1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2101603 MGR.NO. 056 PAGE 001 CONT 6203 SEC 82 JOB 001 RES ENGR CONDRA, RALPH PROJ RMC - 620382001 HWY US0059 800 S 181 KARNES CITY CNTY GOLIAD DIST 16 CONTRACT PRICE $ 159,638.08 REPORT DATE 01/30/2013 15.44.17 CONTRACTOR MISSOURI-TEXAS FARMS, LTD. 11803 EST PERIOD JUN 01,2010 TO JAN 04,2012 EST NO 021 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 01, 2010 TIME COMPUTED FROM JUN 04, 2010 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 603 579 577 2 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 12 1 1 TOTAL DAYS ALLOWED = 603 2 1 DATE WORK COMPLETED 01/04/12 3 1 DAYS CHARGED TO DATE = 580 4 1 WORK COMPLETED AND ACCEPTED ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 583 580 3 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2101603 MGR.NO. 056 PAGE 001 CONT 6203 SEC 82 JOB 001 RES ENGR CONDRA, RALPH PROJ RMC - 620382001 HWY US0059 800 S 181 KARNES CITY CNTY GOLIAD DIST 16 CONTRACT PRICE $ 159,638.08 REPORT DATE 01/30/2013 15.44.17 CONTRACTOR MISSOURI-TEXAS FARMS, LTD. 11803 EST PERIOD JUN 01,2010 TO JAN 04,2012 EST NO 021 & FINAL DIST. 16 COUNTY GOLIAD CONTROL 6203-82-001 PROJECT RMC - 620382001 HIGHWAY US0059 0LIMITS- VARIOUS . 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY KRISTI GILBERTSON 0 0055 MOWING HIGHWAY RIGHT OF WAY NET LENGTH277.056 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 2,024.000 1,012.000 14.430 14,603.16 0065 0730 FULL-WIDTH MOWING AC 9,032.000 9,032.000 14.430 130,331.76 0070 0730 SPOT MOWING AC 100.000 0.000 1.000 .00 0 SUBTOTAL BID ITEMS $ 144,934.92 0 TOTAL AMOUNT WORK DONE MOWING HIGHWAY RIGHT OF WAY $ 144,934.92 0 TOTAL AMOUNT WORK DONE CONTROL 6203-82-001 $ 144,934.92 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2101603 MGR.NO. 056 PAGE 001 CONT 6203 SEC 82 JOB 001 RES ENGR CONDRA, RALPH PROJ RMC - 620382001 HWY US0059 800 S 181 KARNES CITY CNTY GOLIAD DIST 16 CONTRACT PRICE $ 159,638.08 REPORT DATE 01/30/2013 15.44.17 CONTRACTOR MISSOURI-TEXAS FARMS, LTD. 11803 EST PERIOD JUN 01,2010 TO JAN 04,2012 EST NO 021 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 . DATE WORK BEGAN JUN 1 , 2010 WORKING DAYS USED 580 PERCENT COMPLETE 100.00 PERCENT TIME USED 96.10 DATE COMPLETED JAN 4 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6203-82-001 RMC - 620382001 16 US0059 GOLIAD - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 STRIP MOWING AC 2,024.000 1,012.000 14.430 14,603.16 0730 FULL-WIDTH MOWING AC 9,032.000 9,032.000 14.430 130,331.76 0 SUBTOTAL BID ITEMS $ 144,934.92 0 CONTRACT TOTAL ALL ITEMS $ 144,934.92 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2101603 MGR.NO. 056 PAGE 001 CONT 6203 SEC 82 JOB 001 RES ENGR CONDRA, RALPH PROJ RMC - 620382001 HWY US0059 800 S 181 KARNES CITY CNTY GOLIAD DIST 16 CONTRACT PRICE $ 159,638.08 REPORT DATE 01/30/2013 15.44.17 CONTRACTOR MISSOURI-TEXAS FARMS, LTD. 11803 EST PERIOD JUN 01,2010 TO JAN 04,2012 EST NO 021 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 89 RMC - 620382001 6203-82-001 144,934.92 .00 144,934.92 .00 .00 144,934.92 144,934.92 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 144,934.92 .00 144,934.92 .00 .00 144,934.92 144,934.92 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2101603 MGR.NO. 056 PAGE 001 CONT 6203 SEC 82 JOB 001 RES ENGR CONDRA, RALPH PROJ RMC - 620382001 HWY US0059 800 S 181 KARNES CITY CNTY GOLIAD DIST 16 CONTRACT PRICE $ 159,638.08 REPORT DATE 01/30/2013 15.44.17 CONTRACTOR MISSOURI-TEXAS FARMS, LTD. 11803 EST PERIOD JUN 01,2010 TO JAN 04,2012 EST NO 021 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6203-82-001 RMC - 620382001 16 US0059 GOLIAD -LIMITS - VARIOUS . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 144,934.92