1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 4114022 MGR.NO. 050 PAGE 001 CONT 6219 SEC 98 JOB 001 RES ENGR PAUL, ELIZA PROJ RMC - 621998001 HWY FM0522 1033 E. ORANGE ST. ANGLET CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 657,488.53 REPORT DATE 10/29/2013 16.34.05 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD JUN 27,2011 TO NOV 07,2011 EST NO 007 & FINAL INC. 00644 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 27, 2011 TIME COMPUTED FROM JUN 27, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 93 127 80 47 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 11 1 1 AWAITING DISTRICT FINAL ACCEPTANCE TOTAL DAYS ALLOWED = 93 2 1 AWAITING DISTRICT FINAL ACCEPTANCE DATE WORK COMPLETED 11/07/11 3 1 AWAITING DISTRICT FINAL ACCEPTANCE DAYS CHARGED TO DATE = 80 4 1 AWAITING DISTRICT FINAL ACCEPTANCE ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 525 6 1 SUNDAY 7 1 WORK COMPLETED AND ACCEPTED LIQUIDATED DAMAGES 0 DAYS AT $ 525 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 134 80 54 1 SATURDAY 1 SUNDAY 0 HOLIDAY 4 AWAITING DISTRICT FINAL ACCEPTANCE 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 4114022 MGR.NO. 050 PAGE 001 CONT 6219 SEC 98 JOB 001 RES ENGR PAUL, ELIZA PROJ RMC - 621998001 HWY FM0522 1033 E. ORANGE ST. ANGLET CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 657,488.53 REPORT DATE 10/29/2013 16.34.05 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD JUN 27,2011 TO NOV 07,2011 EST NO 007 & FINAL INC. 00644 DIST. 12 COUNTY BRAZORIA CONTROL 6219-98-001 PROJECT RMC - 621998001 HIGHWAY FM0522 0LIMITS- FM522(SH36 TO FM1459),FM524(FM521 TO UPRR),FM2852(SH35 TO PARK ENT) 0TYPE OF WORK- SEAL COAT 0 0005 PREPARED BY MICHELLE E. MILLIARD, P.E. 0 0055 SEAL COAT NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0316 AGGR(TY-PB GR-3S SAC-B) CY 1,527.000 1,348.365 90.000 121,352.85 0065 0316 ASPH(AC-15P OR20-5TR OR20XP OR10-2TR) GAL 60,984.000 68,765.000 3.000 206,295.00 0070 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 3,051.000 4,013.570 47.000 188,637.79 0070 0351 ADJ EST QUANTITY TO DATE 4,013.570 0075 0500 MOBILIZATION LS 1.000 1.000 58,000.000 58,000.00 0080 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 5.000 1,000.000 5,000.00 0085 0662 WK ZN PAV MRK NON-REMOV (W) 4" (SLD) LF 107,284.000 107,679.000 .130 13,998.27 0090 0662 WK ZN PAV MRK NON-REMOV (W) 24" (SLD) LF 216.000 0.000 3.600 .00 0095 0662 WK ZN PAV MRK NON-REMOV (W) (RR XING) EA 1.000 0.000 200.000 .00 0100 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (BRK) LF 8,960.000 10,326.000 .160 1,652.16 0105 0662 WK ZN PAV MRK NON-REMOV (Y) 12" (SLD) LF 135.000 0.000 1.300 .00 0110 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (SLD) LF 61,223.000 47,653.000 .130 6,194.89 0115 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 14,996.000 106,584.000 .340 36,238.56 0120 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 216.000 95.000 5.200 494.00 0125 0666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 1.000 1.000 300.000 300.00 0130 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 8,960.000 9,260.000 .380 3,518.80 1 0135 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 61,223.000 46,991.000 .340 15,976.94 0140 0666 REFL PAV MRK TY I (Y) 12"(SLD)(100MIL) LF 135.000 0.000 2.100 .00 0145 0672 REFL PAV MRKR TY II-A-A EA 1,332.000 1,055.000 3.100 3,270.50 0150 8020 REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) LF 92,288.000 0.000 .770 .00 0 SUBTOTAL BID ITEMS $ 660,929.76 0 TOTAL AMOUNT WORK DONE SEAL COAT $ 660,929.76 0 TOTAL AMOUNT WORK DONE CONTROL 6219-98-001 $ 660,929.76 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 4114022 MGR.NO. 050 PAGE 001 CONT 6219 SEC 98 JOB 001 RES ENGR PAUL, ELIZA PROJ RMC - 621998001 HWY FM0522 1033 E. ORANGE ST. ANGLET CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 657,488.53 REPORT DATE 10/29/2013 16.34.05 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD JUN 27,2011 TO NOV 07,2011 EST NO 007 & FINAL INC. 00644 0*********************************************************************************************************************************** -LIMITS - FM522(SH36 TO FM1459),FM524(FM521 TO 0 UPRR),FM2852(SH35 TO PARK ENT) DATE WORK BEGAN JUN 27, 2011 WORKING DAYS USED 80 PERCENT COMPLETE 100.00 PERCENT TIME USED 86.00 DATE COMPLETED NOV 7 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6219-98-001 RMC - 621998001 12 FM0522 BRAZORIA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0316 AGGR(TY-PB GR-3S SAC-B) CY 1,527.000 1,348.365 90.000 121,352.85 0316 ASPH(AC-15P OR20-5TR OR20XP OR10-2TR) GAL 60,984.000 68,765.000 3.000 206,295.00 0351 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") SY 3,051.000 4,013.570 47.000 188,637.79 0351 ADJ EST QUANTITY TO DATE 4,013.570 0500 MOBILIZATION LS 1.000 1.000 58,000.000 58,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 5.000 5.000 1,000.000 5,000.00 0662 WK ZN PAV MRK NON-REMOV (W) 4" (SLD) LF 107,284.000 107,679.000 .130 13,998.27 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (BRK) LF 8,960.000 10,326.000 .160 1,652.16 0662 WK ZN PAV MRK NON-REMOV (Y) 4" (SLD) LF 61,223.000 47,653.000 .130 6,194.89 0666 REFL PAV MRK TY I (W) 4" (SLD)(100MIL) LF 14,996.000 106,584.000 .340 36,238.56 0666 REFL PAV MRK TY I (W) 24"(SLD)(100MIL) LF 216.000 95.000 5.200 494.00 0666 REFL PAV MRK TY I(W)(RR XING) (100MIL) EA 1.000 1.000 300.000 300.00 0666 REFL PAV MRK TY I (Y) 4" (BRK)(100MIL) LF 8,960.000 9,260.000 .380 3,518.80 0666 REFL PAV MRK TY I (Y) 4" (SLD)(100MIL) LF 61,223.000 46,991.000 .340 15,976.94 10672 REFL PAV MRKR TY II-A-A EA 1,332.000 1,055.000 3.100 3,270.50 0 SUBTOTAL BID ITEMS $ 660,929.76 0 CONTRACT TOTAL ALL ITEMS $ 660,929.76 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 4114022 MGR.NO. 050 PAGE 001 CONT 6219 SEC 98 JOB 001 RES ENGR PAUL, ELIZA PROJ RMC - 621998001 HWY FM0522 1033 E. ORANGE ST. ANGLET CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 657,488.53 REPORT DATE 10/29/2013 16.34.05 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD JUN 27,2011 TO NOV 07,2011 EST NO 007 & FINAL INC. 00644 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 20 RMC - 621998001 6219-98-001 660,929.76 .00 660,929.76 .00 .00 660,929.76 660,929.76 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 660,929.76 .00 660,929.76 .00 .00 660,929.76 660,929.76 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 4114022 MGR.NO. 050 PAGE 001 CONT 6219 SEC 98 JOB 001 RES ENGR PAUL, ELIZA PROJ RMC - 621998001 HWY FM0522 1033 E. ORANGE ST. ANGLET CNTY BRAZORIA DIST 12 CONTRACT PRICE $ 657,488.53 REPORT DATE 10/29/2013 16.34.06 CONTRACTOR FORDE CONSTRUCTION COMPANY, EST PERIOD JUN 27,2011 TO NOV 07,2011 EST NO 007 & FINAL INC. 00644 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6219-98-001 RMC - 621998001 12 FM0522 BRAZORIA -LIMITS - FM522(SH36 TO FM1459),FM524(FM521 TO UPRR),FM2852(SH35 TO PARK ENT) - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 660,929.76