1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6091206 MGR.NO. 060 PAGE 001 CONT 6195 SEC 24 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 619524001 HWY IH0045 5407 GULF FREEWAY LA MARQ CNTY GALVESTON DIST 12 CONTRACT PRICE $ 244,395.00 REPORT DATE 12/27/2013 15.58.23 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD SEP 01,2009 TO AUG 31,2010 EST NO 013 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 23, 2009 TIME COMPUTED FROM SEP 01, 2009 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 334 334 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 10 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 08/31/10 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 WORK COMPLETED AND ACCEPTED ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6091206 MGR.NO. 060 PAGE 001 CONT 6195 SEC 24 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 619524001 HWY IH0045 5407 GULF FREEWAY LA MARQ CNTY GALVESTON DIST 12 CONTRACT PRICE $ 244,395.00 REPORT DATE 12/27/2013 15.58.23 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD SEP 01,2009 TO AUG 31,2010 EST NO 013 & FINAL INC. 00644 DIST. 12 COUNTY GALVESTON CONTROL 6195-24-001 PROJECT RMC - 619524001 HIGHWAY IH0045 0LIMITS- VARIOUS HWYS IN GALVESTON VARIOUS HWYS IN GALVESTON 0TYPE OF WORK- ASPHALT PAVEMENT REPAIR 0 0005 PREPARED BY JAMIE MEDINA 0 0055 ASPHALT PAVEMENT REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 4,700.000 5,827.561 32.850 191,435.38 0065 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 2,000.000 1,991.103 45.000 89,599.64 0 SUBTOTAL BID ITEMS $ 281,035.02 0 TOTAL AMOUNT WORK DONE ASPHALT PAVEMENT REPAIR $ 281,035.02 0 0115 CONTRACTOR FORCE ACCOUNT WORK NET LENGTH 0.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0116 POLICE OFFICERS FOR TRAFFIC CONTROL 0 TOTAL AMOUNT WORK DONE CONTRACTOR FORCE ACCOUNT WORK $ .00 0 TOTAL AMOUNT WORK DONE CONTROL 6195-24-001 $ 281,035.02 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6091206 MGR.NO. 060 PAGE 001 CONT 6195 SEC 24 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 619524001 HWY IH0045 5407 GULF FREEWAY LA MARQ CNTY GALVESTON DIST 12 CONTRACT PRICE $ 244,395.00 REPORT DATE 12/27/2013 15.58.23 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD SEP 01,2009 TO AUG 31,2010 EST NO 013 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - VARIOUS HWYS IN GALVESTON 0 VARIOUS HWYS IN GALVESTON DATE WORK BEGAN NOV 23, 2009 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED AUG 31 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6195-24-001 RMC - 619524001 12 IH0045 GALVESTON - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") SY 4,700.000 5,827.561 32.850 191,435.38 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") SY 2,000.000 1,991.103 45.000 89,599.64 0 SUBTOTAL BID ITEMS $ 281,035.02 0 CONTRACT TOTAL ALL ITEMS $ 281,035.02 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6091206 MGR.NO. 060 PAGE 001 CONT 6195 SEC 24 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 619524001 HWY IH0045 5407 GULF FREEWAY LA MARQ CNTY GALVESTON DIST 12 CONTRACT PRICE $ 244,395.00 REPORT DATE 12/27/2013 15.58.23 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD SEP 01,2009 TO AUG 31,2010 EST NO 013 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 85 RMC - 619524001 6195-24-001 281,035.02 .00 281,035.02 .00 .00 281,035.02 281,035.02 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 281,035.02 .00 281,035.02 .00 .00 281,035.02 281,035.02 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6091206 MGR.NO. 060 PAGE 001 CONT 6195 SEC 24 JOB 001 RES ENGR BABBINGTON, WILLIAM PROJ RMC - 619524001 HWY IH0045 5407 GULF FREEWAY LA MARQ CNTY GALVESTON DIST 12 CONTRACT PRICE $ 244,395.00 REPORT DATE 12/27/2013 15.58.23 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD SEP 01,2009 TO AUG 31,2010 EST NO 013 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6195-24-001 RMC - 619524001 12 IH0045 GALVESTON -LIMITS - VARIOUS HWYS IN GALVESTON VARIOUS HWYS IN GALVESTON - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 281,035.02