1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10111606 MGR.NO. 050 PAGE 001 CONT 6230 SEC 87 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 623087001 HWY IH0037 1071 N.US 281 RR ALICE CNTY LIVE OAK DIST 16 CONTRACT PRICE $ 168,712.20 REPORT DATE 06/25/2014 07.19.18 CONTRACTOR ADVANCED PUMPING CONCEPTS, EST PERIOD NOV 29,2011 TO JAN 13,2012 EST NO 004 & FINAL INC. 15386 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 29, 2011 TIME COMPUTED FROM DEC 05, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 41 33 11 22 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 12 1 1 SUNDAY TOTAL DAYS ALLOWED = 41 2 1 DATE WORK COMPLETED 01/13/12 3 1 DAYS CHARGED TO DATE = 21 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 7 1 LIQUIDATED DAMAGES 8 1 SUNDAY 0 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 WORK COMPLETED AND ACCEPTED TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 46 21 25 0 SATURDAY 2 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10111606 MGR.NO. 050 PAGE 001 CONT 6230 SEC 87 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 623087001 HWY IH0037 1071 N.US 281 RR ALICE CNTY LIVE OAK DIST 16 CONTRACT PRICE $ 168,712.20 REPORT DATE 06/25/2014 07.19.19 CONTRACTOR ADVANCED PUMPING CONCEPTS, EST PERIOD NOV 29,2011 TO JAN 13,2012 EST NO 004 & FINAL INC. 15386 DIST. 16 COUNTY LIVE OAK CONTROL 6230-87-001 PROJECT RMC - 623087001 HIGHWAY IH0037 0LIMITS- VARIOUS LOCATIONS IN JIM WELLS KLEBERG AND LIVE OAK COUNTIES 0TYPE OF WORK- CRACK SEAL 0 0005 PREPARED BY ORLANDO J CARRILLO 0 0055 CRACK SEAL NET LENGTH419.560 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0712 JT/CRCK SEAL (RUBBER-ASPHALT) LMI 423.900 423.900 398.000 168,712.20 0 SUBTOTAL BID ITEMS $ 168,712.20 0 TOTAL AMOUNT WORK DONE CRACK SEAL $ 168,712.20 0 TOTAL AMOUNT WORK DONE CONTROL 6230-87-001 $ 168,712.20 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10111606 MGR.NO. 050 PAGE 001 CONT 6230 SEC 87 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 623087001 HWY IH0037 1071 N.US 281 RR ALICE CNTY LIVE OAK DIST 16 CONTRACT PRICE $ 168,712.20 REPORT DATE 06/25/2014 07.19.19 CONTRACTOR ADVANCED PUMPING CONCEPTS, EST PERIOD NOV 29,2011 TO JAN 13,2012 EST NO 004 & FINAL INC. 15386 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS IN JIM WELLS 0 KLEBERG AND LIVE OAK COUNTIES DATE WORK BEGAN NOV 29, 2011 WORKING DAYS USED 21 PERCENT COMPLETE 100.00 PERCENT TIME USED 51.20 DATE COMPLETED JAN 13 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6230-87-001 RMC - 623087001 16 IH0037 LIVE OAK - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0712 JT/CRCK SEAL (RUBBER-ASPHALT) LMI 423.900 423.900 398.000 168,712.20 0 SUBTOTAL BID ITEMS $ 168,712.20 0 CONTRACT TOTAL ALL ITEMS $ 168,712.20 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10111606 MGR.NO. 050 PAGE 001 CONT 6230 SEC 87 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 623087001 HWY IH0037 1071 N.US 281 RR ALICE CNTY LIVE OAK DIST 16 CONTRACT PRICE $ 168,712.20 REPORT DATE 06/25/2014 07.19.19 CONTRACTOR ADVANCED PUMPING CONCEPTS, EST PERIOD NOV 29,2011 TO JAN 13,2012 EST NO 004 & FINAL INC. 15386 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 149 RMC - 623087001 6230-87-001 168,712.20 .00 168,712.20 .00 .00 168,712.20 168,712.20 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 168,712.20 .00 168,712.20 .00 .00 168,712.20 168,712.20 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10111606 MGR.NO. 050 PAGE 001 CONT 6230 SEC 87 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 623087001 HWY IH0037 1071 N.US 281 RR ALICE CNTY LIVE OAK DIST 16 CONTRACT PRICE $ 168,712.20 REPORT DATE 06/25/2014 07.19.19 CONTRACTOR ADVANCED PUMPING CONCEPTS, EST PERIOD NOV 29,2011 TO JAN 13,2012 EST NO 004 & FINAL INC. 15386 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6230-87-001 RMC - 623087001 16 IH0037 LIVE OAK -LIMITS - VARIOUS LOCATIONS IN JIM WELLS KLEBERG AND LIVE OAK COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 168,712.20