Detail Letting Schedule for Coryell County (FY 2007)

 
 
Last Update: Monday, August 6, 2007
Coryell County (FY 2007)

CCSJ: 0055-03-022

District: Waco Let Date: JUL 2007
Highway: US 84 Let Status: Actual
Project ID: STP 2007(679)HES CSJ: 0055-03-021
Description: UPGRADE GUARDRAIL AND SAFETY TREAT FIXED OBJECTS Handling
Code:
 
Limits From: FM 930 @ ARNETT Fund Cat: 8
Limits To: HAMILTON CO LN Estimate: $1,735,200
Length: 14.9 Miles Actual: $1,547,750
 
District: Waco Let Date: JUL 2007
Highway: US 84 Let Status: Actual
Project ID: STP 2006(770) CSJ: 0055-03-022
Description: REHAB ROADWAY, ADD PASSING LANES AND INTERSECTION Handling
Code:
 
Limits From: FM 930 Fund Cat: 1
Limits To: HAMILTON CO LINE Estimate: $7,500,932
Length: 14.9 Miles Actual: $7,501,376
 
District: Waco Let Date: JUL 2007
Highway: US 84 Let Status: Actual
Project ID: STP 2007(679)HES CSJ: 0055-04-025
Description: UPGRADE GUARDRAIL AND SAFETY TREAT FIXED OBJECTS Handling
Code:
 
Limits From: FM 116 IN GATESVILLE Fund Cat: 8
Limits To: FM 930 @ ARNETT Estimate: $684,150
Length: 7.1 Miles Actual: $536,250
 
District: Waco Let Date: JUL 2007
Highway: US 84 Let Status: Actual
Project ID: STP 2006(770) CSJ: 0055-04-026
Description: REHAB ROADWAY AND ADD PASSING LANES Handling
Code:
 
Limits From: FM 116 Fund Cat: 1
Limits To: FM 930 Estimate: $6,326,154
Length: 7.1 Miles Actual: $5,940,614
 
Bid Tabulations
Award Status
Back...

Totals for 0055-03-022
Length: 44.0 Miles
Estimate: $16,246,436
Actual: $15,525,990


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract