1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10124015 MGR.NO. 030 PAGE 001 CONT 6249 SEC 12 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624912001 HWY US0059 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 185,500.00 REPORT DATE 06/05/2014 16.34.26 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD MAY 01,2014 TO MAY 31,2014 EST NO 018 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN DEC 17, 2012 TIME COMPUTED FROM DEC 06, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 511 428 83 BROUGHT FORWARD ADDL DAYS GRANTED = 180 MAY 14 1 1 TOTAL DAYS ALLOWED = 545 2 1 DATE WORK COMPLETED 05/30/14 3 1 DAYS CHARGED TO DATE = 458 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 590 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 ACCEPTED FINAL AND COMPLETE 0 ----- ----- ----- 541 458 83 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10124015 MGR.NO. 030 PAGE 001 CONT 6249 SEC 12 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624912001 HWY US0059 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 185,500.00 REPORT DATE 06/05/2014 16.34.27 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD MAY 01,2014 TO MAY 31,2014 EST NO 018 DIST. 11 COUNTY SHELBY CONTROL 6249-12-001 PROJECT RMC - 624912001 HIGHWAY US0059 0LIMITS- US 59 & VARIOUS LOCATIONS WITHIN SHELBY,SAN AUG, AND SABINE COUNTIES 0TYPE OF WORK- INSTALL RAISED PAVEMENT MARKINGS 0 0005 PREPARED BY HERBERT E. BICKLEY, P.E., 08/22/12 0 0055 ROADWAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0672 REFL PAV MRKR TY I-C EA 4,500.000 5,577.000 2.200 12,269.40 0060 0672 ADJ EST QUANTITY TO DATE 5,577.000 0065 0672 REFL PAV MRKR TY II-A-A EA 80,000.000 73,686.000 2.140 157,688.04 0070 0672 REFL PAV MRKR TY II-C-R EA 2,000.000 412.000 2.200 906.40 0 SUBTOTAL BID ITEMS $ 170,863.84 0 TOTAL AMOUNT WORK DONE ROADWAY $ 170,863.84 0 TOTAL AMOUNT WORK DONE CONTROL 6249-12-001 $ 170,863.84 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10124015 MGR.NO. 030 PAGE 001 CONT 6249 SEC 12 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624912001 HWY US0059 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 185,500.00 REPORT DATE 06/05/2014 16.34.27 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD MAY 01,2014 TO MAY 31,2014 EST NO 018 0*********************************************************************************************************************************** -LIMITS - US 59 & VARIOUS LOCATIONS WITHIN 0 SHELBY,SAN AUG, AND SABINE COUNTIES DATE WORK BEGAN DEC 17, 2012 WORKING DAYS USED 458 PERCENT COMPLETE 100.00 PERCENT TIME USED 84.00 DATE COMPLETED MAY 30 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6249-12-001 RMC - 624912001 11 US0059 SHELBY - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0672 REFL PAV MRKR TY I-C EA 4,500.000 5,577.000 2.200 12,269.40 0672 ADJ EST QUANTITY TO DATE 5,577.000 0672 REFL PAV MRKR TY II-A-A EA 80,000.000 73,686.000 2.140 157,688.04 0672 REFL PAV MRKR TY II-C-R EA 2,000.000 412.000 2.200 906.40 0 SUBTOTAL BID ITEMS $ 170,863.84 0 CONTRACT TOTAL ALL ITEMS $ 170,863.84 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10124015 MGR.NO. 030 PAGE 001 CONT 6249 SEC 12 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624912001 HWY US0059 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 185,500.00 REPORT DATE 06/05/2014 16.34.27 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD MAY 01,2014 TO MAY 31,2014 EST NO 018 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 210 RMC - 624912001 6249-12-001 170,863.84 .00 170,863.84 .00 .00 170,863.84 170,863.84 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 170,863.84 .00 170,863.84 .00 .00 170,863.84 170,863.84 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10124015 MGR.NO. 030 PAGE 001 CONT 6249 SEC 12 JOB 001 RES ENGR CARRELL, JUDY PROJ RMC - 624912001 HWY US0059 1805 N TIMBERLAND DR LUFK CNTY SHELBY DIST 11 CONTRACT PRICE $ 185,500.00 REPORT DATE 06/05/2014 16.34.27 CONTRACTOR BRYDL CONTRACTING, INC. 12502 EST PERIOD MAY 01,2014 TO MAY 31,2014 EST NO 018 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6249-12-001 RMC - 624912001 11 US0059 SHELBY -LIMITS - US 59 & VARIOUS LOCATIONS WITHIN SHELBY,SAN AUG, AND SABINE COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 170,863.84