1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7130103 MGR.NO. 009 PAGE 001 CONT 6256 SEC 22 JOB 001 RES ENGR SIMS, TAMMY PROJ RMC - 625622001 HWY IH0030 3001 IH 30 EAST GREENVILL CNTY HOPKINS DIST 01 CONTRACT PRICE $ 216,065.00 REPORT DATE 05/09/2014 10.17.36 CONTRACTOR DRS CONSTRUCTION, INC. 6677 EST PERIOD OCT 02,2013 TO FEB 20,2014 EST NO 007 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 02, 2013 TIME COMPUTED FROM OCT 09, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 50 122 33 89 BROUGHT FORWARD ADDL DAYS GRANTED = 0 FEB 14 1 1 WAITING ON FINAL DOCUMENTATION TOTAL DAYS ALLOWED = 50 2 1 WAITING ON FINAL DOCUMENTATION DATE WORK COMPLETED 02/20/14 3 1 WAITING ON FINAL DOCUMENTATION DAYS CHARGED TO DATE = 33 4 1 WAITING ON FINAL DOCUMENTATION ASSESSED LIQ DAMAGES = 0 5 1 WAITING ON FINAL DOCUMENTATION LIQ DAMAGE RATE $ 590 6 1 WAITING ON FINAL DOCUMENTATION 7 1 WAITING ON FINAL DOCUMENTATION LIQUIDATED DAMAGES 8 1 WAITING ON FINAL DOCUMENTATION 0 DAYS AT $ 590 PER DAY 9 1 WAITING ON FINAL DOCUMENTATION TOTAL = $ .00 10 1 WAITING ON FINAL DOCUMENTATION 11 1 WAITING ON FINAL DOCUMENTATION CERTIFIED AS CORRECT AND 12 1 WAITING ON FINAL DOCUMENTATION ONE COPY HAS BEEN GIVEN 13 1 WAITING ON FINAL DOCUMENTATION TO THE CONTRACTOR 14 1 WAITING ON FINAL DOCUMENTATION 15 1 WAITING ON FINAL DOCUMENTATION 16 1 WAITING ON FINAL DOCUMENTATION ---------------------------- 17 1 WAITING ON FINAL DOCUMENTATION AREA/PROJECT ENGINEER 18 1 WAITING ON FINAL DOCUMENTATION 19 1 WAITING ON FINAL DOCUMENTATION 20 1 WORK COMPLETED AND ACCEPTED - - - - ----- ----- ----- 142 33 109 0 SATURDAY 0 SUNDAY 0 HOLIDAY 19 WAITING ON FINAL DOCUMENTATION 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7130103 MGR.NO. 009 PAGE 001 CONT 6256 SEC 22 JOB 001 RES ENGR SIMS, TAMMY PROJ RMC - 625622001 HWY IH0030 3001 IH 30 EAST GREENVILL CNTY HOPKINS DIST 01 CONTRACT PRICE $ 216,065.00 REPORT DATE 05/09/2014 10.17.36 CONTRACTOR DRS CONSTRUCTION, INC. 6677 EST PERIOD OCT 02,2013 TO FEB 20,2014 EST NO 007 & FINAL DIST. 01 COUNTY HOPKINS CONTROL 6256-22-001 PROJECT RMC - 625622001 HIGHWAY IH0030 0LIMITS- ROCKWALL/HUNT COUNTY LINE ALONG IH30 THROUGH HOPKINS AND FRANKLIN COUNTIES 0TYPE OF WORK- INSTALL/REPLACE DELINEATORS 0 0005 ENTERED BY RENEE COSTON 0 0055 REMOVE/INSTALL DELINEATORS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0500 MOBILIZATION LS 1.000 1.000 14,000.000 14,000.00 0065 0658 INSTL DEL ASSM (D-SW)SZ 1(FLX)GF2 EA 1,000.000 1,737.000 30.000 52,110.00 0065 0658 ADJ EST QUANTITY TO DATE 1,737.000 0070 0658 INSTL DEL ASSM (D-SW)SZ (TYC)CTB EA 500.000 552.000 10.000 5,520.00 0070 0658 ADJ EST QUANTITY TO DATE 552.000 0075 0658 INSTL DEL ASSM (D-SY)SZ (TYC)CTB EA 3,800.000 3,834.000 10.000 38,340.00 0075 0658 ADJ EST QUANTITY TO DATE 3,834.000 0080 0658 INSTL DEL ASSM (D-SY)SZ (TYC)CTB(BI) EA 275.000 273.000 10.000 2,730.00 0080 0658 ADJ EST QUANTITY TO DATE 273.000 0085 0658 INSTL DEL ASSM (D-DW)SZ 1(FLX)GND EA 847.000 668.000 35.000 23,380.00 0085 0658 ADJ EST QUANTITY TO DATE 668.000 0090 0658 INSTL DEL ASSM (D-DY)SZ 1(FLX)GND EA 726.000 0.000 30.000 .00 0090 0658 ADJ EST QUANTITY TO DATE 0.000 0095 0658 INSTL OM ASSM (OM-2Z)(FLX)GND EA 1,800.000 1,380.000 30.000 41,400.00 0095 0658 ADJ EST QUANTITY TO DATE 1,380.000 0100 0658 REMOVE DELIN & OBJECT MARKERS ASSMS EA 2,000.000 1,819.000 5.000 9,095.00 0100 0658 ADJ EST QUANTITY TO DATE 1,819.000 0105 0658 INSTL DEL ASSM (D-SW)SZ 1(FLX)GND EA 363.000 753.000 30.000 22,590.00 0105 0658 ADJ EST QUANTITY TO DATE 753.000 1 SUBTOTAL BID ITEMS $ 209,165.00 0 TOTAL AMOUNT WORK DONE REMOVE/INSTALL DELINEATORS $ 209,165.00 0 TOTAL AMOUNT WORK DONE CONTROL 6256-22-001 $ 209,165.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7130103 MGR.NO. 009 PAGE 001 CONT 6256 SEC 22 JOB 001 RES ENGR SIMS, TAMMY PROJ RMC - 625622001 HWY IH0030 3001 IH 30 EAST GREENVILL CNTY HOPKINS DIST 01 CONTRACT PRICE $ 216,065.00 REPORT DATE 05/09/2014 10.17.37 CONTRACTOR DRS CONSTRUCTION, INC. 6677 EST PERIOD OCT 02,2013 TO FEB 20,2014 EST NO 007 & FINAL 0*********************************************************************************************************************************** -LIMITS - ROCKWALL/HUNT COUNTY LINE ALONG IH30 0 THROUGH HOPKINS AND FRANKLIN COUNTIES DATE WORK BEGAN OCT 2 , 2013 WORKING DAYS USED 33 PERCENT COMPLETE 100.00 PERCENT TIME USED 66.00 DATE COMPLETED FEB 20 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6256-22-001 RMC - 625622001 01 IH0030 HOPKINS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 14,000.000 14,000.00 0658 INSTL DEL ASSM (D-SW)SZ 1(FLX)GF2 EA 1,000.000 1,737.000 30.000 52,110.00 0658 ADJ EST QUANTITY TO DATE 1,737.000 0658 INSTL DEL ASSM (D-SW)SZ (TYC)CTB EA 500.000 552.000 10.000 5,520.00 0658 ADJ EST QUANTITY TO DATE 552.000 0658 INSTL DEL ASSM (D-SY)SZ (TYC)CTB EA 3,800.000 3,834.000 10.000 38,340.00 0658 ADJ EST QUANTITY TO DATE 3,834.000 0658 INSTL DEL ASSM (D-SY)SZ (TYC)CTB(BI) EA 275.000 273.000 10.000 2,730.00 0658 ADJ EST QUANTITY TO DATE 273.000 0658 INSTL DEL ASSM (D-DW)SZ 1(FLX)GND EA 847.000 668.000 35.000 23,380.00 0658 ADJ EST QUANTITY TO DATE 668.000 0658 INSTL OM ASSM (OM-2Z)(FLX)GND EA 1,800.000 1,380.000 30.000 41,400.00 0658 ADJ EST QUANTITY TO DATE 1,380.000 0658 REMOVE DELIN & OBJECT MARKERS ASSMS EA 2,000.000 1,819.000 5.000 9,095.00 0658 ADJ EST QUANTITY TO DATE 1,819.000 0658 INSTL DEL ASSM (D-SW)SZ 1(FLX)GND EA 363.000 753.000 30.000 22,590.00 0658 ADJ EST QUANTITY TO DATE 753.000 1 SUBTOTAL BID ITEMS $ 209,165.00 0 CONTRACT TOTAL ALL ITEMS $ 209,165.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7130103 MGR.NO. 009 PAGE 001 CONT 6256 SEC 22 JOB 001 RES ENGR SIMS, TAMMY PROJ RMC - 625622001 HWY IH0030 3001 IH 30 EAST GREENVILL CNTY HOPKINS DIST 01 CONTRACT PRICE $ 216,065.00 REPORT DATE 05/09/2014 10.17.37 CONTRACTOR DRS CONSTRUCTION, INC. 6677 EST PERIOD OCT 02,2013 TO FEB 20,2014 EST NO 007 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 113 RMC - 625622001 6256-22-001 209,165.00 .00 209,165.00 .00 .00 209,165.00 209,165.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 209,165.00 .00 209,165.00 .00 .00 209,165.00 209,165.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7130103 MGR.NO. 009 PAGE 001 CONT 6256 SEC 22 JOB 001 RES ENGR SIMS, TAMMY PROJ RMC - 625622001 HWY IH0030 3001 IH 30 EAST GREENVILL CNTY HOPKINS DIST 01 CONTRACT PRICE $ 216,065.00 REPORT DATE 05/09/2014 10.17.37 CONTRACTOR DRS CONSTRUCTION, INC. 6677 EST PERIOD OCT 02,2013 TO FEB 20,2014 EST NO 007 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6256-22-001 RMC - 625622001 01 IH0030 HOPKINS -LIMITS - ROCKWALL/HUNT COUNTY LINE ALONG IH30 THROUGH HOPKINS AND FRANKLIN COUNTIES - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 209,165.00