1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10101541 MGR.NO. 010 PAGE 001 CONT 6219 SEC 22 JOB 001 RES ENGR ACOSTA, MICHAEL PROJ EMC - 621922001 HWY IH0010 9320 SE LOOP 410 SAN ANTO CNTY BEXAR DIST 15 CONTRACT PRICE $ 394,305.00 REPORT DATE 01/20/2011 16.18.36 CONTRACTOR AUSTIN BRIDGE & ROAD, LP 10552 EST PERIOD OCT 21,2010 TO NOV 23,2010 EST NO 003 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 21, 2010 TIME COMPUTED FROM OCT 21, 2010 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 30 11 11 0 BROUGHT FORWARD ADDL DAYS GRANTED = 4 NOV 10 1 1 TOTAL DAYS ALLOWED = 34 2 1 DATE WORK COMPLETED 11/23/10 3 1 DAYS CHARGED TO DATE = 34 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 500 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 WORK COMPLETED AND ACCEPTED - - - ----- ----- ----- 34 34 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10101541 MGR.NO. 010 PAGE 001 CONT 6219 SEC 22 JOB 001 RES ENGR ACOSTA, MICHAEL PROJ EMC - 621922001 HWY IH0010 9320 SE LOOP 410 SAN ANTO CNTY BEXAR DIST 15 CONTRACT PRICE $ 394,305.00 REPORT DATE 01/20/2011 16.18.37 CONTRACTOR AUSTIN BRIDGE & ROAD, LP 10552 EST PERIOD OCT 21,2010 TO NOV 23,2010 EST NO 003 & FINAL DIST. 15 COUNTY BEXAR CONTROL 6219-22-001 PROJECT EMC - 621922001 HIGHWAY IH0010 0LIMITS- IH EB AT FOSTER ROAD 0TYPE OF WORK- SLOPE FAILURE REPAIR 0 0005 PREPARED BY MICHELLE BARTON 0 0055 SLOPE FAILURE REPAIR NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0161 COMPOST MANUF TOPSOIL (BIP) (4") SY 620.000 0.000 7.000 .00 0065 0164 BROADCAST SEED (TEMP) (COOL) SY 620.000 0.000 3.000 .00 0070 0164 BROADCAST SEED (PERM) (URBAN) (CLAY) SY 620.000 0.000 3.000 .00 0075 0169 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 620.000 555.000 3.000 1,665.00 0080 0400 STRUCT EXCAV CY 4,135.000 4,135.000 31.000 128,185.00 0085 0401 FLOWABLE BACKFILL CY 4.000 1.000 200.000 200.00 0090 0403 TEMPORARY SPL SHORING (SOIL NAIL) SF 3,758.000 4,348.000 50.000 217,400.00 0095 0432 RIPRAP (CONC)(5 IN) CY 2.000 1.300 650.000 845.00 0100 0500 MOBILIZATION LS 1.000 1.000 50,000.000 50,000.00 0105 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 5,000.000 10,000.00 0110 0512 PORT CTB (MOVE)(SNGL SLP) (TY 2) LF 210.000 210.000 20.000 4,200.00 0115 0545 CRASH CUSH ATTEN (REMOVE) EA 1.000 1.000 2,000.000 2,000.00 0 SUBTOTAL BID ITEMS $ 414,495.00 0 TOTAL AMOUNT WORK DONE SLOPE FAILURE REPAIR $ 414,495.00 0 TOTAL AMOUNT WORK DONE CONTROL 6219-22-001 $ 414,495.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10101541 MGR.NO. 010 PAGE 001 CONT 6219 SEC 22 JOB 001 RES ENGR ACOSTA, MICHAEL PROJ EMC - 621922001 HWY IH0010 9320 SE LOOP 410 SAN ANTO CNTY BEXAR DIST 15 CONTRACT PRICE $ 394,305.00 REPORT DATE 01/20/2011 16.18.37 CONTRACTOR AUSTIN BRIDGE & ROAD, LP 10552 EST PERIOD OCT 21,2010 TO NOV 23,2010 EST NO 003 & FINAL 0*********************************************************************************************************************************** -LIMITS - IH EB AT 0 FOSTER ROAD DATE WORK BEGAN OCT 21, 2010 WORKING DAYS USED 34 PERCENT COMPLETE 100.00 PERCENT TIME USED 100.00 DATE COMPLETED NOV 23 2010 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6219-22-001 EMC - 621922001 15 IH0010 BEXAR - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0169 SOIL RETENTION BLANKETS (CL 1) (TY A) SY 620.000 555.000 3.000 1,665.00 0400 STRUCT EXCAV CY 4,135.000 4,135.000 31.000 128,185.00 0401 FLOWABLE BACKFILL CY 4.000 1.000 200.000 200.00 0403 TEMPORARY SPL SHORING (SOIL NAIL) SF 3,758.000 4,348.000 50.000 217,400.00 0432 RIPRAP (CONC)(5 IN) CY 2.000 1.300 650.000 845.00 0500 MOBILIZATION LS 1.000 1.000 50,000.000 50,000.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 2.000 5,000.000 10,000.00 0512 PORT CTB (MOVE)(SNGL SLP) (TY 2) LF 210.000 210.000 20.000 4,200.00 0545 CRASH CUSH ATTEN (REMOVE) EA 1.000 1.000 2,000.000 2,000.00 0 SUBTOTAL BID ITEMS $ 414,495.00 0 CONTRACT TOTAL ALL ITEMS $ 414,495.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10101541 MGR.NO. 010 PAGE 001 CONT 6219 SEC 22 JOB 001 RES ENGR ACOSTA, MICHAEL PROJ EMC - 621922001 HWY IH0010 9320 SE LOOP 410 SAN ANTO CNTY BEXAR DIST 15 CONTRACT PRICE $ 394,305.00 REPORT DATE 01/20/2011 16.18.37 CONTRACTOR AUSTIN BRIDGE & ROAD, LP 10552 EST PERIOD OCT 21,2010 TO NOV 23,2010 EST NO 003 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 15 EMC - 621922001 6219-22-001 414,495.00 .00 414,495.00 .00 .00 414,495.00 412,495.00 2,000.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 414,495.00 .00 414,495.00 .00 .00 414,495.00 412,495.00 2,000.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10101541 MGR.NO. 010 PAGE 001 CONT 6219 SEC 22 JOB 001 RES ENGR ACOSTA, MICHAEL PROJ EMC - 621922001 HWY IH0010 9320 SE LOOP 410 SAN ANTO CNTY BEXAR DIST 15 CONTRACT PRICE $ 394,305.00 REPORT DATE 01/20/2011 16.18.38 CONTRACTOR AUSTIN BRIDGE & ROAD, LP 10552 EST PERIOD OCT 21,2010 TO NOV 23,2010 EST NO 003 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6219-22-001 EMC - 621922001 15 IH0010 BEXAR -LIMITS - IH EB AT FOSTER ROAD - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 414,495.00