1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 6120101 MGR.NO. 002 PAGE 001 CONT 6242 SEC 85 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624285001 HWY US0082 3600 SW LOOP 286 PARIS CNTY RED RIVER DIST 01 CONTRACT PRICE $ 59,520.00 REPORT DATE 06/19/2014 15.14.40 CONTRACTOR RICKEY BAIRD 6764 EST PERIOD JUL 23,2012 TO APR 28,2014 EST NO 023 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 23, 2012 TIME COMPUTED FROM JUL 30, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 365 617 425 192 BROUGHT FORWARD ADDL DAYS GRANTED = 365 APR 14 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 04/28/14 3 1 DAYS CHARGED TO DATE = 444 4 1 ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 570 6 1 SUNDAY 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 570 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 SATURDAY ONE COPY HAS BEEN GIVEN 13 1 SUNDAY TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 SATURDAY 20 1 SUNDAY 21 1 22 1 23 1 24 1 25 1 26 1 SATURDAY 27 1 SUNDAY 28 1 WORK COMPLETED AND ACCEPTED - ----- ----- ----- 645 444 201 4 SATURDAY 4 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 6120101 MGR.NO. 002 PAGE 001 CONT 6242 SEC 85 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624285001 HWY US0082 3600 SW LOOP 286 PARIS CNTY RED RIVER DIST 01 CONTRACT PRICE $ 59,520.00 REPORT DATE 06/19/2014 15.14.40 CONTRACTOR RICKEY BAIRD 6764 EST PERIOD JUL 23,2012 TO APR 28,2014 EST NO 023 & FINAL DIST. 01 COUNTY RED RIVER CONTROL 6242-85-001 PROJECT RMC - 624285001 HIGHWAY US0082 0LIMITS- VARIOUS ROADWAYS IN RED RIVER COUNTY 0TYPE OF WORK- POTHOLE REPAIR 0 0050 ON CALL POTHOLE REPAIR NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0070 PREPARED BY MLS (4-16-12) 8.3.A.6 OTHER 0 0075 0700 POTHOLE REPAIR (STANDARD) TON 480.000 957.690 124.000 118,753.56 0075 0700 ADJ EST QUANTITY TO DATE 960.000 0 SUBTOTAL BID ITEMS $ 118,753.56 0 TOTAL AMOUNT WORK DONE ON CALL POTHOLE REPAIR $ 118,753.56 0 TOTAL AMOUNT WORK DONE CONTROL 6242-85-001 $ 118,753.56 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 6120101 MGR.NO. 002 PAGE 001 CONT 6242 SEC 85 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624285001 HWY US0082 3600 SW LOOP 286 PARIS CNTY RED RIVER DIST 01 CONTRACT PRICE $ 59,520.00 REPORT DATE 06/19/2014 15.14.40 CONTRACTOR RICKEY BAIRD 6764 EST PERIOD JUL 23,2012 TO APR 28,2014 EST NO 023 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN 0 RED RIVER COUNTY DATE WORK BEGAN JUL 23, 2012 WORKING DAYS USED 444 PERCENT COMPLETE 100.00 PERCENT TIME USED 60.80 DATE COMPLETED APR 28 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6242-85-001 RMC - 624285001 01 US0082 RED RIVER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0700 POTHOLE REPAIR (STANDARD) TON 480.000 957.690 124.000 118,753.56 0700 ADJ EST QUANTITY TO DATE 960.000 0 SUBTOTAL BID ITEMS $ 118,753.56 0 CONTRACT TOTAL ALL ITEMS $ 118,753.56 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 6120101 MGR.NO. 002 PAGE 001 CONT 6242 SEC 85 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624285001 HWY US0082 3600 SW LOOP 286 PARIS CNTY RED RIVER DIST 01 CONTRACT PRICE $ 59,520.00 REPORT DATE 06/19/2014 15.14.40 CONTRACTOR RICKEY BAIRD 6764 EST PERIOD JUL 23,2012 TO APR 28,2014 EST NO 023 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 194 RMC - 624285001 6242-85-001 118,753.56 .00 118,753.56 .00 .00 118,753.56 118,753.56 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 118,753.56 .00 118,753.56 .00 .00 118,753.56 118,753.56 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 6120101 MGR.NO. 002 PAGE 001 CONT 6242 SEC 85 JOB 001 RES ENGR HARPER, RICHARD PROJ RMC - 624285001 HWY US0082 3600 SW LOOP 286 PARIS CNTY RED RIVER DIST 01 CONTRACT PRICE $ 59,520.00 REPORT DATE 06/19/2014 15.14.40 CONTRACTOR RICKEY BAIRD 6764 EST PERIOD JUL 23,2012 TO APR 28,2014 EST NO 023 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6242-85-001 RMC - 624285001 01 US0082 RED RIVER -LIMITS - VARIOUS ROADWAYS IN RED RIVER COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 118,753.56