1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8121602 MGR.NO. 050 PAGE 001 CONT 6241 SEC 63 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 624163001 HWY FM2510 1071 NORTH US 281,RR ALIC CNTY KLEBERG DIST 16 CONTRACT PRICE $ 230,375.00 REPORT DATE 12/02/2013 15.42.56 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD SEP 18,2012 TO OCT 03,2012 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 18, 2012 TIME COMPUTED FROM SEP 18, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 20 13 9 4 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 12 1 1 TOTAL DAYS ALLOWED = 20 2 1 DATE WORK COMPLETED 10/03/12 3 1 WORK COMPLETED AND ACCEPTED DAYS CHARGED TO DATE = 11 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 590 0 LIQUIDATED DAMAGES 0 DAYS AT $ 590 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 16 11 5 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8121602 MGR.NO. 050 PAGE 001 CONT 6241 SEC 63 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 624163001 HWY FM2510 1071 NORTH US 281,RR ALIC CNTY KLEBERG DIST 16 CONTRACT PRICE $ 230,375.00 REPORT DATE 12/02/2013 15.42.56 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD SEP 18,2012 TO OCT 03,2012 EST NO 003 & FINAL DIST. 16 COUNTY KLEBERG CONTROL 6241-63-001 PROJECT RMC - 624163001 HIGHWAY FM2510 0LIMITS- FM 771, SOUTH FM 1546 0TYPE OF WORK- BLADE LEVEL-UP 0 0005 PREPARED BY RUBEN GARCIA 0 0055 BLADE LEVEL-UP NET LENGTH 1.900 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 2,250.000 2,250.00 0065 0672 REFL PAV MRKR TY II-A-A EA 220.000 289.000 3.750 1,083.75 0065 0672 ADJ EST QUANTITY TO DATE 318.000 0070 3035 BLADE LEVEL-UP (LIMESTONE ROCK ASPHALT) CY 2,000.000 2,060.000 110.400 227,424.00 0070 3035 ADJ EST QUANTITY TO DATE 2,060.000 0075 8251 RE PM W/RET REQ TY I(Y)4"(BRK)(100MIL) LF 2,200.000 3,660.000 .650 2,379.00 0075 8251 ADJ EST QUANTITY TO DATE 3,660.000 0080 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(100MIL) LF 7,800.000 10,040.000 .650 6,526.00 0080 8251 ADJ EST QUANTITY TO DATE 10,040.000 0 SUBTOTAL BID ITEMS $ 239,662.75 0 TOTAL AMOUNT WORK DONE BLADE LEVEL-UP $ 239,662.75 0 TOTAL AMOUNT WORK DONE CONTROL 6241-63-001 $ 239,662.75 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8121602 MGR.NO. 050 PAGE 001 CONT 6241 SEC 63 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 624163001 HWY FM2510 1071 NORTH US 281,RR ALIC CNTY KLEBERG DIST 16 CONTRACT PRICE $ 230,375.00 REPORT DATE 12/02/2013 15.42.57 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD SEP 18,2012 TO OCT 03,2012 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - FM 771, SOUTH 0 FM 1546 DATE WORK BEGAN SEP 18, 2012 WORKING DAYS USED 11 PERCENT COMPLETE 100.00 PERCENT TIME USED 55.00 DATE COMPLETED OCT 3 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6241-63-001 RMC - 624163001 16 FM2510 KLEBERG - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 1.000 1.000 2,250.000 2,250.00 0672 REFL PAV MRKR TY II-A-A EA 220.000 289.000 3.750 1,083.75 0672 ADJ EST QUANTITY TO DATE 318.000 3035 BLADE LEVEL-UP (LIMESTONE ROCK ASPHALT) CY 2,000.000 2,060.000 110.400 227,424.00 3035 ADJ EST QUANTITY TO DATE 2,060.000 8251 RE PM W/RET REQ TY I(Y)4"(BRK)(100MIL) LF 2,200.000 3,660.000 .650 2,379.00 8251 ADJ EST QUANTITY TO DATE 3,660.000 8251 RE PM W/RET REQ TY I(Y)4"(SLD)(100MIL) LF 7,800.000 10,040.000 .650 6,526.00 8251 ADJ EST QUANTITY TO DATE 10,040.000 0 SUBTOTAL BID ITEMS $ 239,662.75 0 CONTRACT TOTAL ALL ITEMS $ 239,662.75 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8121602 MGR.NO. 050 PAGE 001 CONT 6241 SEC 63 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 624163001 HWY FM2510 1071 NORTH US 281,RR ALIC CNTY KLEBERG DIST 16 CONTRACT PRICE $ 230,375.00 REPORT DATE 12/02/2013 15.42.57 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD SEP 18,2012 TO OCT 03,2012 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 137 RMC - 624163001 6241-63-001 239,662.75 .00 239,662.75 .00 .00 239,662.75 239,662.75 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 239,662.75 .00 239,662.75 .00 .00 239,662.75 239,662.75 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8121602 MGR.NO. 050 PAGE 001 CONT 6241 SEC 63 JOB 001 RES ENGR TREVINO, TOMAS PROJ RMC - 624163001 HWY FM2510 1071 NORTH US 281,RR ALIC CNTY KLEBERG DIST 16 CONTRACT PRICE $ 230,375.00 REPORT DATE 12/02/2013 15.42.57 CONTRACTOR BICK'S CONSTRUCTION, INC. 3211 EST PERIOD SEP 18,2012 TO OCT 03,2012 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6241-63-001 RMC - 624163001 16 FM2510 KLEBERG -LIMITS - FM 771, SOUTH FM 1546 - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 239,662.75