Detail Letting Schedule for Kent County (FY 2005)
Detail Letting Schedule for Kent County (FY 2005) | ||||
Last Update: Monday, August 15, 2005 |
Kent County (FY 2005) |
CCSJ: 0298-02-021 | |||
District: | Abilene | Let Date: | AUG 2005 |
Highway: | US 380 | Let Status: | Actual |
Project ID: | BR 2005(658) | CSJ: | 0298-02-021 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | AT FOUR MILE CREEK | Fund Cat: | 6 |
Limits To: | . | Estimate: | $878,310 |
Length: | 0.1 Miles | Actual: | $961,959 |
District: | Abilene | Let Date: | AUG 2005 |
Highway: | SH 208 | Let Status: | Actual |
Project ID: | BR 2005(658) | CSJ: | 1361-02-021 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | AT THE DOUBLE MOUNTAIN FORK | Fund Cat: | 6 |
Limits To: | OF THE BRAZOS RIVER | Estimate: | $1,379,488 |
Length: | 0.2 Miles | Actual: | $1,512,881 |
List Showing Order Proposal Req Form Bidders List Bid Tabulations Back... |
Totals for 0298-02-021 | ||
---|---|---|---|
Length: | 0.3 Miles | ||
Estimate: | $2,257,798 | ||
Actual: | $2,474,840 |
|
|