1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 9100901 MGR.NO. 801 PAGE 001 CONT 6211 SEC 53 JOB 001 RES ENGR BASHI, ALI PROJ RMC - 621153001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 188,930.00 REPORT DATE 05/16/2012 11.29.32 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS, EST PERIOD NOV 08,2010 TO DEC 01,2011 EST NO 015 & FINAL INC. 13721 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 08, 2010 TIME COMPUTED FROM NOV 08, 2010 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 282 388 129 259 BROUGHT FORWARD ADDL DAYS GRANTED = 0 DEC 11 1 1 TOTAL DAYS ALLOWED = 282 DATE WORK COMPLETED 12/01/11 DAYS CHARGED TO DATE = 130 ASSESSED LIQ DAMAGES = 0 LIQ DAMAGE RATE $ 500 0 LIQUIDATED DAMAGES 0 DAYS AT $ 500 PER DAY TOTAL = $ .00 0 CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 389 130 259 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 9100901 MGR.NO. 801 PAGE 001 CONT 6211 SEC 53 JOB 001 RES ENGR BASHI, ALI PROJ RMC - 621153001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 188,930.00 REPORT DATE 05/16/2012 11.29.33 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS, EST PERIOD NOV 08,2010 TO DEC 01,2011 EST NO 015 & FINAL INC. 13721 DIST. 09 COUNTY BELL CONTROL 6211-53-001 PROJECT RMC - 621153001 HIGHWAY US0190 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- SWEEPING HIGHWAYS AND BRIDGES 0 0005 PREPARED JULY 2010 0 0055 ROADWAY NET LENGTH111.000 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0738 CLEANING/SWEEPING (CENTER MEDIAN) MI 850.200 865.400 90.000 77,886.00 0060 0738 ADJ EST QUANTITY TO DATE 885.000 0065 0738 CLEANING/SWEEPING (OUTSIDE MAIN LANE) MI 911.100 980.600 90.000 88,254.00 0065 0738 ADJ EST QUANTITY TO DATE 946.000 0070 0738 CLEANING/SWEEPING (FRONTAGE ROAD) MI 253.200 239.600 90.000 21,564.00 0075 0738 CLEANING/SWEEPING (ENTRANCE/EXIT RAMP) MI 50.000 51.000 90.000 4,590.00 0080 0738 CLEANING/SWEEPING (AGGREGATE REMOVAL) MI 125.000 85.000 1.000 85.00 0085 0738 CLEANING/SWEEPING (SPOT) MI 30.000 20.000 90.000 1,800.00 0090 0738 CLEANING/SWEEPING (HANDWORK) SY 2,000.000 55.000 .150 8.25 0 SUBTOTAL BID ITEMS $ 194,187.25 0 TOTAL AMOUNT WORK DONE ROADWAY $ 194,187.25 0 TOTAL AMOUNT WORK DONE CONTROL 6211-53-001 $ 194,187.25 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 9100901 MGR.NO. 801 PAGE 001 CONT 6211 SEC 53 JOB 001 RES ENGR BASHI, ALI PROJ RMC - 621153001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 188,930.00 REPORT DATE 05/16/2012 11.29.33 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS, EST PERIOD NOV 08,2010 TO DEC 01,2011 EST NO 015 & FINAL INC. 13721 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN NOV 8 , 2010 WORKING DAYS USED 130 PERCENT COMPLETE 100.00 PERCENT TIME USED 46.00 DATE COMPLETED DEC 1 2011 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6211-53-001 RMC - 621153001 09 US0190 BELL - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0738 CLEANING/SWEEPING (CENTER MEDIAN) MI 850.200 865.400 90.000 77,886.00 0738 ADJ EST QUANTITY TO DATE 885.000 0738 CLEANING/SWEEPING (OUTSIDE MAIN LANE) MI 911.100 980.600 90.000 88,254.00 0738 ADJ EST QUANTITY TO DATE 946.000 0738 CLEANING/SWEEPING (FRONTAGE ROAD) MI 253.200 239.600 90.000 21,564.00 0738 CLEANING/SWEEPING (ENTRANCE/EXIT RAMP) MI 50.000 51.000 90.000 4,590.00 0738 CLEANING/SWEEPING (AGGREGATE REMOVAL) MI 125.000 85.000 1.000 85.00 0738 CLEANING/SWEEPING (SPOT) MI 30.000 20.000 90.000 1,800.00 0738 CLEANING/SWEEPING (HANDWORK) SY 2,000.000 55.000 .150 8.25 0 SUBTOTAL BID ITEMS $ 194,187.25 0 CONTRACT TOTAL ALL ITEMS $ 194,187.25 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 9100901 MGR.NO. 801 PAGE 001 CONT 6211 SEC 53 JOB 001 RES ENGR BASHI, ALI PROJ RMC - 621153001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 188,930.00 REPORT DATE 05/16/2012 11.29.33 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS, EST PERIOD NOV 08,2010 TO DEC 01,2011 EST NO 015 & FINAL INC. 13721 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 14 RMC - 621153001 6211-53-001 194,187.25 .00 194,187.25 .00 .00 194,187.25 194,187.25 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 194,187.25 .00 194,187.25 .00 .00 194,187.25 194,187.25 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 9100901 MGR.NO. 801 PAGE 001 CONT 6211 SEC 53 JOB 001 RES ENGR BASHI, ALI PROJ RMC - 621153001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 188,930.00 REPORT DATE 05/16/2012 11.29.33 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS, EST PERIOD NOV 08,2010 TO DEC 01,2011 EST NO 015 & FINAL INC. 13721 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6211-53-001 RMC - 621153001 09 US0190 BELL -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 194,187.25