1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 8130944 MGR.NO. 830 PAGE 001 CONT 6259 SEC 96 JOB 001 RES ENGR PIERCE, RICKY PROJ SUP - 625996001 HWY SP0299 100 S. LOOP DRIVE WACO CNTY MCLENNAN DIST 09 CONTRACT PRICE $ 5,200.00 REPORT DATE 08/05/2014 11.09.12 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 011 GOODWILL CONTRACT SERVICES, INC. 09737 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN SEP 01, 2013 TIME COMPUTED FROM SEP 01, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 104 303 78 225 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JUL 14 1 1 NO WORK SCHEDULED BY TXDOT TOTAL DAYS ALLOWED = 104 2 1 NO WORK SCHEDULED BY TXDOT DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 87 4 1 NO WORK SCHEDULED BY TXDOT ASSESSED LIQ DAMAGES = 0 5 1 SATURDAY LIQ DAMAGE RATE $ 0 6 1 SUNDAY 7 1 LIQUIDATED DAMAGES 8 1 NO WORK SCHEDULED BY TXDOT 0 DAYS AT $ 0 PER DAY 9 1 NO WORK SCHEDULED BY TXDOT TOTAL = $ .00 10 1 11 1 NO WORK SCHEDULED BY TXDOT CERTIFIED AS CORRECT AND 12 1 SATURDAY ONE COPY HAS BEEN GIVEN 13 1 SUNDAY TO THE CONTRACTOR 14 1 15 1 NO WORK SCHEDULED BY TXDOT 16 1 NO WORK SCHEDULED BY TXDOT ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 NO WORK SCHEDULED BY TXDOT 19 1 SATURDAY 20 1 SUNDAY 21 1 22 1 NO WORK SCHEDULED BY TXDOT 23 1 NO WORK SCHEDULED BY TXDOT 24 1 25 1 NO WORK SCHEDULED BY TXDOT 26 1 SATURDAY 27 1 SUNDAY 28 1 29 1 NO WORK SCHEDULED BY TXDOT 30 1 NO WORK SCHEDULED BY TXDOT 31 1 ----- ----- ----- 334 87 247 4 SATURDAY 4 SUNDAY 0 HOLIDAY 14 NO WORK SCHEDULED BY TXDOT 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 8130944 MGR.NO. 830 PAGE 001 CONT 6259 SEC 96 JOB 001 RES ENGR PIERCE, RICKY PROJ SUP - 625996001 HWY SP0299 100 S. LOOP DRIVE WACO CNTY MCLENNAN DIST 09 CONTRACT PRICE $ 5,200.00 REPORT DATE 08/05/2014 11.09.13 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 011 GOODWILL CONTRACT SERVICES, INC. 09737 DIST. 09 COUNTY MCLENNAN CONTROL 6259-96-001 PROJECT SUP - 625996001 HIGHWAY SP0299 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- CLEANING/SWEEPING DISTRICT COMPLEX 0 0005 PREPARED AUGUST 2013 0 0055 CLEAN SIDEWALKS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 7206 ADDITIONAL LABOR HR 208.000 174.000 25.000 4,350.00 0 SUBTOTAL BID ITEMS $ 4,350.00 0 TOTAL AMOUNT WORK DONE CLEAN SIDEWALKS $ 4,350.00 0 TOTAL AMOUNT WORK DONE CONTROL 6259-96-001 $ 4,350.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 8130944 MGR.NO. 830 PAGE 001 CONT 6259 SEC 96 JOB 001 RES ENGR PIERCE, RICKY PROJ SUP - 625996001 HWY SP0299 100 S. LOOP DRIVE WACO CNTY MCLENNAN DIST 09 CONTRACT PRICE $ 5,200.00 REPORT DATE 08/05/2014 11.09.13 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 011 GOODWILL CONTRACT SERVICES, INC. 09737 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN SEP 1 , 2013 WORKING DAYS USED 87 PERCENT COMPLETE 83.65 PERCENT TIME USED 83.60 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6259-96-001 SUP - 625996001 09 SP0299 MCLENNAN - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -7206 ADDITIONAL LABOR HR 208.000 174.000 25.000 4,350.00 0 SUBTOTAL BID ITEMS $ 4,350.00 0 CONTRACT TOTAL ALL ITEMS $ 4,350.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 8130944 MGR.NO. 830 PAGE 001 CONT 6259 SEC 96 JOB 001 RES ENGR PIERCE, RICKY PROJ SUP - 625996001 HWY SP0299 100 S. LOOP DRIVE WACO CNTY MCLENNAN DIST 09 CONTRACT PRICE $ 5,200.00 REPORT DATE 08/05/2014 11.09.13 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 011 GOODWILL CONTRACT SERVICES, INC. 09737 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 161 SUP - 625996001 6259-96-001 4,350.00 .00 4,350.00 .00 .00 4,350.00 3,900.00 450.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 4,350.00 .00 4,350.00 .00 .00 4,350.00 3,900.00 450.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 8130944 MGR.NO. 830 PAGE 001 CONT 6259 SEC 96 JOB 001 RES ENGR PIERCE, RICKY PROJ SUP - 625996001 HWY SP0299 100 S. LOOP DRIVE WACO CNTY MCLENNAN DIST 09 CONTRACT PRICE $ 5,200.00 REPORT DATE 08/05/2014 11.09.13 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUL 01,2014 TO JUL 31,2014 EST NO 011 GOODWILL CONTRACT SERVICES, INC. 09737 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6259-96-001 SUP - 625996001 09 SP0299 MCLENNAN -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 7206 ADDITIONAL LABOR HR 208.000 18.000 25.000 450.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 450.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 4,350.00