1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7064024 MGR.NO. 060 PAGE 001 CONT 6145 SEC 90 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 614590001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 315,000.00 REPORT DATE 06/18/2013 16.31.32 CONTRACTOR JMI MAINTENANCE INC. 10088 EST PERIOD SEP 05,2006 TO AUG 17,2007 EST NO 013 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 06, 2006 TIME COMPUTED FROM SEP 05, 2006 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 330 330 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 07 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 08/17/07 3 1 DAYS CHARGED TO DATE = 347 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 WORK COMPLETED AND ACCEPTED AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 347 347 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7064024 MGR.NO. 060 PAGE 001 CONT 6145 SEC 90 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 614590001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 315,000.00 REPORT DATE 06/18/2013 16.31.32 CONTRACTOR JMI MAINTENANCE INC. 10088 EST PERIOD SEP 05,2006 TO AUG 17,2007 EST NO 013 & FINAL DIST. 12 COUNTY GALVESTON CONTROL 6145-90-001 PROJECT RMC - 614590001 HIGHWAY IH0045 0LIMITS- VARIOUS HWYS IN GALVESTON COUNTY VARIOUS HWYS IN GLAVESTON COUNTY 0TYPE OF WORK- DITCH CLEANING 0 0005 PREPARED BY JAMIE MEDINA 0 0055 DITCH CLEANING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0760 DITCH CLEAN/RESHAPING(CU YD IN VEHICLE) CY 60,000.000 74,183.413 5.250 389,462.92 0 SUBTOTAL BID ITEMS $ 389,462.92 0 TOTAL AMOUNT WORK DONE DITCH CLEANING $ 389,462.92 0 TOTAL AMOUNT WORK DONE CONTROL 6145-90-001 $ 389,462.92 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7064024 MGR.NO. 060 PAGE 001 CONT 6145 SEC 90 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 614590001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 315,000.00 REPORT DATE 06/18/2013 16.31.32 CONTRACTOR JMI MAINTENANCE INC. 10088 EST PERIOD SEP 05,2006 TO AUG 17,2007 EST NO 013 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN GALVESTON COUNTY 0 VARIOUS HWYS IN GLAVESTON COUNTY DATE WORK BEGAN SEP 6 , 2006 WORKING DAYS USED 347 PERCENT COMPLETE 100.00 PERCENT TIME USED 95.00 DATE COMPLETED AUG 17 2007 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6145-90-001 RMC - 614590001 12 IH0045 GALVESTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0760 DITCH CLEAN/RESHAPING(CU YD IN VEHICLE) CY 60,000.000 74,183.413 5.250 389,462.92 0 SUBTOTAL BID ITEMS $ 389,462.92 0 CONTRACT TOTAL ALL ITEMS $ 389,462.92 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7064024 MGR.NO. 060 PAGE 001 CONT 6145 SEC 90 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 614590001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 315,000.00 REPORT DATE 06/18/2013 16.31.32 CONTRACTOR JMI MAINTENANCE INC. 10088 EST PERIOD SEP 05,2006 TO AUG 17,2007 EST NO 013 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 RMC - 614590001 6145-90-001 389,462.92 .00 389,462.92 .00 .00 389,462.92 389,462.92 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 389,462.92 .00 389,462.92 .00 .00 389,462.92 389,462.92 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7064024 MGR.NO. 060 PAGE 001 CONT 6145 SEC 90 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 614590001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 315,000.00 REPORT DATE 06/18/2013 16.31.32 CONTRACTOR JMI MAINTENANCE INC. 10088 EST PERIOD SEP 05,2006 TO AUG 17,2007 EST NO 013 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6145-90-001 RMC - 614590001 12 IH0045 GALVESTON -LIMITS - VARIOUS HWYS IN GALVESTON COUNTY VARIOUS HWYS IN GLAVESTON COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 389,462.92