1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 5101233 MGR.NO. 058 PAGE 001 CONT 6208 SEC 04 JOB 001 RES ENGR RANFT, GREGORY PROJ SUP - 620804001 HWY IH0010 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 124,368.52 REPORT DATE 09/12/2014 09.00.56 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2010 TO MAY 31,2011 EST NO 013 & FINAL DAVID & IVORY MINISTRIES 12716 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 10, 2010 TIME COMPUTED FROM JUN 01, 2010 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 334 334 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAY 11 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 05/31/11 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 5101233 MGR.NO. 058 PAGE 001 CONT 6208 SEC 04 JOB 001 RES ENGR RANFT, GREGORY PROJ SUP - 620804001 HWY IH0010 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 124,368.52 REPORT DATE 09/12/2014 09.00.56 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2010 TO MAY 31,2011 EST NO 013 & FINAL DAVID & IVORY MINISTRIES 12716 DIST. 12 COUNTY WALLER CONTROL 6208-04-001 PROJECT SUP - 620804001 HIGHWAY IH0010 0LIMITS- VARIOUS ROADWAYS IN WALLER COUNTY VARIOUS ROADWAYS IN WALLER COUNTY 0TYPE OF WORK- LITTER REMOVAL 0 0050 LITTER REMOVAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY TROY WAWAROFSKY 0 0075 0734 LITTER REMOVAL AC 100.000 0.000 11.000 .00 0080 0734 LITTER REMOVAL - TRACT (1) CYC 4.000 3.640 1,033.790 3,763.00 0085 0734 LITTER REMOVAL - TRACT (2) CYC 4.000 3.000 676.200 2,028.60 0090 0734 LITTER REMOVAL - TRACT (3) CYC 6.000 6.000 173.840 1,043.04 0095 0734 LITTER REMOVAL - TRACT (4) CYC 4.000 3.320 691.310 2,295.15 0100 0734 LITTER REMOVAL - TRACT (5) CYC 12.000 12.000 104.230 1,250.76 0105 0734 LITTER REMOVAL - TRACT (6) CYC 6.000 6.000 3,701.490 22,208.94 0110 0734 LITTER REMOVAL - TRACT (7) CYC 8.000 3.520 604.040 2,126.22 0115 0734 LITTER REMOVAL - TRACT (8) CYC 6.000 6.000 3,957.310 23,743.86 0120 0734 LITTER REMOVAL - TRACT (9) CYC 6.000 3.540 798.190 2,825.59 0125 0734 LITTER REMOVAL - TRACT (10) CYC 6.000 6.000 1,351.190 8,107.14 0130 0734 LITTER REMOVAL - TRACT (11) CYC 6.000 6.000 344.740 2,068.44 0135 0734 LITTER REMOVAL - TRACT (12) CYC 6.000 6.000 183.670 1,102.02 0140 0734 LITTER REMOVAL - TRACT (13) CYC 6.000 4.120 1,445.170 5,954.10 0145 0734 LITTER REMOVAL - TRACT (14) CYC 6.000 4.680 2,094.910 9,804.18 0150 0734 LITTER REMOVAL - TRACT (15) CYC 6.000 6.000 1,024.160 6,144.96 0155 0734 LITTER REMOVAL - TRACT (16) CYC 6.000 3.060 1,491.960 4,565.40 0160 0734 LITTER REMOVAL - TRACT (17) CYC 4.000 5.000 390.910 1,954.55 0165 0734 LITTER REMOVAL - TRACT (18) CYC 6.000 4.020 412.750 1,659.26 0170 0734 LITTER REMOVAL - TRACT (19) CYC 4.000 3.530 251.370 887.34 0175 0734 LITTER REMOVAL - TRACT (20) CYC 4.000 2.960 783.710 2,319.78 0 SUBTOTAL BID ITEMS $ 105,852.33 0 TOTAL AMOUNT WORK DONE LITTER REMOVAL $ 105,852.33 0 TOTAL AMOUNT WORK DONE CONTROL 6208-04-001 $ 105,852.33 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 5101233 MGR.NO. 058 PAGE 001 CONT 6208 SEC 04 JOB 001 RES ENGR RANFT, GREGORY PROJ SUP - 620804001 HWY IH0010 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 124,368.52 REPORT DATE 09/12/2014 09.00.57 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2010 TO MAY 31,2011 EST NO 013 & FINAL DAVID & IVORY MINISTRIES 12716 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN WALLER COUNTY 0 VARIOUS ROADWAYS IN WALLER COUNTY DATE WORK BEGAN JUN 10, 2010 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED MAY 31 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6208-04-001 SUP - 620804001 12 IH0010 WALLER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL - TRACT (1) CYC 4.000 3.640 1,033.790 3,763.00 0734 LITTER REMOVAL - TRACT (2) CYC 4.000 3.000 676.200 2,028.60 0734 LITTER REMOVAL - TRACT (3) CYC 6.000 6.000 173.840 1,043.04 0734 LITTER REMOVAL - TRACT (4) CYC 4.000 3.320 691.310 2,295.15 0734 LITTER REMOVAL - TRACT (5) CYC 12.000 12.000 104.230 1,250.76 0734 LITTER REMOVAL - TRACT (6) CYC 6.000 6.000 3,701.490 22,208.94 0734 LITTER REMOVAL - TRACT (7) CYC 8.000 3.520 604.040 2,126.22 0734 LITTER REMOVAL - TRACT (8) CYC 6.000 6.000 3,957.310 23,743.86 0734 LITTER REMOVAL - TRACT (9) CYC 6.000 3.540 798.190 2,825.59 0734 LITTER REMOVAL - TRACT (10) CYC 6.000 6.000 1,351.190 8,107.14 0734 LITTER REMOVAL - TRACT (11) CYC 6.000 6.000 344.740 2,068.44 0734 LITTER REMOVAL - TRACT (12) CYC 6.000 6.000 183.670 1,102.02 0734 LITTER REMOVAL - TRACT (13) CYC 6.000 4.120 1,445.170 5,954.10 0734 LITTER REMOVAL - TRACT (14) CYC 6.000 4.680 2,094.910 9,804.18 0734 LITTER REMOVAL - TRACT (15) CYC 6.000 6.000 1,024.160 6,144.96 0734 LITTER REMOVAL - TRACT (16) CYC 6.000 3.060 1,491.960 4,565.40 0734 LITTER REMOVAL - TRACT (17) CYC 4.000 5.000 390.910 1,954.55 0734 LITTER REMOVAL - TRACT (18) CYC 6.000 4.020 412.750 1,659.26 0734 LITTER REMOVAL - TRACT (19) CYC 4.000 3.530 251.370 887.34 0734 LITTER REMOVAL - TRACT (20) CYC 4.000 2.960 783.710 2,319.78 0 SUBTOTAL BID ITEMS $ 105,852.33 0 CONTRACT TOTAL ALL ITEMS $ 105,852.33 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 5101233 MGR.NO. 058 PAGE 001 CONT 6208 SEC 04 JOB 001 RES ENGR RANFT, GREGORY PROJ SUP - 620804001 HWY IH0010 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 124,368.52 REPORT DATE 09/12/2014 09.00.57 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2010 TO MAY 31,2011 EST NO 013 & FINAL DAVID & IVORY MINISTRIES 12716 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 237 SUP - 620804001 6208-04-001 105,852.33 .00 105,852.33 .00 .00 105,852.33 105,852.33 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 105,852.33 .00 105,852.33 .00 .00 105,852.33 105,852.33 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 5101233 MGR.NO. 058 PAGE 001 CONT 6208 SEC 04 JOB 001 RES ENGR RANFT, GREGORY PROJ SUP - 620804001 HWY IH0010 14838 NW FRWY HOUSTON CNTY WALLER DIST 12 CONTRACT PRICE $ 124,368.52 REPORT DATE 09/12/2014 09.00.57 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2010 TO MAY 31,2011 EST NO 013 & FINAL DAVID & IVORY MINISTRIES 12716 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6208-04-001 SUP - 620804001 12 IH0010 WALLER -LIMITS - VARIOUS ROADWAYS IN WALLER COUNTY VARIOUS ROADWAYS IN WALLER COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 105,852.33