1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8104004 MGR.NO. 052 PAGE 001 CONT 6210 SEC 76 JOB 001 RES ENGR MOORE,TED PROJ RMC - 621076001 HWY SH0214 135 SLATON ROAD LUBBOCK,T CNTY BAILEY DIST 05 CONTRACT PRICE $ 283,389.60 REPORT DATE 09/24/2013 07.23.11 CONTRACTOR BILLY BENSON 8947 EST PERIOD SEP 26,2011 TO SEP 01,2013 EST NO 025 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 26, 2011 TIME COMPUTED FROM OCT 03, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 108 706 35 671 BROUGHT FORWARD ADDL DAYS GRANTED = 0 SEP 13 1 1 WORK COMPLETED AND ACCEPTED TOTAL DAYS ALLOWED = 108 DATE WORK COMPLETED 09/01/13 DAYS CHARGED TO DATE = 35 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 707 35 672 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8104004 MGR.NO. 052 PAGE 001 CONT 6210 SEC 76 JOB 001 RES ENGR MOORE,TED PROJ RMC - 621076001 HWY SH0214 135 SLATON ROAD LUBBOCK,T CNTY BAILEY DIST 05 CONTRACT PRICE $ 283,389.60 REPORT DATE 09/24/2013 07.23.12 CONTRACTOR BILLY BENSON 8947 EST PERIOD SEP 26,2011 TO SEP 01,2013 EST NO 025 & FINAL DIST. 05 COUNTY BAILEY CONTROL 6210-76-001 PROJECT RMC - 621076001 HIGHWAY SH0214 0LIMITS- BAILEY COUNTY COCHRAN COUNTY 0TYPE OF WORK- PLANS ARE REQUIRED FOR THIS PROJECT 0 0005 ROADSIDE ESTIMATED BY JESSICA TIJERINA 0 0055 ROADSIDE MOWING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 16,120.000 16,452.000 17.580 289,226.16 0 SUBTOTAL BID ITEMS $ 289,226.16 0 TOTAL AMOUNT WORK DONE ROADSIDE MOWING $ 289,226.16 0 TOTAL AMOUNT WORK DONE CONTROL 6210-76-001 $ 289,226.16 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8104004 MGR.NO. 052 PAGE 001 CONT 6210 SEC 76 JOB 001 RES ENGR MOORE,TED PROJ RMC - 621076001 HWY SH0214 135 SLATON ROAD LUBBOCK,T CNTY BAILEY DIST 05 CONTRACT PRICE $ 283,389.60 REPORT DATE 09/24/2013 07.23.12 CONTRACTOR BILLY BENSON 8947 EST PERIOD SEP 26,2011 TO SEP 01,2013 EST NO 025 & FINAL 0*********************************************************************************************************************************** -LIMITS - BAILEY COUNTY 0 COCHRAN COUNTY DATE WORK BEGAN SEP 26, 2011 WORKING DAYS USED 35 PERCENT COMPLETE 100.00 PERCENT TIME USED 32.40 DATE COMPLETED SEP 1 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6210-76-001 RMC - 621076001 05 SH0214 BAILEY - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 16,120.000 16,452.000 17.580 289,226.16 0 SUBTOTAL BID ITEMS $ 289,226.16 0 CONTRACT TOTAL ALL ITEMS $ 289,226.16 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8104004 MGR.NO. 052 PAGE 001 CONT 6210 SEC 76 JOB 001 RES ENGR MOORE,TED PROJ RMC - 621076001 HWY SH0214 135 SLATON ROAD LUBBOCK,T CNTY BAILEY DIST 05 CONTRACT PRICE $ 283,389.60 REPORT DATE 09/24/2013 07.23.12 CONTRACTOR BILLY BENSON 8947 EST PERIOD SEP 26,2011 TO SEP 01,2013 EST NO 025 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 9 RMC - 621076001 6210-76-001 289,226.16 .00 289,226.16 .00 .00 289,226.16 289,226.16 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 289,226.16 .00 289,226.16 .00 .00 289,226.16 289,226.16 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8104004 MGR.NO. 052 PAGE 001 CONT 6210 SEC 76 JOB 001 RES ENGR MOORE,TED PROJ RMC - 621076001 HWY SH0214 135 SLATON ROAD LUBBOCK,T CNTY BAILEY DIST 05 CONTRACT PRICE $ 283,389.60 REPORT DATE 09/24/2013 07.23.12 CONTRACTOR BILLY BENSON 8947 EST PERIOD SEP 26,2011 TO SEP 01,2013 EST NO 025 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6210-76-001 RMC - 621076001 05 SH0214 BAILEY -LIMITS - BAILEY COUNTY COCHRAN COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 289,226.16