1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 10110332 MGR.NO. 010 PAGE 001 CONT 6234 SEC 37 JOB 001 RES ENGR STAFFORD, RUSTY PROJ SUP - 623437001 HWY US0082 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 14,613.20 REPORT DATE 07/01/2014 11.23.42 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 033 WORK SERVICES CORPORATION 11541 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN OCT 01, 2011 TIME COMPUTED FROM OCT 01, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 730 974 974 0 BROUGHT FORWARD ADDL DAYS GRANTED = 365 JUN 14 1 1 TOTAL DAYS ALLOWED = 1,095 2 1 DATE WORK COMPLETED 3 1 DAYS CHARGED TO DATE = 1,004 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 0 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 0 PER DAY 9 1 TOTAL = $ .00 10 1 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 ---------------------------- 17 1 AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 25 1 26 1 27 1 28 1 29 1 30 1 0 ----- ----- ----- 1,004 1,004 0 0 SATURDAY 0 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 10110332 MGR.NO. 010 PAGE 001 CONT 6234 SEC 37 JOB 001 RES ENGR STAFFORD, RUSTY PROJ SUP - 623437001 HWY US0082 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 14,613.20 REPORT DATE 07/01/2014 11.23.42 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 033 WORK SERVICES CORPORATION 11541 DIST. 03 COUNTY WICHITA CONTROL 6234-37-001 PROJECT SUP - 623437001 HIGHWAY US0082 0LIMITS- WF ENGINEER/MAINTENANCE COMPLEX 0TYPE OF WORK- GROUNDS MAINTENANCE 0 0005 GROUNDS MAINTENANCE 0 0055 PREPARED BY SS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0745 GROUNDS MAINT (MOWING/TRIMMING) CYC 50.000 36.000 278.120 10,012.32 0065 0751 PLANT BED MAINTENANCE (SITE A) CYC 16.000 11.000 44.200 486.20 0 SUBTOTAL BID ITEMS $ 10,498.52 0 TOTAL AMOUNT WORK DONE PREPARED BY SS $ 10,498.52 0 TOTAL AMOUNT WORK DONE CONTROL 6234-37-001 $ 10,498.52 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 10110332 MGR.NO. 010 PAGE 001 CONT 6234 SEC 37 JOB 001 RES ENGR STAFFORD, RUSTY PROJ SUP - 623437001 HWY US0082 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 14,613.20 REPORT DATE 07/01/2014 11.23.42 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 033 WORK SERVICES CORPORATION 11541 0*********************************************************************************************************************************** -LIMITS - WF ENGINEER/MAINTENANCE 0 COMPLEX DATE WORK BEGAN OCT 1 , 2011 WORKING DAYS USED 1004 PERCENT COMPLETE 71.84 PERCENT TIME USED 91.60 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6234-37-001 SUP - 623437001 03 US0082 WICHITA - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0745 GROUNDS MAINT (MOWING/TRIMMING) CYC 50.000 36.000 278.120 10,012.32 0751 PLANT BED MAINTENANCE (SITE A) CYC 16.000 11.000 44.200 486.20 0 SUBTOTAL BID ITEMS $ 10,498.52 0 CONTRACT TOTAL ALL ITEMS $ 10,498.52 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 10110332 MGR.NO. 010 PAGE 001 CONT 6234 SEC 37 JOB 001 RES ENGR STAFFORD, RUSTY PROJ SUP - 623437001 HWY US0082 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 14,613.20 REPORT DATE 07/01/2014 11.23.42 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 033 WORK SERVICES CORPORATION 11541 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 243 SUP - 623437001 6234-37-001 10,498.52 .00 10,498.52 .00 .00 10,498.52 10,176.20 322.32 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 10,498.52 .00 10,498.52 .00 .00 10,498.52 10,176.20 322.32 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 10110332 MGR.NO. 010 PAGE 001 CONT 6234 SEC 37 JOB 001 RES ENGR STAFFORD, RUSTY PROJ SUP - 623437001 HWY US0082 1601 SOUTHWEST PKWY WICHI CNTY WICHITA DIST 03 CONTRACT PRICE $ 14,613.20 REPORT DATE 07/01/2014 11.23.43 CONTRACTOR TIBH INDUSTRIES, INC. 9160 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 033 WORK SERVICES CORPORATION 11541 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6234-37-001 SUP - 623437001 03 US0082 WICHITA -LIMITS - WF ENGINEER/MAINTENANCE COMPLEX LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0745 GROUNDS MAINT CYC 50.000 1.000 278.120 278.12 (MOWING/TRIMMING) 65 0751 PLANT BED MAINTENANCE (SITE CYC 16.000 1.000 44.200 44.20 A) --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 322.32 0 TOTAL AMOUNT WORK DONE TO DATE - $ 10,498.52