Detail Letting Schedule for Camp County (FY 2012)

 
 
Last Update: Monday, September 24, 2012
Camp County (FY 2012)

CCSJ: 0083-08-047

District: Atlanta Let Date: DEC 2011
Highway: SH 11 Let Status: Actual
Project ID: CRX 83-8-47 CSJ: 0083-08-047
Description: RAILROAD GRADE CROSSING REPLANKING Handling
Code:
XX
Limits From: IN PITTSBURG AT KCS RAILROAD Fund Cat: 10
Limits To: DOT NO. 331521E Estimate: $1
Length: 0.0 Miles Actual: $79,200
 
Back...

Totals for 0083-08-047
Length: 0.0 Miles
Estimate: $1
Actual: $79,200

CCSJ: 0083-08-048

District: Atlanta Let Date: DEC 2011
Highway: SH 11 Let Status: Actual
Project ID: CRX 83-8-48 CSJ: 0083-08-048
Description: RAILRAOD GRADE CROSSING REPLANKING Handling
Code:
XX
Limits From: IN PITTSBURG AT UP RAILROAD Fund Cat: 10
Limits To: DOT NO. 789782X Estimate: $1
Length: 0.0 Miles Actual: $48,128
 
Back...

Totals for 0083-08-048
Length: 0.0 Miles
Estimate: $1
Actual: $48,128

CCSJ: 0248-02-061

District: Atlanta Let Date: DEC 2011
Highway: US 271 Let Status: Actual
Project ID: CRX 248-2-61 CSJ: 0248-02-061
Description: INSTALLATION OF CONCRETE PLANKING Handling
Code:
XX
Limits From: US 271 AT KCS RR NORTH OF SH 11 Fund Cat: 10
Limits To: DOT 331517P RRMP 248.20 Estimate: $79,200
Length: 0.0 Miles Actual: $79,200
 
Back...

Totals for 0248-02-061
Length: 0.0 Miles
Estimate: $79,200
Actual: $79,200

CCSJ: 1019-01-028

District: Atlanta Let Date: DEC 2011
Highway: FM 556 Let Status: Actual
Project ID: CRX 1019-1-28 CSJ: 1019-01-028
Description: RAILROAD GRADE CROSSING REPLANKING Handling
Code:
XX
Limits From: IN PITTSBURG AT UP RAILROAD Fund Cat: 10
Limits To: . Estimate: $1
Length: 0.0 Miles Actual: $90,240
 
Back...

Totals for 1019-01-028
Length: 0.0 Miles
Estimate: $1
Actual: $90,240


Handling Code Definition
XX Project not processed through statewide letting
TR Transfer of funds
LC Project let through local entity
NC Project not charged against district apportionment



Let Status Definition
Tentative Estimated letting date for this project
Approved Project has administrative approval to be let
Actual Project was let to contract