Letting Schedule for Dallas District (FY 2005)
Letting Schedule for Dallas District (FY 2005) | ||||
Last Update: Monday, August 15, 2005 |
Dallas District (FY 2005) |
Collin | Dallas | Denton | Ellis | Kaufman | Navarro | Rockwall | ||||||
Collin County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
---|---|---|---|---|---|---|
0047-06-126 | US 75 | Actual | JUN 2005 | $391,390 | 10 | LANDSCAPE DEVELOPMENT |
0091-05-045 | SH 289 | Actual | AUG 2005 | $713,247 | 5 | 1 ON - SYSTEM INTERSECTION IMPROVEMENT |
0549-03-017 | SH 121 | Actual | JAN 2005 | $869,531 | 1 | MICROSURFACING PAVEMENT MARKINGS |
0918-24-107 | VA | Actual | MAY 2005 | $238,471 | 5 | UPGRADE AND OPTIMIZE TRAFFIC SIGNAL SYSTEM |
0918-24-109 | CS | Actual | SEP 2004 | $2,909,651 | 7 | NEW ROADWAY |
0918-24-120 | VA | Actual | FEB 2005 | $295,983 | 1 | INSTALLING SMALL SIGN MOUNTS |
1012-02-020 | FM 545 | Actual | OCT 2004 | $980,228 | 10 | ADD SHOULDERS AND RECONSTRUCT EXISTING ROADWAY ON NEW |
1012-02-026 | FM 545 | Actual | SEP 2004 | $1,574,313 | 1 | SPOT BASE REPAIR, LEVEL - UP, OVERLAY & PAVEMENT MARKINGS |
3476-02-004 | FM 3286 | Actual | SEP 2004 | $20,767,940 | 6 | REPLACE BRIDGE AND APPROACHES |
Dallas County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0008-08-067 | SH 180 | Actual | MAY 2005 | $490,668 | 1 | REHABILITATION OF EXISTING ROADWAY |
0009-11-188 | IH 30 | Actual | JUL 2005 | $3,798,061 | 1 | CONTINUOUS ILLUMINATION |
0009-11-203 | IH 30 | Actual | JAN 2005 | $177,710 | 1 | REHABILITATE DYNAMIC MESSAGE SIGN |
0047-07-179 | US 75 | Actual | JUN 2005 | $626,188 | 5 | 1 ON - SYSTEM INTERSECTION IMPROVEMENTS |
0047-07-189 | US 75 | Actual | SEP 2004 | $7,063,037 | 7 | CONSTRUCTION AND WIDENING OF CHURCHILL WAY |
0047-07-209 | US 75 | Actual | FEB 2005 | $862,400 | 10 | LANDSCAPE ESTABLISHMENT |
0091-06-038 | SH 289 | Actual | AUG 2005 | $562,333 | 5 | INTERSECTION IMPROVEMENT |
0091-06-040 | SH 289 | Actual | AUG 2005 | $1,573,953 | 5 | 1 ON SYSTEM INTERSECTION IMPROVEMENT |
0091-06-041 | SH 289 | Actual | AUG 2005 | $1,099,906 | 5 | 1 ON SYSTEM INTERSECTION IMPROVEMENT |
0091-06-042 | SH 289 | Actual | AUG 2005 | $3,391,929 | 5 | 1 ON - SYSTEM INTERSECTION IMPROVEMENT |
0092-02-110 | IH 45 | Actual | FEB 2005 | $2,151,638 | 1 | CONC. PAVEMENT, ACP OVERLAY, CLEAN & REPAIR DRAINAGE |
0092-02-111 | IH 45 | Actual | JUN 2005 | $71,522 | 10 | LANDSCAPE DEVELOPMENT |
0092-07-044 | SH 356 | Actual | AUG 2005 | $747,602 | 5 | INTERSECTION IMPROVEMENTS |
0092-14-064 | IH 345 | Actual | MAY 2005 | $488,463 | 7 | WIDEN NB TO WB RAMP TO TWO LANES |
0092-14-068 | IH 345 | Actual | OCT 2004 | $847,625 | 7 | INSTALLATION OF INCIDENT DETECTION AND RESPONSE SYSTEM |
0092-14-074 | IH 45 | Actual | NOV 2004 | $392,960 | 1 | INSTALL WIRE FENCE IN MEDIAN |
0094-03-095 | SH 183 | Actual | AUG 2005 | $195,752 | 5 | EXTEND LEFT TURN LANE |
0094-07-034 | SH 183 | Actual | JUL 2005 | $2,151,212 | 11 | RAMP RELOCATION & WIDENING OF MAINLANES |
0094-07-038 | SH 183 | Actual | OCT 2004 | $470,165 | 10 | LANDSCAPE DEVELOPMENT |
0095-02-095 | US 80 | Actual | DEC 2004 | $1,656,247 | 1 | INSTALL MEDIAN BARRIER & SAFETY LIGHTING |
0196-03-106 | IH 35E | Actual | JUN 2005 | $1,027,520 | 11 | ADD AUXILIARY LANES IN EACH DIRECTION BETWEEN ENTRANCE AND |
0196-03-191 | IH 35E | Actual | AUG 2005 | $908,495 | 5 | INTERSECTION IMPROVEMENTS |
0196-03-192 | IH 35E | Actual | AUG 2005 | $2,664,935 | 5 | 1 ON SYSTEM INTERSECTION IMPROVEMENT |
0196-03-217 | IH 35E | Actual | JUL 2005 | $1,005,348 | 5 | MODIFY TURNING RADIUS FOR TRACKS |
0196-06-022 | LP 354 | Actual | AUG 2005 | $573,437 | 5 | 1 ON SYSTEM INTESECTION IMPROVEMENT |
0197-02-091 | US 175 | Actual | JAN 2005 | $566,599 | 1 | WIDEN RAMP TO TWO LANES |
0197-02-097 | US 175 | Actual | JUL 2005 | $3,351,487 | 1 | MILL & OVERLAY, FULL DEPTH REPAIR, & SHLDR TEXTURING |
0430-01-050 | SH 352 | Actual | AUG 2005 | $983,389 | 1 | FULL DEPTH CONCRETE PAVEMENT REPAIR AND NOVACHIP |
0442-02-138 | IH 35E | Actual | JUN 2005 | $231,820 | 1 | FULL DEPTH CONCRETE PAVEMENT REPAIR |
0581-01-100 | LP 12 | Actual | JUL 2005 | $1,337,354 | 5 | INTERSECTION IMPROVEMENTS |
0581-01-125 | LP 12 | Actual | AUG 2005 | $418,432 | 5 | 1 INTERSECTION IMPROVEMENT |
0581-02-112 | LP 12 | Actual | OCT 2004 | $7,271,133 | 1 | WIDEN EXISTING 6 LANES TO 8 LANES |
0918-00-071 | VA | Actual | NOV 2004 | $4,053,010 | 1 | SEALCOAT |
0918-00-094 | VA | Actual | MAY 2005 | $4,175,000 | 5 | DECREASE EMISSIONS VIA ALTERNATIVE FUELS |
0918-00-096 | VA | Actual | DEC 2004 | $1,186,056 | 1 | COBRA HEAD REPLACEMENT |
0918-00-098 | VA | Actual | JAN 2005 | $248,993 | 1 | GROUND BOX REPLACEMENT |
0918-00-100 | VA | Actual | DEC 2004 | $413,000 | 1 | LED SIGNAL HEAD UPGRADE |
0918-00-101 | VA | Actual | FEB 2005 | $630,851 | 1 | SIGN AND SIGN STRUCTURE REPLACEMENTS |
0918-00-102 | VA | Actual | NOV 2004 | $4,422,784 | 1 | SEALCOAT |
0918-00-104 | VA | Actual | JAN 2005 | $4,300,000 | 1 | SEAL COAT |
0918-00-105 | VA | Actual | JUL 2005 | $258,444 | 1 | REPAIR CANTILEVER AND OVERHEAD SIGN BRIDGES |
0918-00-107 | VA | Actual | NOV 2004 | $200,000 | 7 | LIGHT - EMITTING DIODE TRAFFIC SIGNAL REPLACEMENT PROGRAM |
0918-00-108 | VA | Actual | APR 2005 | $261,198 | 1 | REPAIR CTB - NWAO |
0918-00-110 | VA | Actual | APR 2005 | $500,000 | 7 | DIESEL FREIGHT VEHICLE IDLING REDUCTION PROGRAM |
0918-00-111 | VA | Actual | APR 2005 | $1,000,000 | 7 | EMPLOYEE TRIP REDUCTION PROGRAM |
0918-00-112 | VA | Actual | APR 2005 | $312,500 | 7 | CLEAN FLEET VEHICLE PROCUREMENT POLICY |
0918-00-113 | VA | Actual | APR 2005 | $5,610,000 | 1 | FUNDS TRANSFER FOR CONTRACTED ROUTINE MAINTENANCE |
0918-00-116 | VA | Actual | JUN 2005 | $4,016,849 | 1 | FUNDS TRANSFER FOR BASE REPAIRS, LEVEL UP PAVEMENT AND FULL |
0918-45-166 | CR | Actual | JUL 2005 | $528,285 | 6 | REPLACE BRIDGE AND APPROACHES |
0918-45-295 | CS | Actual | FEB 2005 | $461,191 | 5 | 2 INTERSECTION IMPROVEMENTS |
0918-45-319 | CS | Actual | AUG 2005 | $909,634 | 5 | 3 INTERSECTION IMPROVEMENTS |
0918-45-320 | CS | Actual | AUG 2005 | $1,164,366 | 5 | 5 INTERSECTION IMPROVEMENTS |
0918-45-323 | CS | Actual | AUG 2005 | $1,110,797 | 5 | 4 OFF SYSTEM INTERSECTION IMPROVEMENTS |
0918-45-324 | CS | Actual | NOV 2004 | $374,020 | 5 | 3 INTERSECTION IMPROVEMENTS |
0918-45-343 | CS | Actual | AUG 2005 | $454,111 | 5 | 1 OFF SYSTEM INTERSECTION IMPROVEMENTS |
0918-45-344 | CS | Actual | AUG 2005 | $2,131,713 | 5 | 7 OFF SYSTEM INTERSECTION IMPROVEMENTS |
0918-45-350 | CS | Actual | FEB 2005 | $116,280 | 5 | 2 OFF - SYSTEM INTERSECTION IMPROVEMENTS |
0918-45-355 | CS | Actual | AUG 2005 | $1,197,406 | 5 | 5 OFF SYSTEM INTERSECTION IMPROVEMENTS |
0918-45-397 | CS | Actual | AUG 2005 | $963,209 | 5 | 2 OFF SYSTEM INTERSECTION IMPROVEMENTS |
0918-45-486 | CS | Tentative | AUG 2005 | $1 | 5 | RIGHT OF WAY ACQUISITION, RELOCATION ASSISTANCE & UTILITY |
0918-45-528 | VA | Approved | AUG 2005 | $2,063,417 | 9 | BEAUTIFYING & HUMANIZING THE US 75 / DART RAIL GREENVILLE AVE |
0918-45-579 | VA | Actual | DEC 2004 | $7,584,617 | 7 | ROADWAY WIDENING TO ACCOMMODATE INCREASED TRUCK TRAFFIC WITH |
0918-45-628 | CS | Tentative | AUG 2005 | $1 | 5 | RIGHT OF WAY ACQUISITION |
0918-45-667 | VA | Approved | AUG 2005 | $620,172 | 5 | TRAFFIC CONTROL SYSTEM 31 LOCATIONS |
0918-45-673 | VA | Actual | AUG 2005 | $8,911,000 | 7 | CONSTRUCTION OF THE TXDOT DALLAS CENTRAL CONTROL CENTER |
0918-45-674 | VA | Actual | SEP 2004 | $20,452,240 | 5 | TRINITY RAILWAY EXPRESS DOUBLE TRACK AND GRADE SEPERATIONS; |
0918-45-694 | VA | Actual | APR 2005 | $500,000 | 5 | ALTERNATIVE FUELS |
0918-45-699 | CS | Actual | JUN 2005 | $82,615 | 9 | SIDEWALKS, SCHOOL ZONE FLASHERS, RAMPS RAIL, RETAINING WALL |
0918-45-750 | VA | Actual | APR 2005 | $3,154,760 | 1 | REPAIR OF CONCRETE AND PAVEMENT REPAIR |
0918-45-751 | VA | Actual | APR 2005 | $3,435,193 | 1 | REFLECTORIZED PAVEMENT MARKINGS |
0918-45-752 | VA | Actual | APR 2005 | $400,000 | 7 | EVALUATE IMPACTS OF RESTRICTING TRUCKS TO OPERATE ONLY IN |
0918-45-753 | VA | Actual | DEC 2004 | $1,500,000 | 1 | ABR TRANSFER FOR SWAO CONCRETE PAVEMENT REPAIR |
1047-02-042 | FM 1382 | Actual | DEC 2004 | $228,635 | 10 | LANDSCAPE DEVELOPMENT |
1068-04-133 | IH 30 | Actual | JAN 2005 | $41,735,764 | 1 | RECONSTRUCT FREEWAY AND OVERPASS AT LOOP 12 |
1068-04-135 | IH 30 | Actual | MAY 2005 | $755,000 | 1 | REPLACE WB EXIT RAMP RETAINING WALL |
2208-02-018 | SP 303 | Actual | SEP 2004 | $1,144,460 | 1 | REHABILITATION OF EXISTING ROADWAY |
2374-01-111 | IH 635 | Actual | OCT 2004 | $1,142,119 | 2 | 3 INTERSECTION IMPROVEMENTS |
2374-01-131 | IH 635 | Actual | AUG 2005 | $765,803 | 5 | ONE ON SYSTEM INTERSECTION IMPROVEMENT |
2374-01-132 | IH 635 | Actual | MAY 2005 | $635,839 | 1 | REHABILITATE VARIOUS DYNAMIC MESSAGE SIGNS ON IH 635 |
2374-01-154 | IH 635 | Actual | NOV 2004 | $3,088,045 | 5 | PHASE 1 OF HOV / ITS PROJECT: HIGH MAST ILLUMINATION |
2374-02-089 | IH 635 | Actual | AUG 2005 | $1,384,842 | 5 | 3 ON SYSTEM INTERSECTION IMPROVEMENTS |
2374-02-121 | IH 635 | Actual | OCT 2004 | $2,500 | 10 | WILDFLOWER SEEDING |
2374-03-064 | IH 20 | Actual | JUL 2005 | $14,939,000 | 7 | CONSTRUCT 2 LANE FRONTAGE ROADS EASTBOUND AND WESTBOUND |
2374-03-068 | IH 20 | Actual | JUL 2005 | $5,313,034 | 1 | FULL - DEPTH REPAIR, MILL & OVERLAY, CROSS - STITCHING & SURFACE |
2374-04-046 | IH 20 | Actual | MAY 2005 | $7,870,576 | 1 | REHAB OF EXISTING FREEWAY |
2374-04-058 | IH 20 | Actual | OCT 2004 | $3,606,395 | 5 | INSTALL SENSOR STATIONS WITH COMPRESSED CCTV CAMERAS, |
2964-01-029 | SH 161 | Actual | JUN 2005 | $43,132,516 | 2 | CONSTRUCT 6 LANE FRONTAGE ROAD SECTIONS (PHASE I) |
2964-01-030 | SH 161 | Actual | JUL 2005 | $24,960,709 | 2 | CONSTRUCT 6 LANE FRONTAGE ROAD SECTIONS (PHASE I) |
2964-01-034 | SH 161 | Actual | MAR 2005 | $9,432,432 | 2 | COURT MANDATED MITIGATION FOR PARKS IMPACTED BY SH 161 |
2964-01-035 | SH 161 | Actual | OCT 2004 | $5,182,590 | 1 | INSTALLATION / CONSTRUCTION OF CTB |
8043-18-005 | MH | Actual | JUL 2005 | $38,534,000 | 7 | RECONSTRUCT EXISTING 4 - LANE ROADWAY TO 6 - LANE DIVIDED |
8050-18-037 | MH | Actual | SEP 2004 | $5,708,080 | 2 | TRINITY RAILWAY EXPRESS DOUBLE TRACK AND GRADE SEPERATIONS; |
8050-18-042 | MH | Actual | FEB 2005 | $22,509,208 | 2 | RECONSTRUCT EXISTING 4 - LANE DIVIDED RURAL ROADWAY TO |
Denton County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0134-09-047 | US 380 | Actual | MAY 2005 | $4,257,000 | 6 | REPLACE BRIDGE AND APPROACHES |
0134-09-060 | US 380 | Actual | JUN 2005 | $1,696,828 | 1 | MILL / INLAY, OVERLAY |
0134-09-061 | US 380 | Actual | AUG 2005 | $195,602 | 1 | INTERSECTION IMPROVEMENTS |
0195-02-056 | US 77 | Actual | MAR 2005 | $299,984 | 10 | LANDSCAPE DEVELOPMENT |
0195-03-066 | IH 35E | Actual | AUG 2005 | $227,814 | 11 | INSTALL RIGHT TURN LANE |
0196-01-088 | IH 35E | Actual | JUL 2005 | $4,464,054 | 11 | WIDEN FROM 4 TO 6 MAINLANES |
0196-01-093 | IH 35E | Actual | NOV 2004 | $1,397,298 | 11 | REVERSE NORTHBOUND ENTRANCE AND EXIT RAMPS |
0196-02-094 | IH 35E | Actual | JAN 2005 | $918,543 | 7 | NB RAMP REVERSAL |
0196-02-102 | IH 35E | Actual | AUG 2005 | $149,942 | 7 | CONSTRUCT LEFT TURN LANE ON SB APPROADCH |
0718-01-048 | FM 156 | Actual | OCT 2004 | $159,403 | 1 | INSTALL FLASHING BEACONS, ACP OVERLAY FOR LEFT TURN BAY, |
0918-46-042 | CR | Actual | JAN 2005 | $683,204 | 6 | REPLACE BRIDGE AND APPROACHES |
0918-46-084 | CS | Actual | AUG 2005 | $989,604 | 5 | 3 OFF SYSTEM INTERSECTION IMPROVEMENTS |
0918-46-100 | CR | Actual | APR 2005 | $1,048,832 | 6 | REPLACE BRIDGE AND APPROACHES |
0918-46-101 | CR | Actual | OCT 2004 | $645,361 | 6 | REPLACE BRIDGE AND APPROACHES |
0918-46-128 | VA | Actual | JUN 2005 | $1,324,684 | 9 | CONSTRUCTION OF (PHASE I) OF HIGHLAND VILLAGE INLAND TRAIL |
0918-46-140 | CR | Actual | JAN 2005 | $403,932 | 6 | REPLACE BRIDGE AND APPROACHES |
0918-46-141 | CR | Actual | DEC 2004 | $437,736 | 6 | REPLACE BR & APPRS |
0918-46-144 | CS | Actual | JAN 2005 | $1,172,366 | 7 | CONSTRUCT 3 ADDITIONAL WESTBOUND MAINLANES TO COMPLETE |
0918-46-167 | CS | Actual | JUN 2005 | $437,052 | 6 | REPLACE BRIDGE AND APPROACHES |
0918-46-193 | CS | Actual | JUN 2005 | $1,068,823 | 7 | NEW CITY STREETS |
1311-01-044 | FM 1171 | Actual | APR 2005 | $30,080 | 10 | RAILROAD GRADE CROSSING REPLANKING |
2250-02-015 | LP 288 | Actual | SEP 2004 | $820,278 | 1 | INSTALL CTB & HEADLIGHT BARRIER FENCE TO PROVIDE SAFETY |
3547-01-010 | SH 121 | Actual | APR 2005 | $997,482 | 1 | FULL DEPTH REPAIR |
Ellis County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0092-04-067 | IH 45 | Actual | JUN 2005 | $8,116,816 | 1 | FRONTAGE ROAD PAVEMENT REPAIR |
0173-01-043 | SH 34 | Actual | FEB 2005 | $2,592,355 | 1 | CONSTRUCT CONTINUOUS LEFT - TURN LANE |
0596-02-031 | FM 66 | Actual | DEC 2004 | $2,092,415 | 6 | REPLACE BR & APPRS |
0596-02-032 | FM 66 | Actual | AUG 2005 | $717,495 | 6 | REPLACE BRIDGE AND APPROACHES |
0596-02-033 | FM 66 | Actual | AUG 2005 | $6,096,729 | 8 | ADD SHOULDERS AND GUARD FENCE, UPGRADE CULVERT AND BRIDGE |
0596-04-037 | FM 878 | Actual | AUG 2005 | $925,467 | 6 | REPLACE BRIDGE AND APPROACHES |
0918-22-070 | CS | Actual | FEB 2005 | $484,812 | 6 | REPLACE BRIDGE & APPROACHES |
0918-22-071 | CR | Actual | APR 2005 | $679,000 | 6 | REPLACE BRIDGE AND APPROACHES |
0918-22-072 | CR | Actual | FEB 2005 | $687,770 | 6 | REPLACE BRIDGE & APPROACHES |
0918-22-073 | CR | Actual | APR 2005 | $1,067,381 | 6 | REPLACE BRIDGE AND APPROACHES |
1048-02-027 | FM 660 | Actual | AUG 2005 | $1,041,603 | 6 | REPLACE BRIDGE AND APPROACHES |
1139-02-014 | FM 813 | Actual | MAY 2005 | $1,795,000 | 1 | REPLACE BRIDGE AND APPROACHES |
1211-01-016 | FM 984 | Actual | AUG 2005 | $605,560 | 6 | REPLACE BRIDGE AND APPROACHES |
1211-02-016 | FM 984 | Actual | APR 2005 | $22,135 | 10 | RAILROAD GRADE CROSSING REPLANKING |
Kaufman County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0095-04-050 | US 80 | Actual | SEP 2004 | $1,016,316 | 6 | WIDEN BRIDGES AND APPROACHES |
0197-12-004 | BU 175D | Actual | MAY 2005 | $711,112 | 1 | MILL AND OVERLAY |
0495-01-050 | IH 20 | Actual | MAR 2005 | $2,791,797 | 1 | RESTORATION OF IH 20 FOLLOWING EXPIRATION OF TOTAL MAINT |
0751-03-033 | FM 3094 | Actual | JUN 2005 | $578,377 | 1 | REPLACE BRIDGE AND APPROACHES |
0918-11-060 | VA | Actual | JUN 2005 | $4,666,649 | 1 | BASE REPAIR AND OVERLAY |
0918-11-061 | VA | Actual | JUN 2005 | $5,619,443 | 1 | BASE REPAIR AND OVERLAY |
0918-11-062 | VA | Actual | JUN 2005 | $989,376 | 1 | BRIDGE JOINT REPAIR |
1091-01-013 | FM 740 | Actual | MAR 2005 | $2,186,530 | 11 | RECONSTRUCT EXISTING 2 - LANE ROADWAY TO 4 - LANES |
1091-02-016 | FM 740 | Actual | APR 2005 | $30,080 | 10 | RAILROAD GRADE CROSSING REPLANKING |
3089-01-009 | FM 3039 | Actual | NOV 2004 | $896,831 | 1 | ADD TURN LANES |
Navarro County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0093-01-080 | IH 45 | Actual | SEP 2004 | $181,492 | 1 | SAFETY LIGHTING |
0093-01-082 | IH 45 | Actual | JUN 2005 | $1,557,091 | 8 | INSTALL WIRE FENCE IN MEDIAN |
0999-01-026 | FM 1394 | Actual | JUN 2005 | $6,948,164 | 1 | OV - ASPHALTIC CONCRETE PAVEMENT OVERLAY |
Rockwall County | ||||||
CCSJ | Highway | Let Status | Letting Date |
Contract Cost |
Fund Cat |
Description |
0009-04-057 | SH 66 | Actual | OCT 2004 | $161,538 | 10 | LANDSCAPE DEVELOPMENT |
0009-12-067 | IH 30 | Actual | JUN 2005 | $371,322 | 11 | ADD NEW EXIT RAMP |
|
|