Letting Schedule for Fort Worth District (FY 2007)

 
 
Last Update: Friday, August 24, 2007
Fort Worth District (FY 2007)
Johnson | Tarrant

Johnson County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
1181-02-030 FM 917 Actual AUG 2007 $7,563,589 1 CONSTRUCT SAFETY TREAT & SHOULDERS
1181-03-027 FM 917 Actual AUG 2007 $5,353,690 1 GRADING, HOT MIX ASPHALT, DRAINAGE STRUCTURES, AND PAVEMENT

Tarrant County

CCSJ Highway Let Status Letting
Date
Contract
Cost
Fund
Cat
Description
0008-13-217 IH 820 Actual AUG 2007 $1,177,401 1 CONSTRUCT AUXILIARY LANE ON SOUTHBOUND IH 820 TO PROVIDE
0014-02-041 IH 35W Actual AUG 2007 $8,690,271 5 CONSTRUCT ADDITIONAL LANES ON BRIDGE OVER IH 35W, TURNAROUND
0172-02-066 BU 287P Actual AUG 2007 $101,000 10 INSTALLATION OF A FULL TRAFFIC ACTUATED TRAFFIC SIGNAL
0902-00-104 VA Actual AUG 2007 $1,512,102 1 EROSION & SCOUR MEASURES, RIPRAP REPAIR, DEBRIS REMOVAL &
0902-48-503 VA Actual AUG 2007 $1,194,189 5 OFF - SYSTEM ATMS
0902-48-690 VA Actual AUG 2007 $2,463,857 5 ITS DEPLOYMENT; IH 20 - HULEN TO IH 820; IH 820 - IH20 TO IH30;
1068-02-124 IH 30 Actual AUG 2007 143,880,367 2 WIDEN FROM 6 TO 8 LANES_ (TOLL)
2266-02-127 SH 360 Tentative AUG 2007 $60,240,913 2 RECONSTRUCT FREEWAY INTERCHANGE WITH SH 180 INCLUDING
3125-01-010 FM 3029 Actual AUG 2007 $9,873,767 7 RECONSTRUCT AND WIDEN FROM 5 TO 6 LANES WITH RAISED MEDIAN


Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract