Detail Letting Schedule for Motley County (FY 2007)
Detail Letting Schedule for Motley County (FY 2007) | ||||
Last Update: Monday, July 30, 2007 |
Motley County (FY 2007) |
CCSJ: 0704-06-011 | |||
District: | Childress | Let Date: | JUN 2007 |
Highway: | FS 94 | Let Status: | Actual |
Project ID: | STP 2007(606) | CSJ: | 0105-09-005 |
Description: | REHABILITATION OF ROADWAY | Handling Code: |
|
Limits From: | SH 70, E | Fund Cat: | 1 |
Limits To: | FM 94 | Estimate: | $224,533 |
Length: | 0.8 Miles | Actual: | $224,432 |
District: | Childress | Let Date: | JUN 2007 |
Highway: | FM 94 | Let Status: | Actual |
Project ID: | BR 2007(607) | CSJ: | 0704-06-008 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | @ MIDDLE PEASE RIVER | Fund Cat: | 11 |
Limits To: | . | Estimate: | $1,848,747 |
Length: | 0.7 Miles | Actual: | $2,327,608 |
District: | Childress | Let Date: | JUN 2007 |
Highway: | FM 94 | Let Status: | Actual |
Project ID: | STP 2007(606) | CSJ: | 0704-06-011 |
Description: | REHABILITATION OF ROADWAY | Handling Code: |
|
Limits From: | SPUR 94 | Fund Cat: | 1 |
Limits To: | SOUTH END OF THE MIDDLE PEASE RIVER | Estimate: | $2,862,372 |
Length: | 8.6 Miles | Actual: | $2,868,519 |
District: | Childress | Let Date: | JUN 2007 |
Highway: | FM 94 | Let Status: | Actual |
Project ID: | BR 2007(607) | CSJ: | 0704-06-014 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | @ LONG'S BRANCH CREEK | Fund Cat: | 6 |
Limits To: | . | Estimate: | $650,138 |
Length: | 0.1 Miles | Actual: | $897,786 |
District: | Childress | Let Date: | JUN 2007 |
Highway: | FM 1380 | Let Status: | Actual |
Project ID: | STP 2007(606) | CSJ: | 3428-01-002 |
Description: | REHAB | Handling Code: |
|
Limits From: | FM 94 | Fund Cat: | 1 |
Limits To: | US 62/70 | Estimate: | $257,156 |
Length: | 1.1 Miles | Actual: | $253,475 |
Bid Tabulations Back... |
Totals for 0704-06-011 | ||
---|---|---|---|
Length: | 11.3 Miles | ||
Estimate: | $5,842,946 | ||
Actual: | $6,571,820 |
|
|