1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4132405 MGR.NO. 770 PAGE 001 CONT 6255 SEC 93 JOB 001 RES ENGR CEDILLO,MARGIE PROJ RMC - 625593001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 126,092.00 REPORT DATE 11/08/2013 11.14.19 CONTRACTOR MLEE CORP. 15735 EST PERIOD JUN 17,2013 TO OCT 31,2013 EST NO 005 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 17, 2013 TIME COMPUTED FROM JUN 17, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 60 106 60 46 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 13 1 1 WORK SUSPENDED TOTAL DAYS ALLOWED = 60 2 1 WORK SUSPENDED DATE WORK COMPLETED 10/11/13 3 1 WORK SUSPENDED DAYS CHARGED TO DATE = 60 4 1 WORK SUSPENDED ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 590 6 1 SUNDAY 7 1 WORK SUSPENDED LIQUIDATED DAMAGES 8 1 WORK SUSPENDED 0 DAYS AT $ 590 PER DAY 9 1 WORK SUSPENDED TOTAL = $ .00 10 1 WORK SUSPENDED 11 1 WORK COMPLETED AND ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 117 60 57 1 SATURDAY 1 SUNDAY 0 HOLIDAY 8 WORK SUSPENDED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4132405 MGR.NO. 770 PAGE 001 CONT 6255 SEC 93 JOB 001 RES ENGR CEDILLO,MARGIE PROJ RMC - 625593001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 126,092.00 REPORT DATE 11/08/2013 11.14.20 CONTRACTOR MLEE CORP. 15735 EST PERIOD JUN 17,2013 TO OCT 31,2013 EST NO 005 & FINAL DIST. 24 COUNTY EL PASO CONTROL 6255-93-001 PROJECT RMC - 625593001 HIGHWAY IH0010 0LIMITS- VARIOUS LOCATIONS VARIOUS LOCATIONS 0TYPE OF WORK- CONCRETE CURB INSTALL AND REPAIR 0 0005 BOB BIELEK, P.E. DISTRICT ENGINEER 0010 EAO/WAO 0 0060 CONCRETE CURB INSTALL AND REPAIR NET LENGTH 3.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0065 0104 REMOVING CONC (CURB) LF 13,500.000 16,313.000 7.340 119,737.42 0070 0500 MOBILIZATION LS 1.000 1.000 1.010 1.01 0075 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 .330 .99 0080 0529 CONC CURB (MONO) (TY II) LF 13,500.000 15,216.000 2.000 30,432.00 0 SUBTOTAL BID ITEMS $ 150,171.42 0 TOTAL AMOUNT WORK DONE CONCRETE CURB INSTALL AND REPAIR $ 150,171.42 0 TOTAL AMOUNT WORK DONE CONTROL 6255-93-001 $ 150,171.42 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4132405 MGR.NO. 770 PAGE 001 CONT 6255 SEC 93 JOB 001 RES ENGR CEDILLO,MARGIE PROJ RMC - 625593001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 126,092.00 REPORT DATE 11/08/2013 11.14.20 CONTRACTOR MLEE CORP. 15735 EST PERIOD JUN 17,2013 TO OCT 31,2013 EST NO 005 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS 0 VARIOUS LOCATIONS DATE WORK BEGAN JUN 17, 2013 WORKING DAYS USED 60 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED OCT 11 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6255-93-001 RMC - 625593001 24 IH0010 EL PASO - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0104 REMOVING CONC (CURB) LF 13,500.000 16,313.000 7.340 119,737.42 0500 MOBILIZATION LS 1.000 1.000 1.010 1.01 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 3.000 .330 .99 0529 CONC CURB (MONO) (TY II) LF 13,500.000 15,216.000 2.000 30,432.00 0 SUBTOTAL BID ITEMS $ 150,171.42 0 CONTRACT TOTAL ALL ITEMS $ 150,171.42 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4132405 MGR.NO. 770 PAGE 001 CONT 6255 SEC 93 JOB 001 RES ENGR CEDILLO,MARGIE PROJ RMC - 625593001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 126,092.00 REPORT DATE 11/08/2013 11.14.20 CONTRACTOR MLEE CORP. 15735 EST PERIOD JUN 17,2013 TO OCT 31,2013 EST NO 005 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 72 RMC - 625593001 6255-93-001 150,171.42 .00 150,171.42 .00 .00 150,171.42 145,024.98 5,146.44 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 150,171.42 .00 150,171.42 .00 .00 150,171.42 145,024.98 5,146.44 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4132405 MGR.NO. 770 PAGE 001 CONT 6255 SEC 93 JOB 001 RES ENGR CEDILLO,MARGIE PROJ RMC - 625593001 HWY IH0010 13301 GATEWAY WEST EL PAS CNTY EL PASO DIST 24 CONTRACT PRICE $ 126,092.00 REPORT DATE 11/08/2013 11.14.21 CONTRACTOR MLEE CORP. 15735 EST PERIOD JUN 17,2013 TO OCT 31,2013 EST NO 005 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6255-93-001 RMC - 625593001 24 IH0010 EL PASO -LIMITS - VARIOUS LOCATIONS VARIOUS LOCATIONS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0104 REMOVING CONC (CURB) LF 13,500.000 551.000 7.340 4,044.34 70 0500 MOBILIZATION LS 1.000 0.100 1.010 0.10 80 0529 CONC CURB (MONO) (TY II) LF 13,500.000 551.000 2.000 1,102.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 5,146.44 0 TOTAL AMOUNT WORK DONE TO DATE - $ 150,171.42