1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 7110302 MGR.NO. 010 PAGE 001 CONT 6227 SEC 01 JOB 001 RES ENGR ROHMER, DAVID PROJ RMC - 622701001 HWY IH0035 1601 SOUTHWEST PKWY WICHI CNTY COOKE DIST 03 CONTRACT PRICE $ 59,725.00 REPORT DATE 12/05/2013 13.02.23 CONTRACTOR HIGHWAY INTELLIGENT TRAFFIC EST PERIOD NOV 29,2011 TO NOV 29,2013 EST NO 018 & FINAL SYSTEMS, CORP. 13538 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN NOV 29, 2011 TIME COMPUTED FROM DEC 06, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 489 487 2 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 13 1 1 TOTAL DAYS ALLOWED = 730 2 1 DATE WORK COMPLETED 11/29/13 3 1 DAYS CHARGED TO DATE = 516 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 425 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 425 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 - ----- ----- ----- 518 516 2 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 7110302 MGR.NO. 010 PAGE 001 CONT 6227 SEC 01 JOB 001 RES ENGR ROHMER, DAVID PROJ RMC - 622701001 HWY IH0035 1601 SOUTHWEST PKWY WICHI CNTY COOKE DIST 03 CONTRACT PRICE $ 59,725.00 REPORT DATE 12/05/2013 13.02.23 CONTRACTOR HIGHWAY INTELLIGENT TRAFFIC EST PERIOD NOV 29,2011 TO NOV 29,2013 EST NO 018 & FINAL SYSTEMS, CORP. 13538 DIST. 03 COUNTY COOKE CONTROL 6227-01-001 PROJECT RMC - 622701001 HIGHWAY IH0035 0LIMITS- VARIOUS LOCATIONS DISTRICT WIDE 0TYPE OF WORK- ONCALL LOOP DETECTOR INSTALL & REPAIR 0 0005 PREPARED BY LARRY TEGTMEYER P.E. 0 0055 ONCALL LOOP DETECTOR INSTALL & REPA NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0618 CONDT (PVC) (SCHD 40) (1") LF 100.000 0.000 5.000 .00 0065 0618 CONDT (PVC) (SCHD 40) ( 2") LF 100.000 0.000 8.000 .00 0070 0618 CONDT (PVC) (SCHD 80) (1") (BORE) LF 100.000 0.000 14.000 .00 0075 0618 CONDT (PVC) (SCHD 80) (2") (BORE) LF 50.000 0.000 18.000 .00 0080 0624 GROUND BOX TY A (122311) W/APRON EA 5.000 0.000 650.000 .00 0085 0624 GROUND BOX TY C (162911) W/APRON EA 2.000 0.000 700.000 .00 0090 0684 TRF SIG CBL (TY C) (14 AWG) ( 2 CONDR) LF 500.000 0.000 2.000 .00 0095 0688 VEH LP DETECT (SAWCUT) LF 3,500.000 2,512.000 8.250 20,724.00 0100 6266 VIVIDS CAMERA SYS (INSTALLATION ONLY) EA 24.000 0.000 300.000 .00 0105 6266 VIVDS COMMUNICATION CABLE (COAXIAL) LF 6,000.000 0.000 2.400 .00 0 SUBTOTAL BID ITEMS $ 20,724.00 0 TOTAL AMOUNT WORK DONE ONCALL LOOP DETECTOR INSTALL & REPA $ 20,724.00 0 TOTAL AMOUNT WORK DONE CONTROL 6227-01-001 $ 20,724.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 7110302 MGR.NO. 010 PAGE 001 CONT 6227 SEC 01 JOB 001 RES ENGR ROHMER, DAVID PROJ RMC - 622701001 HWY IH0035 1601 SOUTHWEST PKWY WICHI CNTY COOKE DIST 03 CONTRACT PRICE $ 59,725.00 REPORT DATE 12/05/2013 13.02.23 CONTRACTOR HIGHWAY INTELLIGENT TRAFFIC EST PERIOD NOV 29,2011 TO NOV 29,2013 EST NO 018 & FINAL SYSTEMS, CORP. 13538 0*********************************************************************************************************************************** -LIMITS - VARIOUS LOCATIONS 0 DISTRICT WIDE DATE WORK BEGAN NOV 29, 2011 WORKING DAYS USED 516 PERCENT COMPLETE 100.00 PERCENT TIME USED 70.60 DATE COMPLETED NOV 29 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6227-01-001 RMC - 622701001 03 IH0035 COOKE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0688 VEH LP DETECT (SAWCUT) LF 3,500.000 2,512.000 8.250 20,724.00 0 SUBTOTAL BID ITEMS $ 20,724.00 0 CONTRACT TOTAL ALL ITEMS $ 20,724.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 7110302 MGR.NO. 010 PAGE 001 CONT 6227 SEC 01 JOB 001 RES ENGR ROHMER, DAVID PROJ RMC - 622701001 HWY IH0035 1601 SOUTHWEST PKWY WICHI CNTY COOKE DIST 03 CONTRACT PRICE $ 59,725.00 REPORT DATE 12/05/2013 13.02.23 CONTRACTOR HIGHWAY INTELLIGENT TRAFFIC EST PERIOD NOV 29,2011 TO NOV 29,2013 EST NO 018 & FINAL SYSTEMS, CORP. 13538 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 49 RMC - 622701001 6227-01-001 20,724.00 .00 20,724.00 .00 .00 20,724.00 20,724.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 20,724.00 .00 20,724.00 .00 .00 20,724.00 20,724.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 7110302 MGR.NO. 010 PAGE 001 CONT 6227 SEC 01 JOB 001 RES ENGR ROHMER, DAVID PROJ RMC - 622701001 HWY IH0035 1601 SOUTHWEST PKWY WICHI CNTY COOKE DIST 03 CONTRACT PRICE $ 59,725.00 REPORT DATE 12/05/2013 13.02.24 CONTRACTOR HIGHWAY INTELLIGENT TRAFFIC EST PERIOD NOV 29,2011 TO NOV 29,2013 EST NO 018 & FINAL SYSTEMS, CORP. 13538 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6227-01-001 RMC - 622701001 03 IH0035 COOKE -LIMITS - VARIOUS LOCATIONS DISTRICT WIDE - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 20,724.00