Detail Letting Schedule for Washington County (FY 2005)
Detail Letting Schedule for Washington County (FY 2005) | ||||
Last Update: Monday, August 15, 2005 |
Washington County (FY 2005) |
CCSJ: 0114-09-063 | |||
District: | Bryan | Let Date: | SEP 2004 |
Highway: | US 290 | Let Status: | Actual |
Project ID: | NH 2004(673) | CSJ: | 0114-09-063 |
Description: | MISCELLANEOUS WORK CONSISTING OF REPLACING LARGE GUIDE SIGNS | Handling Code: |
|
Limits From: | 1.2 MI. W. OF SH 36N/US 290 INTERCH | Fund Cat: | 1 |
Limits To: | THE SH 36N/US 290 INTERCHANGE | Estimate: | $34,380 |
Length: | 1.3 Miles | Actual: | $29,732 |
District: | Bryan | Let Date: | SEP 2004 |
Highway: | US 290 | Let Status: | Actual |
Project ID: | NH 2004(673) | CSJ: | 0114-10-086 |
Description: | MISCELLANEOUS WORK CONSISTING OF REPLACING LARGE GUIDE SIGNS | Handling Code: |
|
Limits From: | FM 577 | Fund Cat: | 1 |
Limits To: | 1.O MILE EAST OF FM 577 | Estimate: | $12,545 |
Length: | 1.0 Miles | Actual: | $11,962 |
District: | Bryan | Let Date: | SEP 2004 |
Highway: | SH 36 | Let Status: | Actual |
Project ID: | NH 2004(673) | CSJ: | 0186-05-034 |
Description: | MISCELLANEOUS WORK CONSISTING OF REPLACING LARGE GUIDE SIGNS | Handling Code: |
|
Limits From: | 2.0 MILES NORTH OF BS 36-J INTERCHA | Fund Cat: | 1 |
Limits To: | THE BS 36-J INTERCHANGE | Estimate: | $9,928 |
Length: | 2.0 Miles | Actual: | $9,252 |
District: | Bryan | Let Date: | SEP 2004 |
Highway: | SH 36 | Let Status: | Actual |
Project ID: | NH 2004(673) | CSJ: | 0186-06-063 |
Description: | MISCELLANEOUS WORK CONSISTING OF REPLACING LARGE GUIDE SIGNS | Handling Code: |
|
Limits From: | THE BS 36-J INTERCHANGE | Fund Cat: | 1 |
Limits To: | THE SH 36N/US 290 INTERCHANGE | Estimate: | $30,262 |
Length: | 2.8 Miles | Actual: | $28,203 |
District: | Bryan | Let Date: | SEP 2004 |
Highway: | US 290 | Let Status: | Actual |
Project ID: | NH 2004(673) | CSJ: | 0186-06-064 |
Description: | MISCELLANEOUS WORK CONSISTING OF REPLACING LARGE GUIDE SIGNS | Handling Code: |
|
Limits From: | THE SH 36N/US 290 INTERCHANGE | Fund Cat: | 1 |
Limits To: | FM 577 | Estimate: | $56,591 |
Length: | 4.7 Miles | Actual: | $53,577 |
Back... |
Totals for 0114-09-063 | ||
---|---|---|---|
Length: | 11.8 Miles | ||
Estimate: | $143,706 | ||
Actual: | $132,726 | ||
CCSJ: 0315-06-030 | |||
District: | Bryan | Let Date: | DEC 2004 |
Highway: | SH 105 | Let Status: | Actual |
Project ID: | CPM 315-6-30 | CSJ: | 0315-06-030 |
Description: | OVERLAY CONSISTING OF A ONE COURSE SURFACE TREATMENT, AN HMA | Handling Code: |
|
Limits From: | FM 912 | Fund Cat: | 1 |
Limits To: | FM 1155 | Estimate: | $759,212 |
Length: | 4.5 Miles | Actual: | $836,649 |
Back... |
Totals for 0315-06-030 | ||
Length: | 4.5 Miles | ||
Estimate: | $759,212 | ||
Actual: | $836,649 | ||
CCSJ: 0917-19-039 | |||
District: | Bryan | Let Date: | JUN 2005 |
Highway: | VA | Let Status: | Actual |
Project ID: | STP 2002(115)TE | CSJ: | 0917-19-039 |
Description: | TRANSPORTATION ENHANCEMENT PROJECT TO CONSISTING OF HIKE AND | Handling Code: |
LN |
Limits From: | CITY OF BRENHAM GREENWAYS PROJECT | Fund Cat: | 9 |
Limits To: | . | Estimate: | $2,290,036 |
Length: | 0.0 Miles | Actual: | $1,456,836 |
Back... |
Totals for 0917-19-039 | ||
Length: | 0.0 Miles | ||
Estimate: | $2,290,036 | ||
Actual: | $1,456,836 |
|
|