Detail Letting Schedule for Wilson County (FY 2005)
|
Detail Letting Schedule for Wilson County (FY 2005) |
|
Last Update: Monday, August 15, 2005 |
CCSJ: 0100-03-069
|
District: |
San Antonio |
Let Date: |
DEC 2004 |
Highway: |
US 181 |
Let Status: |
Actual |
Project ID: |
CPM 100-2-56 |
CSJ: |
0100-02-056 |
Description: |
ULTRATHIN BONDED WEARING COURSE & PAVEMENT MARKINGS |
Handling Code: |
NC |
Limits From: |
LP 1604 |
Fund Cat: |
1 |
Limits To: |
BEXAR COUNTY LINE |
Estimate: |
$368,320 |
Length: |
1.4 Miles |
Actual: |
$443,654 |
|
District: |
San Antonio |
Let Date: |
DEC 2004 |
Highway: |
US 181 |
Let Status: |
Actual |
Project ID: |
CPM 100-3-69 |
CSJ: |
0100-03-069 |
Description: |
ULTRATHIN BONDED WEARING COURSE & PAVEMENT MARKINGS |
Handling Code: |
NC |
Limits From: |
BEXAR COUNTY LINE |
Fund Cat: |
1 |
Limits To: |
FM 537 |
Estimate: |
$2,748,637 |
Length: |
13.9 Miles |
Actual: |
$3,104,678 |
|
District: |
San Antonio |
Let Date: |
DEC 2004 |
Highway: |
FM 539 |
Let Status: |
Actual |
Project ID: |
CPM 2233-2-5 |
CSJ: |
2233-02-005 |
Description: |
OVERLAY & PAVEMENT MARKINGS |
Handling Code: |
NC |
Limits From: |
FM 467 |
Fund Cat: |
1 |
Limits To: |
WILSON COUNTY LINE |
Estimate: |
$486,412 |
Length: |
3.7 Miles |
Actual: |
$597,921 |
|
Back...
|
Totals for 0100-03-069 |
Length: |
19.0 Miles |
Estimate: |
$3,603,369 |
Actual: |
$4,146,253 |
Handling Code |
Definition |
XX |
Project not processed through statewide letting |
TR |
Transfer of funds |
LC |
Project let through local entity |
NC |
Project not charged against district apportionment |
Let Status |
Definition |
Tentative |
Estimated letting date for this project |
Approved |
Project has administrative approval to be let |
Actual |
Project was let to contract |
|