1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2130901 MGR.NO. 801 PAGE 001 CONT 6253 SEC 23 JOB 001 RES ENGR BASHI, ALI PROJ ABT - 625323001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 134,805.00 REPORT DATE 01/23/2014 14.37.18 CONTRACTOR EMPIRE ENVIRONMENTAL GROUP, EST PERIOD JUL 15,2013 TO OCT 10,2013 EST NO 004 & FINAL LLC 13867 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 18, 2013 TIME COMPUTED FROM JUL 15, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 40 78 40 38 BROUGHT FORWARD ADDL DAYS GRANTED = 5 OCT 13 1 1 TOTAL DAYS ALLOWED = 45 2 1 DATE WORK COMPLETED 10/10/13 3 1 DAYS CHARGED TO DATE = 47 4 1 ASSESSED LIQ DAMAGES = 2 5 1 SATURDAY LIQ DAMAGE RATE $ 590 6 1 SUNDAY 7 1 LIQUIDATED DAMAGES 8 1 2 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ 1,180.00 10 1 WORK COMPLETED AND ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 88 47 41 1 SATURDAY 1 SUNDAY 0 HOLIDAY 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2130901 MGR.NO. 801 PAGE 001 CONT 6253 SEC 23 JOB 001 RES ENGR BASHI, ALI PROJ ABT - 625323001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 134,805.00 REPORT DATE 01/23/2014 14.37.19 CONTRACTOR EMPIRE ENVIRONMENTAL GROUP, EST PERIOD JUL 15,2013 TO OCT 10,2013 EST NO 004 & FINAL LLC 13867 DIST. 09 COUNTY BELL CONTROL 6253-23-001 PROJECT ABT - 625323001 HIGHWAY US0190 0LIMITS- VARIOUS LOCATIONS ON US 190 IN BELL COUNTY 0TYPE OF WORK- BRIDGE ASBESTOS ABATEMENT 0 0005 PREPARED DECEMBER 2012 0 0055 ASBESTOS ABATEMENT NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0500 MOBILIZATION LS 1.000 1.000 4,500.000 4,500.00 0065 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 3.000 9,000.000 27,000.00 0065 0502 ADJ EST QUANTITY TO DATE 3.000 0070 7602 ASBESTOS ABATEMENT (COATINGS) SF 14,974.000 16,604.490 7.500 124,533.68 0070 7602 ADJ EST QUANTITY TO DATE 16,604.490 0075 9001*LAW ENFORCEMENT HR 391.000 391.000 40.000 15,640.00 0 SUBTOTAL BID ITEMS $ 171,673.68 0 TOTAL AMOUNT WORK DONE ASBESTOS ABATEMENT $ 171,673.68 0 TOTAL AMOUNT WORK DONE CONTROL 6253-23-001 $ 171,673.68 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2130901 MGR.NO. 801 PAGE 001 CONT 6253 SEC 23 JOB 001 RES ENGR BASHI, ALI PROJ ABT - 625323001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 134,805.00 REPORT DATE 01/23/2014 14.37.19 CONTRACTOR EMPIRE ENVIRONMENTAL GROUP, EST PERIOD JUL 15,2013 TO OCT 10,2013 EST NO 004 & FINAL LLC 13867 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS ON 0 US 190 IN BELL COUNTY DATE WORK BEGAN JUL 18, 2013 WORKING DAYS USED 47 PERCENT COMPLETE 100.00 PERCENT TIME USED 104.40 DATE COMPLETED OCT 10 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6253-23-001 ABT - 625323001 09 US0190 BELL - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0500 MOBILIZATION LS 1.000 1.000 4,500.000 4,500.00 0502 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 2.000 3.000 9,000.000 27,000.00 0502 ADJ EST QUANTITY TO DATE 3.000 7602 ASBESTOS ABATEMENT (COATINGS) SF 14,974.000 16,604.490 7.500 124,533.68 7602* ADJ EST QUANTITY TO DATE 16,604.490 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 09001* LAW ENFORCEMENT HR 391.000 391.000 40.000 15,640.00 0 SUBTOTAL BID ITEMS $ 171,673.68 0 CONTRACT TOTAL ALL ITEMS $ 171,673.68 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2130901 MGR.NO. 801 PAGE 001 CONT 6253 SEC 23 JOB 001 RES ENGR BASHI, ALI PROJ ABT - 625323001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 134,805.00 REPORT DATE 01/23/2014 14.37.19 CONTRACTOR EMPIRE ENVIRONMENTAL GROUP, EST PERIOD JUL 15,2013 TO OCT 10,2013 EST NO 004 & FINAL LLC 13867 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 14 ABT - 625323001 6253-23-001 171,673.68 .00 171,673.68 .00 1,180.00 170,493.68 133,410.00 37,083.68 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 171,673.68 .00 171,673.68 .00 1,180.00 170,493.68 133,410.00 37,083.68 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2130901 MGR.NO. 801 PAGE 001 CONT 6253 SEC 23 JOB 001 RES ENGR BASHI, ALI PROJ ABT - 625323001 HWY US0190 410 W. LOOP 121 BELTON CNTY BELL DIST 09 CONTRACT PRICE $ 134,805.00 REPORT DATE 01/23/2014 14.37.19 CONTRACTOR EMPIRE ENVIRONMENTAL GROUP, EST PERIOD JUL 15,2013 TO OCT 10,2013 EST NO 004 & FINAL LLC 13867 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6253-23-001 ABT - 625323001 09 US0190 BELL -LIMITS - VARIOUS LOCATIONS ON US 190 IN BELL COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0500 MOBILIZATION LS 1.000 0.100 4,500.000 450.00 70 7602 ASBESTOS ABATEMENT SF 14,974.000 2,956.490 7.500 22,173.68 (COATINGS) 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 75 9001* LAW ENFORCEMENT HR 0.000 391.000 40.000 15,640.00 0 * ITEMS ADDED IN ACCORDANCE WITH STANDARD SPECIFICATIONS OR BY SUPPLEMENTAL AGREEMENTS 0 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 38,263.68 0 TOTAL AMOUNT WORK DONE TO DATE - $ 171,673.68