGR SMITH, LARRY PROJ RMC - 623169001 HWY US0183 906 EAST MAIN EASTLAND CNTY STEPHENS DIST 23 CONTRACT PRICE $ 592,587.82 REPORT DATE 06/10/2013 14.32.42 CONTRACTOR ZACK BURKETT CO. 236 EST PERIOD JUL 30,2012 TO SEP 01,2012 EST NO 004 & FINAL 0*********************************************************************************************************************************** -LIMITS - JCT FM 2231, SOUTH 0 JCT FM 1032 DATE WORK BEGAN JUL 30, 2012 WORKING DAYS USED 14 PERCENT COMPLETE 100.00 PERCENT TIME USED 93.30 DATE COMPLETED SEP 1 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6231-69-001 RMC - 623169001 23 US0183 STEPHENS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 40,000.000 40,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 4,484.000 4,484.00 0662 WK ZN PAV MRK SHT TERM (TAB) TY Y-2 EA 3,470.000 3,470.000 1.000 3,470.00 0672 REFL PAV MRKR TY I-C EA 10.000 36.000 3.810 137.16 0672 REFL PAV MRKR TY II-A-A EA 850.000 764.000 3.810 2,910.84 3243 FGSM (ASPHALT) PG 76-22 TON 283.000 346.460 926.000 320,821.96 3243 FGSM (AGGREGATE) (TY I FGPFC) SAC-B TON 4,711.000 4,983.750 47.500 236,728.13 8251 RE PM W/RET REQ TY I(W)4"(BRK)(090MIL) LF 790.000 710.000 .460 326.60 8251 RE PM W/RET REQ TY I(W)4"(SLD)(090MIL) LF 94,076.000 94,076.000 .390 36,689.64 8251 RE PM W/RET REQ TY I(Y)4"(BRK)(090MIL) LF 8,950.000 10,940.000 .460 5,032.40 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(090MIL) LF 36,812.000 17,844.000 .390 6,959.16 0 SUBTOTAL BID ITEMS $ 657,559.89 0 CONTRACT TOTAL ALL ITEMS $ 657,559.89 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3124018 MGR.NO. PAGE 001 CONT 6231 SEC 69 JOB 001 RES ENGR SMITH, LARRY PROJ RMC - 623169001 HWY US0183 906 EAST MAIN EASTLAND CNTY STEPHENS DIST 23 CONTRACT PRICE $ 592,587.82 REPORT DATE 06/10/2013 14.32.42 CONTRACTOR ZACK BURKETT CO. 236 EST PERIOD JUL 30,2012 TO SEP 01,2012 EST NO 004 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 215 RMC - 623169001 6231-69-001 657,559.89 .00 657,559.89 .00 .00 657,559.89 657,559.89 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 657,559.89 .00 657,559.89 .00 .00 657,559.89 657,559.89 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3124018 MGR.NO. PAGE 001 CONT 6231 SEC 69 JOB 001 RES ENGR SMITH, LARRY PROJ RMC - 623169001 HWY US0183 906 EAST MAIN EASTLAND CNTY STEPHENS DIST 23 CONTRACT PRICE $ 592,587.82 REPORT DATE 06/10/2013 14.32.42 CONTRACTOR ZACK BURKETT CO. 236 EST PERIOD JUL 30,2012 TO SEP 01,2012 EST NO 004 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6231-69-001 RMC - 623169001 23 US0183 STEPHENS -LIMITS - JCT FM 2231, SOUTH JCT FM 1032 - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 657,559.89