1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11110902 MGR.NO. 801 PAGE 001 CONT 6234 SEC 45 JOB 001 RES ENGR BASHI, ALI PROJ RMC - 623445001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 200,828.98 REPORT DATE 07/24/2013 16.29.00 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS, EST PERIOD JAN 09,2012 TO MAR 26,2013 EST NO 016 & FINAL INC. 13721 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JAN 12, 2012 TIME COMPUTED FROM JAN 09, 2012 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 290 417 109 308 BROUGHT FORWARD ADDL DAYS GRANTED = 0 MAR 13 1 1 NO WORK SCHEDULED BY TXDOT TOTAL DAYS ALLOWED = 290 2 1 SATURDAY DATE WORK COMPLETED 03/26/13 3 1 SUNDAY DAYS CHARGED TO DATE = 119 4 1 CYCLE TIME NOT STARTED ASSESSED LIQ DAMAGES = 0 5 1 CYCLE TIME NOT STARTED LIQ DAMAGE RATE $ 590 6 1 CYCLE TIME NOT STARTED 7 1 CYCLE TIME NOT STARTED LIQUIDATED DAMAGES 8 1 CYCLE TIME NOT STARTED 0 DAYS AT $ 590 PER DAY 9 1 CYCLE TIME NOT STARTED TOTAL = $ .00 10 1 CYCLE TIME NOT STARTED 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 SATURDAY ---------------------------- 17 1 SUNDAY AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 SATURDAY 24 1 SUNDAY 25 1 CYCLE WORK COMPLETED AND ACCEPTED 26 1 WORK COMPLETED AND ACCEPTED - - ----- ----- ----- 443 119 324 3 SATURDAY 3 SUNDAY 0 HOLIDAY 1 NO WORK SCHEDULED BY TXDOT 7 CYCLE TIME NOT STARTED 1 CYCLE WORK COMPLETED AND ACCEPTED 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11110902 MGR.NO. 801 PAGE 001 CONT 6234 SEC 45 JOB 001 RES ENGR BASHI, ALI PROJ RMC - 623445001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 200,828.98 REPORT DATE 07/24/2013 16.29.01 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS, EST PERIOD JAN 09,2012 TO MAR 26,2013 EST NO 016 & FINAL INC. 13721 DIST. 09 COUNTY BELL CONTROL 6234-45-001 PROJECT RMC - 623445001 HIGHWAY US0190 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- SWEEPING HIGHWAYS AND BRIDGES 0 0005 PREPARED SEPTEMBER 2011 0 0055 ROADWAY NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0738 CLEANING/SWEEPING (CENTER MEDIAN) MI 860.880 873.010 93.000 81,189.93 0065 0738 CLEANING/SWEEPING (OUTSIDE MAIN LANE) MI 963.780 980.910 93.000 91,224.63 0070 0738 CLEANING/SWEEPING (FRONTAGE ROAD) MI 253.200 221.000 93.000 20,553.00 0075 0738 CLEANING/SWEEPING (ENTRANCE/EXIT RAMP) MI 50.000 50.000 93.000 4,650.00 0080 0738 CLEANING/SWEEPING (AGGREGATE REMOVAL) MI 125.000 0.000 1.000 .00 0085 0738 CLEANING/SWEEPING (SPOT) MI 30.000 13.000 93.000 1,209.00 0090 0738 CLEANING/SWEEPING (HANDWORK) SY 100.000 394.300 .230 90.69 0 SUBTOTAL BID ITEMS $ 198,917.25 0 TOTAL AMOUNT WORK DONE ROADWAY $ 198,917.25 0 TOTAL AMOUNT WORK DONE CONTROL 6234-45-001 $ 198,917.25 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11110902 MGR.NO. 801 PAGE 001 CONT 6234 SEC 45 JOB 001 RES ENGR BASHI, ALI PROJ RMC - 623445001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 200,828.98 REPORT DATE 07/24/2013 16.29.01 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS, EST PERIOD JAN 09,2012 TO MAR 26,2013 EST NO 016 & FINAL INC. 13721 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN JAN 12, 2012 WORKING DAYS USED 119 PERCENT COMPLETE 100.00 PERCENT TIME USED 41.00 DATE COMPLETED MAR 26 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6234-45-001 RMC - 623445001 09 US0190 BELL - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0738 CLEANING/SWEEPING (CENTER MEDIAN) MI 860.880 873.010 93.000 81,189.93 0738 CLEANING/SWEEPING (OUTSIDE MAIN LANE) MI 963.780 980.910 93.000 91,224.63 0738 CLEANING/SWEEPING (FRONTAGE ROAD) MI 253.200 221.000 93.000 20,553.00 0738 CLEANING/SWEEPING (ENTRANCE/EXIT RAMP) MI 50.000 50.000 93.000 4,650.00 0738 CLEANING/SWEEPING (SPOT) MI 30.000 13.000 93.000 1,209.00 0738 CLEANING/SWEEPING (HANDWORK) SY 100.000 394.300 .230 90.69 0 SUBTOTAL BID ITEMS $ 198,917.25 0 CONTRACT TOTAL ALL ITEMS $ 198,917.25 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11110902 MGR.NO. 801 PAGE 001 CONT 6234 SEC 45 JOB 001 RES ENGR BASHI, ALI PROJ RMC - 623445001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 200,828.98 REPORT DATE 07/24/2013 16.29.01 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS, EST PERIOD JAN 09,2012 TO MAR 26,2013 EST NO 016 & FINAL INC. 13721 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 14 RMC - 623445001 6234-45-001 198,917.25 .00 198,917.25 .00 .00 198,917.25 198,917.25 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 198,917.25 .00 198,917.25 .00 .00 198,917.25 198,917.25 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11110902 MGR.NO. 801 PAGE 001 CONT 6234 SEC 45 JOB 001 RES ENGR BASHI, ALI PROJ RMC - 623445001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 200,828.98 REPORT DATE 07/24/2013 16.29.01 CONTRACTOR CEN-TEX IRRIGATION SYSTEMS, EST PERIOD JAN 09,2012 TO MAR 26,2013 EST NO 016 & FINAL INC. 13721 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6234-45-001 RMC - 623445001 09 US0190 BELL -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 198,917.25