1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 12120905 MGR.NO. 805 PAGE 001 CONT 6250 SEC 55 JOB 001 RES ENGR CHAU, JACOB PROJ RMC - 625055001 HWY SH0007 1400 S. ABBOTT AVE. HILLS CNTY FALLS DIST 09 CONTRACT PRICE $ 159,083.41 REPORT DATE 01/21/2014 14.07.41 CONTRACTOR P-VILLE, INCORPORATED 6856 EST PERIOD JUN 10,2013 TO OCT 15,2013 EST NO 006 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 10, 2013 TIME COMPUTED FROM JUN 17, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 63 113 43 70 BROUGHT FORWARD ADDL DAYS GRANTED = 0 OCT 13 1 1 TOTAL DAYS ALLOWED = 63 2 1 DATE WORK COMPLETED 10/15/13 3 1 DAYS CHARGED TO DATE = 58 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 128 58 70 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 12120905 MGR.NO. 805 PAGE 001 CONT 6250 SEC 55 JOB 001 RES ENGR CHAU, JACOB PROJ RMC - 625055001 HWY SH0007 1400 S. ABBOTT AVE. HILLS CNTY FALLS DIST 09 CONTRACT PRICE $ 159,083.41 REPORT DATE 01/21/2014 14.07.42 CONTRACTOR P-VILLE, INCORPORATED 6856 EST PERIOD JUN 10,2013 TO OCT 15,2013 EST NO 006 & FINAL DIST. 09 COUNTY FALLS CONTROL 6250-55-001 PROJECT RMC - 625055001 HIGHWAY SH0007 0LIMITS- VARIOUS ROADWAYS IN FALLS COUNTY 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED OCTOBER 2012 0 0055 ROADWAY NET LENGTH338.743 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 SPOT MOWING AC 15.000 0.000 2.000 .00 0065 0730 FULL-WIDTH MOWING - (RURAL) AC 7,164.568 7,164.568 22.200 159,053.41 0 SUBTOTAL BID ITEMS $ 159,053.41 0 TOTAL AMOUNT WORK DONE ROADWAY $ 159,053.41 0 TOTAL AMOUNT WORK DONE CONTROL 6250-55-001 $ 159,053.41 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 12120905 MGR.NO. 805 PAGE 001 CONT 6250 SEC 55 JOB 001 RES ENGR CHAU, JACOB PROJ RMC - 625055001 HWY SH0007 1400 S. ABBOTT AVE. HILLS CNTY FALLS DIST 09 CONTRACT PRICE $ 159,083.41 REPORT DATE 01/21/2014 14.07.42 CONTRACTOR P-VILLE, INCORPORATED 6856 EST PERIOD JUN 10,2013 TO OCT 15,2013 EST NO 006 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN 0 FALLS COUNTY DATE WORK BEGAN JUN 10, 2013 WORKING DAYS USED 58 PERCENT COMPLETE 100.00 PERCENT TIME USED 92.00 DATE COMPLETED OCT 15 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6250-55-001 RMC - 625055001 09 SH0007 FALLS - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING - (RURAL) AC 7,164.568 7,164.568 22.200 159,053.41 0 SUBTOTAL BID ITEMS $ 159,053.41 0 CONTRACT TOTAL ALL ITEMS $ 159,053.41 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 12120905 MGR.NO. 805 PAGE 001 CONT 6250 SEC 55 JOB 001 RES ENGR CHAU, JACOB PROJ RMC - 625055001 HWY SH0007 1400 S. ABBOTT AVE. HILLS CNTY FALLS DIST 09 CONTRACT PRICE $ 159,083.41 REPORT DATE 01/21/2014 14.07.42 CONTRACTOR P-VILLE, INCORPORATED 6856 EST PERIOD JUN 10,2013 TO OCT 15,2013 EST NO 006 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 74 RMC - 625055001 6250-55-001 159,053.41 .00 159,053.41 .00 .00 159,053.41 159,053.41 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 159,053.41 .00 159,053.41 .00 .00 159,053.41 159,053.41 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 12120905 MGR.NO. 805 PAGE 001 CONT 6250 SEC 55 JOB 001 RES ENGR CHAU, JACOB PROJ RMC - 625055001 HWY SH0007 1400 S. ABBOTT AVE. HILLS CNTY FALLS DIST 09 CONTRACT PRICE $ 159,083.41 REPORT DATE 01/21/2014 14.07.42 CONTRACTOR P-VILLE, INCORPORATED 6856 EST PERIOD JUN 10,2013 TO OCT 15,2013 EST NO 006 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6250-55-001 RMC - 625055001 09 SH0007 FALLS -LIMITS - VARIOUS ROADWAYS IN FALLS COUNTY - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 159,053.41