1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11081245 MGR.NO. 060 PAGE 001 CONT 6190 SEC 42 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ EMC - 619042001 HWY SH0087 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 888,000.00 REPORT DATE 11/12/2013 16.41.08 CONTRACTOR BYRD BROTHERS INCORPORATED 10922 EST PERIOD DEC 13,2008 TO JAN 11,2009 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN DEC 15, 2008 TIME COMPUTED FROM DEC 13, 2008 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 19 19 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 09 1 1 TOTAL DAYS ALLOWED = 30 2 1 DATE WORK COMPLETED 01/11/09 3 1 DAYS CHARGED TO DATE = 30 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 500 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 WORK COMPLETED AND ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 30 30 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11081245 MGR.NO. 060 PAGE 001 CONT 6190 SEC 42 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ EMC - 619042001 HWY SH0087 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 888,000.00 REPORT DATE 11/12/2013 16.41.08 CONTRACTOR BYRD BROTHERS INCORPORATED 10922 EST PERIOD DEC 13,2008 TO JAN 11,2009 EST NO 003 & FINAL DIST. 12 COUNTY GALVESTON CONTROL 6190-42-001 PROJECT EMC - 619042001 HIGHWAY SH0087 0LIMITS- VARIOUS HWYS ON BOLIVAR PENINSULA VARIOUS HWYS ON BOLIVAR PENINSULA 0TYPE OF WORK- EMERGENCY DEBRIS REMOVAL AND DISPOSAL 0 0005 PREPARED BY JAMIE MEDINA 0 0055 EMERGENCY ROADWAY DEBRIS REMOVAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7431 DEBRIS REMOVAL AND DISPOSAL CY 50,000.000 24,091.129 17.760 427,858.45 0 SUBTOTAL BID ITEMS $ 427,858.45 0 TOTAL AMOUNT WORK DONE EMERGENCY ROADWAY DEBRIS REMOVAL $ 427,858.45 0 TOTAL AMOUNT WORK DONE CONTROL 6190-42-001 $ 427,858.45 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11081245 MGR.NO. 060 PAGE 001 CONT 6190 SEC 42 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ EMC - 619042001 HWY SH0087 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 888,000.00 REPORT DATE 11/12/2013 16.41.08 CONTRACTOR BYRD BROTHERS INCORPORATED 10922 EST PERIOD DEC 13,2008 TO JAN 11,2009 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS ON BOLIVAR PENINSULA 0 VARIOUS HWYS ON BOLIVAR PENINSULA DATE WORK BEGAN DEC 15, 2008 WORKING DAYS USED 30 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED JAN 11 2009 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6190-42-001 EMC - 619042001 12 SH0087 GALVESTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7431 DEBRIS REMOVAL AND DISPOSAL CY 50,000.000 24,091.129 17.760 427,858.45 0 SUBTOTAL BID ITEMS $ 427,858.45 0 CONTRACT TOTAL ALL ITEMS $ 427,858.45 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11081245 MGR.NO. 060 PAGE 001 CONT 6190 SEC 42 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ EMC - 619042001 HWY SH0087 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 888,000.00 REPORT DATE 11/12/2013 16.41.08 CONTRACTOR BYRD BROTHERS INCORPORATED 10922 EST PERIOD DEC 13,2008 TO JAN 11,2009 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 EMC - 619042001 6190-42-001 427,858.45 .00 427,858.45 .00 .00 427,858.45 427,858.45 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 427,858.45 .00 427,858.45 .00 .00 427,858.45 427,858.45 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11081245 MGR.NO. 060 PAGE 001 CONT 6190 SEC 42 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ EMC - 619042001 HWY SH0087 5407 GULF FREEWAY LAMARQU CNTY GALVESTON DIST 12 CONTRACT PRICE $ 888,000.00 REPORT DATE 11/12/2013 16.41.08 CONTRACTOR BYRD BROTHERS INCORPORATED 10922 EST PERIOD DEC 13,2008 TO JAN 11,2009 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6190-42-001 EMC - 619042001 12 SH0087 GALVESTON -LIMITS - VARIOUS HWYS ON BOLIVAR PENINSULA VARIOUS HWYS ON BOLIVAR PENINSULA - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 427,858.45