1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9101231 MGR.NO. 058 PAGE 001 CONT 6213 SEC 97 JOB 001 RES ENGR RANFT, GREGORY PROJ SUP - 621397001 HWY US0290 14838 NW FRWY HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 329,198.52 REPORT DATE 12/17/2013 16.34.08 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2010 TO SEP 30,2011 EST NO 013 & FINAL RUCON, INC. 10168 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 04, 2010 TIME COMPUTED FROM OCT 01, 2010 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 335 335 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 11 1 1 TOTAL DAYS ALLOWED = 365 2 1 DATE WORK COMPLETED 09/30/11 3 1 DAYS CHARGED TO DATE = 365 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 365 365 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9101231 MGR.NO. 058 PAGE 001 CONT 6213 SEC 97 JOB 001 RES ENGR RANFT, GREGORY PROJ SUP - 621397001 HWY US0290 14838 NW FRWY HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 329,198.52 REPORT DATE 12/17/2013 16.34.08 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2010 TO SEP 30,2011 EST NO 013 & FINAL RUCON, INC. 10168 DIST. 12 COUNTY HARRIS CONTROL 6213-97-001 PROJECT SUP - 621397001 HIGHWAY US0290 0LIMITS- VARIOUS HIGHWAYS IN WEST HARRIS CO. . 0TYPE OF WORK- LITTER REMOVAL 0 0005 PREPARED BY GREGORY A. RANFT, P.E. 0 0055 LITTER REMOVAL NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0734 LITTER REMOVAL(SPOT) AC 150.000 32.000 13.000 416.00 0065 0734 LITTER REMOVAL - TRACT (1) CYC 17.000 17.000 250.040 4,250.68 0070 0734 LITTER REMOVAL - TRACT (2) CYC 17.000 17.000 128.390 2,182.63 0075 0734 LITTER REMOVAL - TRACT (3) CYC 26.000 26.000 351.880 9,148.88 0080 0734 LITTER REMOVAL - TRACT (4) CYC 52.000 51.000 278.980 14,227.98 0085 0734 LITTER REMOVAL - TRACT (5) CYC 52.000 51.000 239.470 12,212.97 0090 0734 LITTER REMOVAL - TRACT (6) CYC 52.000 51.000 156.770 7,995.27 0095 0734 LITTER REMOVAL - TRACT (7) CYC 26.000 26.000 953.110 24,780.86 0100 0734 LITTER REMOVAL - TRACT (8) CYC 26.000 26.000 1,140.340 29,648.84 0105 0734 LITTER REMOVAL - TRACT (9) CYC 26.000 26.000 1,129.290 29,361.54 0110 0734 LITTER REMOVAL - TRACT (10) CYC 2.000 2.000 1,438.420 2,876.84 0115 0734 LITTER REMOVAL - TRACT (11) CYC 26.000 26.000 171.000 4,446.00 0120 0734 LITTER REMOVAL - TRACT (12) CYC 4.000 4.000 1,568.800 6,275.20 0125 0734 LITTER REMOVAL - TRACT (13) CYC 26.000 26.000 133.630 3,474.38 0130 0734 LITTER REMOVAL - TRACT (14) CYC 6.000 6.000 524.650 3,147.90 0135 0734 LITTER REMOVAL - TRACT (15) CYC 4.000 4.000 2,077.260 8,309.04 0140 0734 LITTER REMOVAL - TRACT (16) CYC 26.000 26.000 153.700 3,996.20 0145 0734 LITTER REMOVAL - TRACT (17) CYC 26.000 26.000 173.000 4,498.00 0150 0734 LITTER REMOVAL - TRACT (18) CYC 12.000 12.000 365.130 4,381.56 0155 0734 LITTER REMOVAL - TRACT (19) CYC 26.000 26.000 268.410 6,978.66 0160 0734 LITTER REMOVAL - TRACT (20) CYC 26.000 26.000 312.290 8,119.54 0165 0734 LITTER REMOVAL - TRACT (21) CYC 17.000 17.000 1,666.270 28,326.59 0170 0734 LITTER REMOVAL - TRACT (22) CYC 17.000 17.000 124.320 2,113.44 0175 0734 LITTER REMOVAL - TRACT (23) CYC 12.000 13.000 1,257.320 16,345.16 0180 0734 LITTER REMOVAL - TRACT (24) CYC 26.000 25.000 802.130 20,053.25 0185 0734 LITTER REMOVAL - TRACT (25) CYC 26.000 26.000 715.690 18,607.94 0190 0734 LITTER REMOVAL - TRACT (26) CYC 26.000 26.000 836.240 21,742.24 0195 0734 LITTER REMOVAL - TRACT (27) CYC 26.000 26.000 1,135.650 29,526.90 1 SUBTOTAL BID ITEMS $ 327,444.49 0 TOTAL AMOUNT WORK DONE LITTER REMOVAL $ 327,444.49 0 TOTAL AMOUNT WORK DONE CONTROL 6213-97-001 $ 327,444.49 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9101231 MGR.NO. 058 PAGE 001 CONT 6213 SEC 97 JOB 001 RES ENGR RANFT, GREGORY PROJ SUP - 621397001 HWY US0290 14838 NW FRWY HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 329,198.52 REPORT DATE 12/17/2013 16.34.09 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2010 TO SEP 30,2011 EST NO 013 & FINAL RUCON, INC. 10168 0*********************************************************************************************************************************** -LIMITS - VARIOUS HIGHWAYS IN WEST HARRIS CO. 0 . DATE WORK BEGAN OCT 4 , 2010 WORKING DAYS USED 365 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED SEP 30 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6213-97-001 SUP - 621397001 12 US0290 HARRIS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0734 LITTER REMOVAL(SPOT) AC 150.000 32.000 13.000 416.00 0734 LITTER REMOVAL - TRACT (1) CYC 17.000 17.000 250.040 4,250.68 0734 LITTER REMOVAL - TRACT (2) CYC 17.000 17.000 128.390 2,182.63 0734 LITTER REMOVAL - TRACT (3) CYC 26.000 26.000 351.880 9,148.88 0734 LITTER REMOVAL - TRACT (4) CYC 52.000 51.000 278.980 14,227.98 0734 LITTER REMOVAL - TRACT (5) CYC 52.000 51.000 239.470 12,212.97 0734 LITTER REMOVAL - TRACT (6) CYC 52.000 51.000 156.770 7,995.27 0734 LITTER REMOVAL - TRACT (7) CYC 26.000 26.000 953.110 24,780.86 0734 LITTER REMOVAL - TRACT (8) CYC 26.000 26.000 1,140.340 29,648.84 0734 LITTER REMOVAL - TRACT (9) CYC 26.000 26.000 1,129.290 29,361.54 0734 LITTER REMOVAL - TRACT (10) CYC 2.000 2.000 1,438.420 2,876.84 0734 LITTER REMOVAL - TRACT (11) CYC 26.000 26.000 171.000 4,446.00 0734 LITTER REMOVAL - TRACT (12) CYC 4.000 4.000 1,568.800 6,275.20 0734 LITTER REMOVAL - TRACT (13) CYC 26.000 26.000 133.630 3,474.38 0734 LITTER REMOVAL - TRACT (14) CYC 6.000 6.000 524.650 3,147.90 0734 LITTER REMOVAL - TRACT (15) CYC 4.000 4.000 2,077.260 8,309.04 0734 LITTER REMOVAL - TRACT (16) CYC 26.000 26.000 153.700 3,996.20 0734 LITTER REMOVAL - TRACT (17) CYC 26.000 26.000 173.000 4,498.00 0734 LITTER REMOVAL - TRACT (18) CYC 12.000 12.000 365.130 4,381.56 0734 LITTER REMOVAL - TRACT (19) CYC 26.000 26.000 268.410 6,978.66 0734 LITTER REMOVAL - TRACT (20) CYC 26.000 26.000 312.290 8,119.54 0734 LITTER REMOVAL - TRACT (21) CYC 17.000 17.000 1,666.270 28,326.59 0734 LITTER REMOVAL - TRACT (22) CYC 17.000 17.000 124.320 2,113.44 0734 LITTER REMOVAL - TRACT (23) CYC 12.000 13.000 1,257.320 16,345.16 0734 LITTER REMOVAL - TRACT (24) CYC 26.000 25.000 802.130 20,053.25 10734 LITTER REMOVAL - TRACT (25) CYC 26.000 26.000 715.690 18,607.94 0734 LITTER REMOVAL - TRACT (26) CYC 26.000 26.000 836.240 21,742.24 0734 LITTER REMOVAL - TRACT (27) CYC 26.000 26.000 1,135.650 29,526.90 0 SUBTOTAL BID ITEMS $ 327,444.49 0 CONTRACT TOTAL ALL ITEMS $ 327,444.49 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9101231 MGR.NO. 058 PAGE 001 CONT 6213 SEC 97 JOB 001 RES ENGR RANFT, GREGORY PROJ SUP - 621397001 HWY US0290 14838 NW FRWY HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 329,198.52 REPORT DATE 12/17/2013 16.34.09 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2010 TO SEP 30,2011 EST NO 013 & FINAL RUCON, INC. 10168 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 102 SUP - 621397001 6213-97-001 327,444.49 .00 327,444.49 .00 .00 327,444.49 327,444.49 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 327,444.49 .00 327,444.49 .00 .00 327,444.49 327,444.49 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9101231 MGR.NO. 058 PAGE 001 CONT 6213 SEC 97 JOB 001 RES ENGR RANFT, GREGORY PROJ SUP - 621397001 HWY US0290 14838 NW FRWY HOUSTON CNTY HARRIS DIST 12 CONTRACT PRICE $ 329,198.52 REPORT DATE 12/17/2013 16.34.09 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD OCT 01,2010 TO SEP 30,2011 EST NO 013 & FINAL RUCON, INC. 10168 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6213-97-001 SUP - 621397001 12 US0290 HARRIS -LIMITS - VARIOUS HIGHWAYS IN WEST HARRIS CO. . - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 327,444.49