1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2131841 MGR.NO. 003 PAGE 001 CONT 6251 SEC 35 JOB 001 RES ENGR WILLIAMS, PAUL PROJ EMC - 625135001 HWY LP0012 4777 E. HWY 80 MESQUITE CNTY DALLAS DIST 18 CONTRACT PRICE $ 296,000.00 REPORT DATE 04/03/2013 10.35.20 CONTRACTOR SILVER CREEK CONSTRUCTION, EST PERIOD FEB 08,2013 TO MAR 26,2013 EST NO 002 & FINAL INC. 06521 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN FEB 08, 2013 TIME COMPUTED FROM FEB 08, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 60 21 18 3 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 13 1 1 TOTAL DAYS ALLOWED = 60 2 1 DATE WORK COMPLETED 03/26/13 3 1 SUNDAY DAYS CHARGED TO DATE = 39 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 1,000 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 1,000 PER DAY 9 1 TOTAL = $ .00 10 1 SUNDAY 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 SUNDAY AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 SUNDAY 25 1 26 1 WORK COMPLETED AND ACCEPTED - - ----- ----- ----- 47 39 8 0 SATURDAY 4 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2131841 MGR.NO. 003 PAGE 001 CONT 6251 SEC 35 JOB 001 RES ENGR WILLIAMS, PAUL PROJ EMC - 625135001 HWY LP0012 4777 E. HWY 80 MESQUITE CNTY DALLAS DIST 18 CONTRACT PRICE $ 296,000.00 REPORT DATE 04/03/2013 10.35.21 CONTRACTOR SILVER CREEK CONSTRUCTION, EST PERIOD FEB 08,2013 TO MAR 26,2013 EST NO 002 & FINAL INC. 06521 DIST. 18 COUNTY DALLAS CONTROL 6251-35-001 PROJECT EMC - 625135001 HIGHWAY LP0012 0LIMITS- LP12 AT SOUTH FORK OF FIVE MILE CREEK 0TYPE OF WORK- EMERGENCY - BRIDGE REPAIR 0 0005 PREPARED BY PAUL E. WILLIAMS, P.E. 0 0055 EMERGENCY BRIDGE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 9054 REPAIR TO STRUCTURE LS 1.000 1.000 296,000.000 296,000.00 0 SUBTOTAL BID ITEMS $ 296,000.00 0 TOTAL AMOUNT WORK DONE EMERGENCY BRIDGE REPAIR $ 296,000.00 0 TOTAL AMOUNT WORK DONE CONTROL 6251-35-001 $ 296,000.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2131841 MGR.NO. 003 PAGE 001 CONT 6251 SEC 35 JOB 001 RES ENGR WILLIAMS, PAUL PROJ EMC - 625135001 HWY LP0012 4777 E. HWY 80 MESQUITE CNTY DALLAS DIST 18 CONTRACT PRICE $ 296,000.00 REPORT DATE 04/03/2013 10.35.21 CONTRACTOR SILVER CREEK CONSTRUCTION, EST PERIOD FEB 08,2013 TO MAR 26,2013 EST NO 002 & FINAL INC. 06521 0*********************************************************************************************************************************** -LIMITS - LP12 0 AT SOUTH FORK OF FIVE MILE CREEK DATE WORK BEGAN FEB 8 , 2013 WORKING DAYS USED 39 PERCENT COMPLETE 100.00 PERCENT TIME USED 65.00 DATE COMPLETED MAR 26 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6251-35-001 EMC - 625135001 18 LP0012 DALLAS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -9054 REPAIR TO STRUCTURE LS 1.000 1.000 296,000.000 296,000.00 0 SUBTOTAL BID ITEMS $ 296,000.00 0 CONTRACT TOTAL ALL ITEMS $ 296,000.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2131841 MGR.NO. 003 PAGE 001 CONT 6251 SEC 35 JOB 001 RES ENGR WILLIAMS, PAUL PROJ EMC - 625135001 HWY LP0012 4777 E. HWY 80 MESQUITE CNTY DALLAS DIST 18 CONTRACT PRICE $ 296,000.00 REPORT DATE 04/03/2013 10.35.21 CONTRACTOR SILVER CREEK CONSTRUCTION, EST PERIOD FEB 08,2013 TO MAR 26,2013 EST NO 002 & FINAL INC. 06521 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 57 EMC - 625135001 6251-35-001 296,000.00 .00 296,000.00 .00 .00 296,000.00 .00 296,000.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 296,000.00 .00 296,000.00 .00 .00 296,000.00 .00 296,000.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2131841 MGR.NO. 003 PAGE 001 CONT 6251 SEC 35 JOB 001 RES ENGR WILLIAMS, PAUL PROJ EMC - 625135001 HWY LP0012 4777 E. HWY 80 MESQUITE CNTY DALLAS DIST 18 CONTRACT PRICE $ 296,000.00 REPORT DATE 04/03/2013 10.35.21 CONTRACTOR SILVER CREEK CONSTRUCTION, EST PERIOD FEB 08,2013 TO MAR 26,2013 EST NO 002 & FINAL INC. 06521 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6251-35-001 EMC - 625135001 18 LP0012 DALLAS -LIMITS - LP12 AT SOUTH FORK OF FIVE MILE CREEK LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 9054 REPAIR TO STRUCTURE LS 1.000 1.000 296,000.000 296,000.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 296,000.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 296,000.00