1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12071230 MGR.NO. 060 PAGE 001 CONT 6173 SEC 22 JOB 001 RES ENGR BABBINGTON,WILLIAM PROJ SUP - 617322001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 153,805.75 REPORT DATE 08/26/2013 16.34.00 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2008 TO DEC 31,2008 EST NO 013 & FINAL THE TEXAS HOUSE 09728 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JAN 08, 2008 TIME COMPUTED FROM JAN 01, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 366 335 335 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 08 1 1 TOTAL DAYS ALLOWED = 366 2 1 DATE WORK COMPLETED 12/31/08 3 1 DAYS CHARGED TO DATE = 366 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 366 366 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12071230 MGR.NO. 060 PAGE 001 CONT 6173 SEC 22 JOB 001 RES ENGR BABBINGTON,WILLIAM PROJ SUP - 617322001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 153,805.75 REPORT DATE 08/26/2013 16.34.00 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2008 TO DEC 31,2008 EST NO 013 & FINAL THE TEXAS HOUSE 09728 DIST. 12 COUNTY GALVESTON CONTROL 6173-22-001 PROJECT SUP - 617322001 HIGHWAY IH0045 0LIMITS- VARIOUS HWYS IN GALVESTON COUNTY VARIOUS HWYS IN GALVESTON COUNTY 0TYPE OF WORK- LITTER REMOVAL 0 0005 PREPARED BY JAMIE MEDINA 0 0055 LITTER REMOVAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL(SPOT) AC 1,000.000 16.000 13.000 208.00 0065 0734 LITTER REMOVAL - TRACT (1) CYC 6.000 6.000 214.470 1,286.82 0070 0734 LITTER REMOVAL - TRACT (2) CYC 6.000 6.000 26.820 160.92 0075 0734 LITTER REMOVAL - TRACT (3) CYC 2.000 2.000 2,585.600 5,171.20 0080 0734 LITTER REMOVAL - TRACT (4) CYC 2.000 2.000 228.020 456.04 0085 0734 LITTER REMOVAL - TRACT (5) CYC 2.000 2.000 110.210 220.42 0090 0734 LITTER REMOVAL - TRACT (6) CYC 6.000 6.000 643.780 3,862.68 0095 0734 LITTER REMOVAL - TRACT (7) CYC 8.000 8.000 89.610 716.88 0100 0734 LITTER REMOVAL - TRACT (8) CYC 4.000 4.000 1,198.770 4,795.08 0105 0734 LITTER REMOVAL - TRACT (9) CYC 2.000 2.000 1,266.450 2,532.90 0110 0734 LITTER REMOVAL - TRACT (10) CYC 6.000 6.000 125.590 753.54 0115 0734 LITTER REMOVAL - TRACT (11) CYC 8.000 8.000 1,106.120 8,848.96 0120 0734 LITTER REMOVAL - TRACT (12) CYC 17.000 17.000 3,540.380 60,186.46 0125 0734 LITTER REMOVAL - TRACT (13) CYC 3.000 2.000 2,505.530 5,011.06 0125 0734 ADJ EST QUANTITY TO DATE 2.000 0130 0734 LITTER REMOVAL - TRACT (14) CYC 2.000 2.000 488.920 977.84 0135 0734 LITTER REMOVAL - TRACT (15) CYC 2.000 2.000 310.840 621.68 0140 0734 LITTER REMOVAL - TRACT (16) CYC 12.000 12.000 361.670 4,340.04 0145 0734 LITTER REMOVAL - TRACT (17) CYC 12.000 12.000 470.760 5,649.12 0150 0734 LITTER REMOVAL - TRACT (18) CYC 6.000 6.000 134.980 809.88 0155 0734 LITTER REMOVAL - TRACT (19) CYC 5.000 5.000 204.410 1,022.05 0160 0734 LITTER REMOVAL - TRACT (20) CYC 12.000 12.000 435.800 5,229.60 0165 0734 LITTER REMOVAL - TRACT (21) CYC 3.000 3.000 352.740 1,058.22 0170 0734 LITTER REMOVAL - TRACT (22) CYC 8.000 8.000 255.690 2,045.52 0175 0734 LITTER REMOVAL - TRACT (23) CYC 6.000 6.000 1,536.030 9,216.18 0180 0734 LITTER REMOVAL - TRACT (24) CYC 6.000 6.000 49.200 295.20 0185 0734 LITTER REMOVAL - TRACT (25) CYC 3.000 3.000 1,815.510 5,446.53 0190 0734 LITTER REMOVAL - TRACT (26) CYC 4.000 4.000 143.550 574.20 0195 0734 LITTER REMOVAL - TRACT (27) CYC 4.000 4.000 1,237.110 4,948.44 1 0200 0734 LITTER REMOVAL - TRACT (28) CYC 2.000 2.000 87.020 174.04 0205 0734 LITTER REMOVAL - TRACT (29) CYC 2.000 1.000 628.300 628.30 0210 0734 LITTER REMOVAL - TRACT (30) CYC 4.000 4.000 141.450 565.80 0215 0734 LITTER REMOVAL - TRACT (31) CYC 2.000 2.000 33.160 66.32 0216 9000*REVETMENT @ SH 87 CLEAN UP CYC 6.000 2.000 3,150.000 6,300.00 0217 9000*MINIMUM WAGE INCREASE EA 8,555.610 6,667.520 1.000 6,667.52 0218 9000*IH 45 DEBRIS REMOVAL DUE TO HURRICANE LS 1.000 1.000 10,620.000 10,620.00 0 SUBTOTAL BID ITEMS $ 161,467.44 0 TOTAL AMOUNT WORK DONE LITTER REMOVAL $ 161,467.44 0 TOTAL AMOUNT WORK DONE CONTROL 6173-22-001 $ 161,467.44 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12071230 MGR.NO. 060 PAGE 001 CONT 6173 SEC 22 JOB 001 RES ENGR BABBINGTON,WILLIAM PROJ SUP - 617322001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 153,805.75 REPORT DATE 08/26/2013 16.34.00 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2008 TO DEC 31,2008 EST NO 013 & FINAL THE TEXAS HOUSE 09728 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN GALVESTON COUNTY 0 VARIOUS HWYS IN GALVESTON COUNTY DATE WORK BEGAN JAN 8 , 2008 WORKING DAYS USED 366 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED DEC 31 2008 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6173-22-001 SUP - 617322001 12 IH0045 GALVESTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL(SPOT) AC 1,000.000 16.000 13.000 208.00 0734 LITTER REMOVAL - TRACT (1) CYC 6.000 6.000 214.470 1,286.82 0734 LITTER REMOVAL - TRACT (2) CYC 6.000 6.000 26.820 160.92 0734 LITTER REMOVAL - TRACT (3) CYC 2.000 2.000 2,585.600 5,171.20 0734 LITTER REMOVAL - TRACT (4) CYC 2.000 2.000 228.020 456.04 0734 LITTER REMOVAL - TRACT (5) CYC 2.000 2.000 110.210 220.42 0734 LITTER REMOVAL - TRACT (6) CYC 6.000 6.000 643.780 3,862.68 0734 LITTER REMOVAL - TRACT (7) CYC 8.000 8.000 89.610 716.88 0734 LITTER REMOVAL - TRACT (8) CYC 4.000 4.000 1,198.770 4,795.08 0734 LITTER REMOVAL - TRACT (9) CYC 2.000 2.000 1,266.450 2,532.90 0734 LITTER REMOVAL - TRACT (10) CYC 6.000 6.000 125.590 753.54 0734 LITTER REMOVAL - TRACT (11) CYC 8.000 8.000 1,106.120 8,848.96 0734 LITTER REMOVAL - TRACT (12) CYC 17.000 17.000 3,540.380 60,186.46 0734 LITTER REMOVAL - TRACT (13) CYC 3.000 2.000 2,505.530 5,011.06 0734 ADJ EST QUANTITY TO DATE 2.000 0734 LITTER REMOVAL - TRACT (14) CYC 2.000 2.000 488.920 977.84 0734 LITTER REMOVAL - TRACT (15) CYC 2.000 2.000 310.840 621.68 0734 LITTER REMOVAL - TRACT (16) CYC 12.000 12.000 361.670 4,340.04 0734 LITTER REMOVAL - TRACT (17) CYC 12.000 12.000 470.760 5,649.12 0734 LITTER REMOVAL - TRACT (18) CYC 6.000 6.000 134.980 809.88 0734 LITTER REMOVAL - TRACT (19) CYC 5.000 5.000 204.410 1,022.05 0734 LITTER REMOVAL - TRACT (20) CYC 12.000 12.000 435.800 5,229.60 0734 LITTER REMOVAL - TRACT (21) CYC 3.000 3.000 352.740 1,058.22 0734 LITTER REMOVAL - TRACT (22) CYC 8.000 8.000 255.690 2,045.52 0734 LITTER REMOVAL - TRACT (23) CYC 6.000 6.000 1,536.030 9,216.18 10734 LITTER REMOVAL - TRACT (24) CYC 6.000 6.000 49.200 295.20 0734 LITTER REMOVAL - TRACT (25) CYC 3.000 3.000 1,815.510 5,446.53 0734 LITTER REMOVAL - TRACT (26) CYC 4.000 4.000 143.550 574.20 0734 LITTER REMOVAL - TRACT (27) CYC 4.000 4.000 1,237.110 4,948.44 0734 LITTER REMOVAL - TRACT (28) CYC 2.000 2.000 87.020 174.04 0734 LITTER REMOVAL - TRACT (29) CYC 2.000 1.000 628.300 628.30 0734 LITTER REMOVAL - TRACT (30) CYC 4.000 4.000 141.450 565.80 0734 LITTER REMOVAL - TRACT (31) CYC 2.000 2.000 33.160 66.32 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09000* REVETMENT @ SH 87 CLEAN UP CYC 6.000 2.000 3,150.000 6,300.00 9000* MINIMUM WAGE INCREASE EA 8,555.610 6,667.520 1.000 6,667.52 9000* IH 45 DEBRIS REMOVAL DUE TO HURRICANE LS 1.000 1.000 10,620.000 10,620.00 0 SUBTOTAL BID ITEMS $ 161,467.44 0 CONTRACT TOTAL ALL ITEMS $ 161,467.44 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12071230 MGR.NO. 060 PAGE 001 CONT 6173 SEC 22 JOB 001 RES ENGR BABBINGTON,WILLIAM PROJ SUP - 617322001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 153,805.75 REPORT DATE 08/26/2013 16.34.00 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2008 TO DEC 31,2008 EST NO 013 & FINAL THE TEXAS HOUSE 09728 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 SUP - 617322001 6173-22-001 161,467.44 .00 161,467.44 .00 .00 161,467.44 161,467.44 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 161,467.44 .00 161,467.44 .00 .00 161,467.44 161,467.44 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12071230 MGR.NO. 060 PAGE 001 CONT 6173 SEC 22 JOB 001 RES ENGR BABBINGTON,WILLIAM PROJ SUP - 617322001 HWY IH0045 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 153,805.75 REPORT DATE 08/26/2013 16.34.01 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JAN 01,2008 TO DEC 31,2008 EST NO 013 & FINAL THE TEXAS HOUSE 09728 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6173-22-001 SUP - 617322001 12 IH0045 GALVESTON -LIMITS - VARIOUS HWYS IN GALVESTON COUNTY VARIOUS HWYS IN GALVESTON COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 161,467.44