1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9081230 MGR.NO. 052 PAGE 001 CONT 6184 SEC 48 JOB 001 RES ENGR ALLEN, QUINCY PROJ SUP - 618448001 HWY IH0010 7303 MESA HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 90,000.00 REPORT DATE 08/23/2013 14.01.51 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 22,2008 TO JUL 14,2009 EST NO 012 & FINAL D & D HELPING OTHERS, INC. 09775 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 22, 2008 TIME COMPUTED FROM SEP 22, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 282 282 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 09 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 07/14/09 3 1 DAYS CHARGED TO DATE = 296 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 0 ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 296 296 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9081230 MGR.NO. 052 PAGE 001 CONT 6184 SEC 48 JOB 001 RES ENGR ALLEN, QUINCY PROJ SUP - 618448001 HWY IH0010 7303 MESA HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 90,000.00 REPORT DATE 08/23/2013 14.01.52 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 22,2008 TO JUL 14,2009 EST NO 012 & FINAL D & D HELPING OTHERS, INC. 09775 DIST. 12 COUNTY HARRIS CONTROL 6184-48-001 PROJECT SUP - 618448001 HIGHWAY IH0010 0LIMITS- 500 FT SOUTH OF NEW ROAD CEDAR BAYOU 0TYPE OF WORK- TREE AND BRUSH REMOVAL (CHANNELS) 0 0050 TREE AND BRUSH REMOVAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY RHONDA K. LANGE 0 0075 0752 TREE TRIMMING/BRUSH REMOVAL(CHANNELS) AC 60.000 56.000 1,500.000 84,000.00 0 SUBTOTAL BID ITEMS $ 84,000.00 0 TOTAL AMOUNT WORK DONE TREE AND BRUSH REMOVAL $ 84,000.00 0 TOTAL AMOUNT WORK DONE CONTROL 6184-48-001 $ 84,000.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9081230 MGR.NO. 052 PAGE 001 CONT 6184 SEC 48 JOB 001 RES ENGR ALLEN, QUINCY PROJ SUP - 618448001 HWY IH0010 7303 MESA HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 90,000.00 REPORT DATE 08/23/2013 14.01.52 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 22,2008 TO JUL 14,2009 EST NO 012 & FINAL D & D HELPING OTHERS, INC. 09775 0*********************************************************************************************************************************** -LIMITS - 500 FT SOUTH OF NEW ROAD 0 CEDAR BAYOU DATE WORK BEGAN SEP 22, 2008 WORKING DAYS USED 296 PERCENT COMPLETE 100.00 PERCENT TIME USED 81.00 DATE COMPLETED JUL 14 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6184-48-001 SUP - 618448001 12 IH0010 HARRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0752 TREE TRIMMING/BRUSH REMOVAL(CHANNELS) AC 60.000 56.000 1,500.000 84,000.00 0 SUBTOTAL BID ITEMS $ 84,000.00 0 CONTRACT TOTAL ALL ITEMS $ 84,000.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9081230 MGR.NO. 052 PAGE 001 CONT 6184 SEC 48 JOB 001 RES ENGR ALLEN, QUINCY PROJ SUP - 618448001 HWY IH0010 7303 MESA HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 90,000.00 REPORT DATE 08/23/2013 14.01.52 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 22,2008 TO JUL 14,2009 EST NO 012 & FINAL D & D HELPING OTHERS, INC. 09775 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 SUP - 618448001 6184-48-001 84,000.00 .00 84,000.00 .00 .00 84,000.00 84,000.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 84,000.00 .00 84,000.00 .00 .00 84,000.00 84,000.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9081230 MGR.NO. 052 PAGE 001 CONT 6184 SEC 48 JOB 001 RES ENGR ALLEN, QUINCY PROJ SUP - 618448001 HWY IH0010 7303 MESA HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 90,000.00 REPORT DATE 08/23/2013 14.01.52 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD SEP 22,2008 TO JUL 14,2009 EST NO 012 & FINAL D & D HELPING OTHERS, INC. 09775 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6184-48-001 SUP - 618448001 12 IH0010 HARRIS -LIMITS - 500 FT SOUTH OF NEW ROAD CEDAR BAYOU - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 84,000.00