1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 3130503 MGR.NO. 052 PAGE 001 CONT 6257 SEC 21 JOB 001 RES ENGR PROJ SUP - 625721001 HWY US0084 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 9,456.48 REPORT DATE 11/04/2013 14.10.46 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO AUG 31,2013 EST NO 006 & FINAL ENTERPRISE PROFESSIONAL SERVICES, INC. 15666 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN APR 01, 2013 TIME COMPUTED FROM APR 01, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 155 122 122 0 BROUGHT FORWARD ADDL DAYS GRANTED = 0 AUG 13 1 1 TOTAL DAYS ALLOWED = 155 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 153 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 31 1 ----- ----- ----- 153 153 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 3130503 MGR.NO. 052 PAGE 001 CONT 6257 SEC 21 JOB 001 RES ENGR PROJ SUP - 625721001 HWY US0084 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 9,456.48 REPORT DATE 11/04/2013 14.10.46 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO AUG 31,2013 EST NO 006 & FINAL ENTERPRISE PROFESSIONAL SERVICES, INC. 15666 DIST. 05 COUNTY LUBBOCK CONTROL 6257-21-001 PROJECT SUP - 625721001 HIGHWAY US0084 0LIMITS- DISTRICT HQ DISTRICT HQ 0TYPE OF WORK- DAY LABORER 0 0005 DISTRICT HQ 0 0055 DISTRICT HQ NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7205 ADDITIONAL LABOR HR 528.000 519.000 17.910 9,295.29 0 SUBTOTAL BID ITEMS $ 9,295.29 0 TOTAL AMOUNT WORK DONE DISTRICT HQ $ 9,295.29 0 TOTAL AMOUNT WORK DONE CONTROL 6257-21-001 $ 9,295.29 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 3130503 MGR.NO. 052 PAGE 001 CONT 6257 SEC 21 JOB 001 RES ENGR PROJ SUP - 625721001 HWY US0084 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 9,456.48 REPORT DATE 11/04/2013 14.10.46 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO AUG 31,2013 EST NO 006 & FINAL ENTERPRISE PROFESSIONAL SERVICES, INC. 15666 0*********************************************************************************************************************************** -LIMITS - DISTRICT HQ 0 DISTRICT HQ DATE WORK BEGAN APR 1 , 2013 WORKING DAYS USED 153 PERCENT COMPLETE 98.29 PERCENT TIME USED 98.70 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6257-21-001 SUP - 625721001 05 US0084 LUBBOCK - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7205 ADDITIONAL LABOR HR 528.000 519.000 17.910 9,295.29 0 SUBTOTAL BID ITEMS $ 9,295.29 0 CONTRACT TOTAL ALL ITEMS $ 9,295.29 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 3130503 MGR.NO. 052 PAGE 001 CONT 6257 SEC 21 JOB 001 RES ENGR PROJ SUP - 625721001 HWY US0084 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 9,456.48 REPORT DATE 11/04/2013 14.10.46 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO AUG 31,2013 EST NO 006 & FINAL ENTERPRISE PROFESSIONAL SERVICES, INC. 15666 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 152 SUP - 625721001 6257-21-001 9,295.29 .00 9,295.29 .00 .00 9,295.29 9,295.29 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 9,295.29 .00 9,295.29 .00 .00 9,295.29 9,295.29 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 3130503 MGR.NO. 052 PAGE 001 CONT 6257 SEC 21 JOB 001 RES ENGR PROJ SUP - 625721001 HWY US0084 135 SLATON ROAD LUBBOCK CNTY LUBBOCK DIST 05 CONTRACT PRICE $ 9,456.48 REPORT DATE 11/04/2013 14.10.46 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD APR 01,2013 TO AUG 31,2013 EST NO 006 & FINAL ENTERPRISE PROFESSIONAL SERVICES, INC. 15666 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6257-21-001 SUP - 625721001 05 US0084 LUBBOCK -LIMITS - DISTRICT HQ DISTRICT HQ - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 9,295.29