1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2130306 MGR.NO. 010 PAGE 001 CONT 6254 SEC 02 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625402001 HWY SH0079 1601 SOUTHWEST PKWY WICHI CNTY CLAY DIST 03 CONTRACT PRICE $ 105,273.50 REPORT DATE 01/16/2014 07.23.04 CONTRACTOR FOUR R OILFIELD SERVICES, LLC 15753 EST PERIOD JUL 01,2013 TO JAN 14,2014 EST NO 007 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUL 01, 2013 TIME COMPUTED FROM JUL 08, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 54 184 37 147 BROUGHT FORWARD ADDL DAYS GRANTED = 0 JAN 14 1 1 HOLIDAY TOTAL DAYS ALLOWED = 54 2 1 DATE WORK COMPLETED 01/14/14 3 1 DAYS CHARGED TO DATE = 45 4 1 ASSESSED LIQ DAMAGES = 0 5 1 SUNDAY LIQ DAMAGE RATE $ 590 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 590 PER DAY 9 1 TOTAL = $ .00 10 1 TOO WET 11 1 SATURDAY CERTIFIED AS CORRECT AND 12 1 SUNDAY ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 WORK COMPLETED AND ACCEPTED 0 ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 198 45 153 1 SATURDAY 2 SUNDAY 1 HOLIDAY 1 TOO WET 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2130306 MGR.NO. 010 PAGE 001 CONT 6254 SEC 02 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625402001 HWY SH0079 1601 SOUTHWEST PKWY WICHI CNTY CLAY DIST 03 CONTRACT PRICE $ 105,273.50 REPORT DATE 01/16/2014 07.23.05 CONTRACTOR FOUR R OILFIELD SERVICES, LLC 15753 EST PERIOD JUL 01,2013 TO JAN 14,2014 EST NO 007 & FINAL DIST. 03 COUNTY CLAY CONTROL 6254-02-001 PROJECT RMC - 625402001 HIGHWAY SH0079 0LIMITS- VARIOUS ROADWAYS IN CLAY COUNTY 0TYPE OF WORK- RIGHT OF WAY MOWING 0 0005 PREPARED BY LARRY TEGTMEYER PE 0 0055 RIGHT OF WAY MOWING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 STRIP MOWING AC 565.000 0.000 19.500 .00 0065 0730 FULL-WIDTH MOWING AC 4,712.800 4,712.800 20.000 94,256.00 0 SUBTOTAL BID ITEMS $ 94,256.00 0 SPECIAL DEDUCTIONS - 0 LINE MATRL. NO MATERIAL DESCRIPTION UNIT QUANTITY UNIT AMOUNT NO. PRICE($) ($) - 0100 00000000779 DELINEATORS EA 5.000 35.000 -175.00 0 0105 00000000779 DELINEATORS EA 5.000 40.000 -200.00 0 TOTAL SPECIAL DEDUCTIONS - $ -375.00 0 TOTAL AMOUNT WORK DONE RIGHT OF WAY MOWING $ 94,256.00 TOTAL SPECIAL DEDUCTIONS RIGHT OF WAY MOWING $ -375.00 0 TOTAL AMOUNT WORK DONE CONTROL 6254-02-001 $ 94,256.00 0 TOTAL SPECIAL DEDUCTIONS CONTROL 6254-02-001 $ -375.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2130306 MGR.NO. 010 PAGE 001 CONT 6254 SEC 02 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625402001 HWY SH0079 1601 SOUTHWEST PKWY WICHI CNTY CLAY DIST 03 CONTRACT PRICE $ 105,273.50 REPORT DATE 01/16/2014 07.23.05 CONTRACTOR FOUR R OILFIELD SERVICES, LLC 15753 EST PERIOD JUL 01,2013 TO JAN 14,2014 EST NO 007 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN 0 CLAY COUNTY DATE WORK BEGAN JUL 1 , 2013 WORKING DAYS USED 45 PERCENT COMPLETE 100.00 PERCENT TIME USED 83.30 DATE COMPLETED JAN 14 2014 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6254-02-001 RMC - 625402001 03 SH0079 CLAY - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 4,712.800 4,712.800 20.000 94,256.00 0 SUBTOTAL BID ITEMS $ 94,256.00 0 CONTRACT TOTAL ALL ITEMS $ 94,256.00 SPECIAL DEDUCTIONS 0 UNIT AMOUNT MATRL. NO. MATERIAL DESCRIPTION UNIT QUANTITY PRICE ($) ($) 0 00000000779 DELINEATORS EA 5.000 40.000 -200.00 0 00000000779 DELINEATORS EA 5.000 35.000 -175.00 0 TOTAL SPECIAL DEDUCTIONS $ -375.00 0 CONTRACT TOTAL SPECIAL DEDUCTIONS $ -375.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2130306 MGR.NO. 010 PAGE 001 CONT 6254 SEC 02 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625402001 HWY SH0079 1601 SOUTHWEST PKWY WICHI CNTY CLAY DIST 03 CONTRACT PRICE $ 105,273.50 REPORT DATE 01/16/2014 07.23.05 CONTRACTOR FOUR R OILFIELD SERVICES, LLC 15753 EST PERIOD JUL 01,2013 TO JAN 14,2014 EST NO 007 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 39 RMC - 625402001 6254-02-001 94,256.00 .00 94,256.00 375.00 .00 93,881.00 84,543.00 9,338.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 94,256.00 .00 94,256.00 375.00 .00 93,881.00 84,543.00 9,338.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2130306 MGR.NO. 010 PAGE 001 CONT 6254 SEC 02 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625402001 HWY SH0079 1601 SOUTHWEST PKWY WICHI CNTY CLAY DIST 03 CONTRACT PRICE $ 105,273.50 REPORT DATE 01/16/2014 07.23.05 CONTRACTOR FOUR R OILFIELD SERVICES, LLC 15753 EST PERIOD JUL 01,2013 TO JAN 14,2014 EST NO 007 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6254-02-001 RMC - 625402001 03 SH0079 CLAY -LIMITS - VARIOUS ROADWAYS IN CLAY COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 65 0730 FULL-WIDTH MOWING AC 4,712.800 476.900 20.000 9,538.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 9,538.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 94,256.00