1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 2130307 MGR.NO. 010 PAGE 001 CONT 6254 SEC 05 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625405001 HWY US0082 1601 SOUTHWEST PKWY WICHI CNTY MONTAGUE DIST 03 CONTRACT PRICE $ 88,858.14 REPORT DATE 12/03/2013 08.58.38 CONTRACTOR EDDIE G. TYLER 7883 EST PERIOD JUN 10,2013 TO NOV 24,2013 EST NO 006 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 10, 2013 TIME COMPUTED FROM JUN 17, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 51 144 26 118 BROUGHT FORWARD ADDL DAYS GRANTED = 0 NOV 13 1 1 TOTAL DAYS ALLOWED = 51 2 1 DATE WORK COMPLETED 11/24/13 3 1 SUNDAY DAYS CHARGED TO DATE = 43 4 1 ASSESSED LIQ DAMAGES = 0 5 1 RAIN LIQ DAMAGE RATE $ 570 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 570 PER DAY 9 1 SATURDAY TOTAL = $ .00 10 1 SUNDAY 11 1 CERTIFIED AS CORRECT AND 12 1 ONE COPY HAS BEEN GIVEN 13 1 TO THE CONTRACTOR 14 1 15 1 16 1 SATURDAY ---------------------------- 17 1 SUNDAY AREA/PROJECT ENGINEER 18 1 19 1 20 1 21 1 22 1 23 1 24 1 WORK COMPLETED AND ACCEPTED - - 0 ----- ----- ----- 168 43 125 2 SATURDAY 3 SUNDAY 0 HOLIDAY 1 RAIN 1 WORK COMPLETED AND ACCEPTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 2130307 MGR.NO. 010 PAGE 001 CONT 6254 SEC 05 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625405001 HWY US0082 1601 SOUTHWEST PKWY WICHI CNTY MONTAGUE DIST 03 CONTRACT PRICE $ 88,858.14 REPORT DATE 12/03/2013 08.58.39 CONTRACTOR EDDIE G. TYLER 7883 EST PERIOD JUN 10,2013 TO NOV 24,2013 EST NO 006 & FINAL DIST. 03 COUNTY MONTAGUE CONTROL 6254-05-001 PROJECT RMC - 625405001 HIGHWAY US0082 0LIMITS- VARIOUS ROADWAYS IN MONTAGUE AND COOKE COUNTY 0TYPE OF WORK- RIGHT OF WAY MOWING 0 0005 PREPARED BY LARRY TEGTMEYER PE 0 0055 RIGHT OF WAY MOWING NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 5,098.000 5,098.000 17.430 88,858.14 0 SUBTOTAL BID ITEMS $ 88,858.14 0 TOTAL AMOUNT WORK DONE RIGHT OF WAY MOWING $ 88,858.14 0 TOTAL AMOUNT WORK DONE CONTROL 6254-05-001 $ 88,858.14 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 2130307 MGR.NO. 010 PAGE 001 CONT 6254 SEC 05 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625405001 HWY US0082 1601 SOUTHWEST PKWY WICHI CNTY MONTAGUE DIST 03 CONTRACT PRICE $ 88,858.14 REPORT DATE 12/03/2013 08.58.39 CONTRACTOR EDDIE G. TYLER 7883 EST PERIOD JUN 10,2013 TO NOV 24,2013 EST NO 006 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS ROADWAYS IN MONTAGUE 0 AND COOKE COUNTY DATE WORK BEGAN JUN 10, 2013 WORKING DAYS USED 43 PERCENT COMPLETE 100.00 PERCENT TIME USED 84.30 DATE COMPLETED NOV 24 2013 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6254-05-001 RMC - 625405001 03 US0082 MONTAGUE - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 5,098.000 5,098.000 17.430 88,858.14 0 SUBTOTAL BID ITEMS $ 88,858.14 0 CONTRACT TOTAL ALL ITEMS $ 88,858.14 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 2130307 MGR.NO. 010 PAGE 001 CONT 6254 SEC 05 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625405001 HWY US0082 1601 SOUTHWEST PKWY WICHI CNTY MONTAGUE DIST 03 CONTRACT PRICE $ 88,858.14 REPORT DATE 12/03/2013 08.58.39 CONTRACTOR EDDIE G. TYLER 7883 EST PERIOD JUN 10,2013 TO NOV 24,2013 EST NO 006 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 169 RMC - 625405001 6254-05-001 88,858.14 .00 88,858.14 .00 .00 88,858.14 55,950.30 32,907.84 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 88,858.14 .00 88,858.14 .00 .00 88,858.14 55,950.30 32,907.84 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 2130307 MGR.NO. 010 PAGE 001 CONT 6254 SEC 05 JOB 001 RES ENGR STAFFORD, RUSTY PROJ RMC - 625405001 HWY US0082 1601 SOUTHWEST PKWY WICHI CNTY MONTAGUE DIST 03 CONTRACT PRICE $ 88,858.14 REPORT DATE 12/03/2013 08.58.39 CONTRACTOR EDDIE G. TYLER 7883 EST PERIOD JUN 10,2013 TO NOV 24,2013 EST NO 006 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6254-05-001 RMC - 625405001 03 US0082 MONTAGUE -LIMITS - VARIOUS ROADWAYS IN MONTAGUE AND COOKE COUNTY LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 5,098.000 1,888.000 17.430 32,907.84 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 32,907.84 0 TOTAL AMOUNT WORK DONE TO DATE - $ 88,858.14